Joyner v. Dumas Arkansas, City of

District Court, E.D. Arkansas·Decided August 2, 2024·No. 2:22-cv-00062·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT EASTERN DISTRICT OF ARKANSAS DELTA DIVISION

ROSCOE JOYNER d/b/a Joyner Construction Company PLAINTIFF

v. No. 2:22-cv-62-DPM

CITY OF DUMAS, ARKANSAS DEFENDANT

ORDER Roscoe Joyner, a black man, has been a construction contractor in Dumas, Arkansas for nearly forty years. He has won construction jobs from the City of Dumas, its agencies, and other public entities in and around Desha County “many dozens of times.” Doc. 40 at 1. In January 2022, the city rejected Joyner’s bid to clear some land. He believes his race was the reason. He has sued the city, pressing various federal and state law claims. The city moves for summary judgment. Many of the material facts are undisputed. Where there is a dispute, the Court takes the record in the light most favorable to Joyner. Oglesby v. Lesan, 929 F.3d 526, 531-32 (8th Cir. 2019). When Arkansas cities wish to spend more than thirty-five thousand dollars, they must generally do so through a competitive bidding process. ARK. CODE ANN. § 14-58-303(b)(2)(A) (West 2021) (effective 28 July 2021 to 31 July 2023). The mayor solicits bids by

advertising in a local newspaper; interested parties submit bids; and the bids received are opened on a set date in the mayor’s presence. After opening the bids, the mayor has two choices: “award the bid to the lowest responsible bidder,” or “reject any and all bids received.” Ibid. This case is about competitive bidding for a Dumas project. The relevant events happened between late 2021 and early 2022, when the city sought bids to construct a new maintenance building. Construction was to begin around March or April 2022. But the building site—a thirty-acre tract of land—needed to be cleared first. In October 2021, the city council authorized then-Mayor Flora Simon to advertise for land-clearing _ bids. Three months later, on 11 January 2022, she did. sy Ct i City of Dumas is accepting bids for the cleaning of all of the old Dollar General Warehouse property located on Hwy 54 West. The deadline for the bids is January 21, 2022. In the bid, include in addition to the cost the approximate time frame to have the property cleared. Bids are to be mailed to the attention of Mayor Flora Simon, P O Box 157, Dumas, AR 71639, or can be hand delivered to Dumas City Hall, 155 East Waterman Street. Doc. 23-1 at 8. This ad ran twice in three local newspapers. Only two companies submitted bids: Pat Clark Trucking Company and Richard

-2-

Pambianchi Construction Company, LLC. Joyner missed the deadline. The reasons, he says, were the ten-day submission window and an inability to get a bid packet from the mayor’s office. Mayor Simon reviewed the bids two or three days after the January 21st deadline. Both were based on the costs needed to clear all thirty acres. They were pricier than she expected. The mayor wrote a memo to the city council’s maintenance building committee on January 24th. In it, she suggested that the bidding period be re-opened and the project’s scope be narrowed to clear only “the area that is a must for the building.” Doc. 23-1 at 28. The rest could be cleared later. The next day, the committee met and adopted the mayor’s suggestions. To save money and time, the committee cut the project’s scope from clearing all thirty acres to only two; extended the bid-submission deadline to January 31st; and asked the two first-round bidders to revise their bids. The mayor did not publish an invitation for second-round bids. But Joyner caught wind of the changes and requested a bid packet from the street department. They gave him one —redacted copies of the original two bids. The full city council held a special meeting to discuss the second-round bids on January 31st. Clark and Pambianchi had already submitted revised bids. The street department’s superintendent called Joyner two hours before the meeting because he “hadn’t turned [his bid packet] back in.” Doc. 23-1 at 15. Joyner attended the meeting and

-3-

submitted a bid from his sole proprietorship, Joyner Construction. The city considered it along with the two revised bids. These were the three second-round bids. e □□□□□□□□□□□□□□□□□□□□□□□□□□ Total costs of $235,000 to clear the two acres, but no time estimate; e Pambianchi........... Daily costs of $7,260 to clear all thirty acres, but no time estimate; and e Joynert..................... Total costs of $135,000 to clear the two acres with a six-week time estimate. Doc. 23-1 at 46-49. The bulk of the parties’ dispute centers around Pambianchi’s second-round bid. It didn’t include a total cost estimate; it only provided daily costs with no timeline. During the meeting, □ Councilman Roy Dalton told the council that he had spoken to Pambianchi. Doc. 28 at 0:13:36-0:14:22 (Meeting Audio). He said Pambianchi could do the job in “fifteen to twenty” days, but that he would not use “the skidder steer with the hammer and the dozer” every day. Ibid. The council members calculated Pambianchi’s daily costs for using every piece of equipment to be $7,260/day. Doc. 28 at 0:18:47- 0:19:05. They then multiplied that number by twenty days and arrived at a high-end cost of $145,800. Doc. 28 at 0:19:07-0:19:57. But they determined that, if Pambianchi used the skidder and the dozer half the time, his total would be $130,200. Doc. 28 at 0:20:04-0:20:14. The city

-4-

council determined that Pambianchi was the lowest bidder: $130,200 for all thirty acres in fifteen to twenty days. It awarded him the contract. Doc. 28 at 0:28:04-0:30:35. Pambianchi ultimately cleared all thirty acres for less than $130,000, although he didn’t finish until several months later.

Joyner brings claims under 42 U.S.C. § 1983 and the Arkansas Civil Rights Act for procedural due process violations and for race discrimination in violation of 42 U.S.C. § 1981. He also claims an illegal exaction under state law. The city defends the legitimacy of its bidding process. But first, it challenges Joyner’s standing to bring the case. The standing/ capacity issues drop out of the case. The record is now clear. No Joyner-related LLC or corporation was involved in the bid. It was just Mr. Joyner, doing business as Joyner Construction Company. He has both standing and capacity to press the claims made. L & H Sanitation, Inc. v. Lake City Sanitation, Inc., 769 F.2d 517, 524 (8th Cir. 1985) (standing); Certain Underwriters at Lloyd's, London v. Bass, 2015 Ark. 178, at 12, 461 S.W.3d 317, 324-25 (capacity). Procedural Due Process. Joyner contends he was the true lowest bidder and that the city tinkered with Pambianchi’s numbers to undercut his bid. He claims the city violated his due process property rights in the land-clearing contract. He attacks the procedure used to deny him the contract, not the substance of what the city did. Compare

-5-

L & H Sanitation, 769 F.2d at 523. The threshold issue is whether he had, as a matter of Arkansas law, a property interest in the contract. “Arkansas statutes create a property interest in a competitively bid public contract for the lowest bidder that complied with the bidding specifications and procedures.” Harris v. Hays, 452 F.3d 714, 719 (8th Cir. 2006). But the Arkansas Supreme Court has made clear that “lowest” doesn’t necessarily mean the “lowest monetary bidder.” Conway Corp. v. Construction Engineers, Inc., 300 Ark. 225, 229,

Joyner v. Dumas Arkansas, City of, (E.D. Ark. 2024).

Joyner v. Dumas Arkansas, City of (Joyner v. Dumas Arkansas, City of) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

FREVERT v. Ford Motor Co.
614 F.3d 466 (Eighth Circuit, 2010)
L & H Sanitation, Inc. v. Lake City Sanitation, Inc.
769 F.2d 517 (Eighth Circuit, 1985)
Harris v. Hays
452 F.3d 714 (Eighth Circuit, 2006)
Conway Corp. v. Construction Engineers, Inc.
782 S.W.2d 36 (Supreme Court of Arkansas, 1989)
Certain Underwriters at Lloyd's, London v. Bass
2015 Ark. 178 (Supreme Court of Arkansas, 2015)
Robert Oglesby v. Amy Lesan
929 F.3d 526 (Eighth Circuit, 2019)
Jennifer Paskert v. Brent Burns
950 F.3d 535 (Eighth Circuit, 2020)
Worth James Construction Co. v. Jacksonville Water Commission
590 S.W.2d 256 (Supreme Court of Arkansas, 1979)