Kaman Aerospace Corp. v. Arizona Board of Regents

CourtCourt of Appeals of Arizona
DecidedAugust 23, 2007
Docket2 CA-CV 2006-0177
StatusPublished

This text of Kaman Aerospace Corp. v. Arizona Board of Regents (Kaman Aerospace Corp. v. Arizona Board of Regents) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kaman Aerospace Corp. v. Arizona Board of Regents, (Ark. Ct. App. 2007).

Opinion

FILED BY CLERK IN THE COURT OF APPEALS AUG 23 2007 STATE OF ARIZONA COURT OF APPEALS DIVISION TWO DIVISION TWO

KAMAN AEROSPACE ) CORPORATION, a Delaware ) 2 CA-CV 2006-0177 corporation, ) DEPARTMENT A ) Plaintiff/Counterdefendant/ ) OPINION Appellee/Cross-Appellant, ) ) v. ) ) THE ARIZONA BOARD OF REGENTS, ) UNIVERSITY OF ARIZONA, ) a political subdivision of the State of ) Arizona, ) ) Defendant/Counterclaimant/ ) Appellant/Cross-Appellee. ) )

APPEAL FROM THE SUPERIOR COURT OF PIMA COUNTY

Cause No. C20045114

Honorable Carmine Cornelio, Judge

REVERSED IN PART, AFFIRMED IN PART Fennemore Craig, P.C. By George O. Krauja and Erwin D. Kratz Tucson Attorneys for Plaintiff/Counterdefendant/ Appellee/Cross-Appellant

Lewis and Roca LLP By Brian J. Pollock, Lawrence A. Kasten, Phoenix and Dale A. Danneman Attorneys for Defendant/Counterclaimant/ Appellant/Cross-Appellee

B R A M M E R, Judge.

¶1 The Arizona Board of Regents (ABOR)1 appeals from a judgment entered after

a jury rendered its verdict in favor of Kaman Aerospace Corporation (Kaman) on ABOR’s

counterclaim for breach of contract and Kaman’s breach of contract claim, awarding Kaman

$0. ABOR asserts the trial court erred when it denied ABOR’s motions for judgment as a

matter of law on Kaman’s claim because there was no written agreement obligating it to

compensate Kaman for additional work and because Kaman had failed to prove an authorized

signatory had executed contract modifications on ABOR’s behalf. ABOR contends that

Kaman failed to prove the damages element of its claim and failed to establish that ABOR’s

breach was material. ABOR also argues Kaman’s breach of contract claim was untimely and

that the trial court erred in denying ABOR’s motions for a new trial on that claim and on the

1 At trial and on appeal, the parties and the trial court use the term “the University” interchangeably with “ABOR.”

2 jury’s verdict in Kaman’s favor on ABOR’s counterclaim for damages. Kaman cross-

appeals, asserting the court erred by not awarding it attorney fees as the prevailing party at

trial.

Factual and Procedural Background

¶2 We view “the evidence in a light most favorable to upholding the jury

verdict[s].” Hutcherson v. City of Phoenix, 192 Ariz. 51, ¶ 13, 961 P.2d 449, 451 (1998).

ABOR is the governing body of the University of Arizona; the astronomy department of the

University “has a research wing called Steward Observatory.” The observatory has a mirror

laboratory, “a unique facility in the world,” that makes large mirrors with “unique properties”

to exacting specifications. In March 2003, ABOR entered into a fixed price contract with

Lockheed Martin, effective September 2001, for ABOR to “[d]esign, develop, fabricate,

assemble, test, deliver, and support integration of a 6.5 [meter] class Collimator” for

approximately $32 million. A collimator was described at trial as “a telescope operating in

reverse”; it would be used to test the accuracy of space telescopes while they were still on

earth.

¶3 The mirror laboratory’s manager testified “the scope of the project was larger

than the observatory could handle alone during the time that Lockheed . . . wanted delivery.”

Accordingly, ABOR decided to partner with Kaman. ABOR was to provide the mirrors, and

Kaman would be responsible for providing support and control components of the collimator.

3 ¶4 Kaman and ABOR entered into a written contract on December 20, 2001. It

listed a “Firm Fixed Price” of $9,083,269 for the components Kaman was to provide. The

contract contained a statement of work (SOW)2 , which described various tasks Kaman was

expected to perform, and identified certain “billing milestones” when Kaman was to be

compensated for completing various tasks from March 2002 to May 2006. The SOW listed

three documents that provided its basis.

¶5 Paragraph four of the contract stated the “proposal reflects a fixed price for the

effort proposed. In the event that there is a modification to the work scope, a modified level

of effort will be indicated in a revised scope of work to be agreed upon by the parties at the

time of modification.” Part of paragraph two of the “terms and conditions of sale” attached

to the contract stated, “[a]fter acceptance by [Kaman] any change of specification/drawings

manufacturing process delivery schedule and/or quantity may be made only with [Kaman’s]

written consent and at a charge which [Kaman] shall determine reasonably sufficient to cover

its additional costs.”

¶6 Eleven modifications were entered into by the parties. Relevant here are

modifications two and four. Modification two, dated May 31, 2002, provided a new SOW,

now based on six documents, including the original three and “design guidelines” from the

University.

2 ABOR asserts, and Kaman does not dispute, that the “Statement of Work” describes the “work scope,” a term that is used in other parts of the contract.

4 ¶7 Modification number four, dated August 16, 2002, increased the total value of

the contract to $12,800,000. This modification included a new “terms and conditions of

sale,” with a revised paragraph two, that stated in part, “After acceptance by [Kaman] any

change of specification/drawings manufacturing process delivery schedule and/or quantity

may be made only with both parties’ written agreement and at a charge which [Kaman] and

[ABOR] shall determine reasonably sufficient to cover any additional costs.”

¶8 Mark Yokley, the program manager for Kaman, testified that when the parties

agreed to the May 2002 SOW, there were ten design guidelines in existence that formed the

basis of 222 requirements. Nearly two years later, when Kaman presented its claim to

ABOR, Yokley stated there had been forty-six revisions or additions to the design guidelines

leading to a total of seventeen design guidelines and 472 requirements, although only sixty-

three of the requirements were “really new.” Yokley testified twenty-three of the

requirements were more difficult to perform.

¶9 On December 18, 2003, Kaman gave ABOR a “very preliminary, rough”

estimate of what it claimed were additional costs in its “new scope and new/changed

requirements list.” This proposal listed twenty-eight “new requirement description[s]” and

an explanation for each charge, with a “total estimated price impact” of $3,821,400. In

January 2004, ABOR wrote a letter to Kaman, rejecting most of Kaman’s claims and stating

that “most derive from a failure by Kaman to perform to the statement of work and teaming

agreement.” Twenty-five of the twenty-eight claims were rejected with supporting rationale,

5 two were accepted “pending a full cost proposal,” and one was accepted and a new contract

was formed with respect to this item, a “dual-use collimator support structure study.”

¶10 Kaman then assembled a claim, presenting it to ABOR on April 5, 2004. This

claim listed twenty-nine separate items at a cost totalling approximately $6.25 million. Three

of the claims were accepted by ABOR “pending cost evaluation” with a fourth, the support

structure study, having already been accepted. The rest of the claims were rejected by

ABOR. In July 2004, Kaman filed a notice of claim through counsel pursuant to A.R.S.

§ 12-821.01 as to ABOR, stating its “claim can be settled for $6,250,110.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Crop Ins. Corp. v. Merrill
332 U.S. 380 (Supreme Court, 1947)
Bruce Church, Inc. v. United Farm Workers of America
816 P.2d 919 (Court of Appeals of Arizona, 1991)
City of Tempe v. Arizona Board of Regents
461 P.2d 503 (Court of Appeals of Arizona, 1969)
Porta House, Inc. v. Scottsdale Auto Lease, Inc.
584 P.2d 579 (Court of Appeals of Arizona, 1978)
Hutcherson v. City of Phoenix
961 P.2d 449 (Arizona Supreme Court, 1998)
Clay v. Arizona Interscholastic Ass'n
779 P.2d 349 (Arizona Supreme Court, 1989)
Henderson v. Las Cruces Production Credit Ass'n
435 P.2d 56 (Court of Appeals of Arizona, 1967)
General Cable Corp. v. Citizens Utilities Co.
555 P.2d 350 (Court of Appeals of Arizona, 1976)
Sanborn v. Brooker & Wake Property Management, Inc.
874 P.2d 982 (Court of Appeals of Arizona, 1994)
Godbey v. ROOSEVELT SCH. DIST. NO. 66, ETC.
638 P.2d 235 (Court of Appeals of Arizona, 1981)
Peck v. Board of Education of Yuma Union High School District
612 P.2d 1076 (Court of Appeals of Arizona, 1980)
Monaco v. HealthPartners of Southern Arizona
995 P.2d 735 (Court of Appeals of Arizona, 1999)
Civil Service Commission v. Foley
257 P.2d 384 (Arizona Supreme Court, 1953)
Orme School v. Reeves
802 P.2d 1000 (Arizona Supreme Court, 1990)
School District No. One of Pima County v. Lohr
498 P.2d 512 (Court of Appeals of Arizona, 1972)
Coldwell Banker Commercial Group, Inc. v. Camelback Office Park
751 P.2d 542 (Arizona Supreme Court, 1988)
Coldwell Banker Commercial Group, Inc. v. Camelback Office Park
751 P.2d 530 (Court of Appeals of Arizona, 1987)
Silva v. De Mund
299 P.2d 638 (Arizona Supreme Court, 1956)
Kondos v. West Virginia Board of Regents
318 F. Supp. 394 (S.D. West Virginia, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
Kaman Aerospace Corp. v. Arizona Board of Regents, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kaman-aerospace-corp-v-arizona-board-of-regents-arizctapp-2007.