Joseph v. Hess Oil Virgin Islands Corp.

54 V.I. 657, 2011 WL 1304611, 2011 V.I. Supreme LEXIS 8
CourtSupreme Court of The Virgin Islands
DecidedMarch 8, 2011
DocketS. Ct. Civ. No. 2009-0054
StatusPublished
Cited by20 cases

This text of 54 V.I. 657 (Joseph v. Hess Oil Virgin Islands Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of The Virgin Islands primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph v. Hess Oil Virgin Islands Corp., 54 V.I. 657, 2011 WL 1304611, 2011 V.I. Supreme LEXIS 8 (virginislands 2011).

Opinion

OPINION OF THE COURT

(March 8, 2011)

CABRET, J.

Pierre Paul Joseph injured his back while working as a laborer for United Dominion Construction, Inc. (“UDCI”) at Hess Oil Virgin Islands Corporation’s (“HOVIC”) oil refinery on St. Croix. Joseph sued HOVIC, alleging that his injury was caused by HOVIC’s negligence in failing to provide him with the proper equipment to safely perform his job. HOVIC moved for summary judgment, asserting that it was not liable because UDCI was an independent contractor that decided which equipment Joseph used. The motion remained pending in the Superior [659]*659Court for approximately eight years before the court granted summary judgment to HOVIC. Joseph filed this appeal asserting that the Superior Court erred in making credibility determinations and in not resolving all inferences in his favor. For the reasons that follow, the Superior Court’s grant of summary judgment to HOVIC will be reversed.

I. FACTS AND PROCEDURAL BACKGROUND

The record shows that when Joseph was injured, he was working for UDCI at HOVIC’s oil refinery on St. Croix. At the time, HOVIC had contracted with UDCI to construct a fluid catalytic cracking unit at HOVIC’s existing refinery. The contract between HOVIC and UDCI expressly designated UDCI as an “independent contractor” (J.A. 79) and generally required UDCI to provide all construction management and labor for the project. The contract further required UDCI to maintain control over the hiring and discharging of its employees, the designation of work hours, the classification of work for each employee, and to perform all work in accordance with OSHA standards.

However, even under the contract terms, UDCI was not in complete control of the work it performed at the refinery. The contract required UDCI to complete the work in accordance with “HOVIC’s personnel and safety regulations which HOVIC has established for contractors performing work on its premises.” (J.A. 79-80.) In addition, if HOVIC “disagree[d] with [UDCI’s] method of execution of the Work,” HOVIC could “advise [UDCI] in writing and both parties . . . [were obligated to] use their best efforts to resolve the dispute.” (J.A. 79.) Under the contract, HOVIC provided all the engineering drawings, specifications, and “[a]ll construction equipment, construction tools and supplies as required by UDCI in writing.” (J.A. 87.) And, pursuant to the contract, HOVIC designated a “construction manager with whom [UDCI could] consult at all regular work hours.” (J.A. 86.)

The injury which provided the basis for the underlying civil action occurred on April 29, 1993, while UDCI was performing construction services under the contract. On that morning, Joseph reported to his immediate supervisor, a UDCI employee, who told him and another UDCI laborer to report to the general foreman, also a UDCI employee, for their job assignment. The general foreman instructed Joseph and the other employee to resume digging a hole that they had been excavating the previous day. Because there were electrical wires buried in the area, [660]*660Joseph was using a shovel to dig the hole. About one hour after they started digging that day, Joseph’s back started to hurt. When he could no 'longer continue digging, Joseph went to his supervisor and told the supervisor he needed to see the nurse about his back injury.

Joseph ultimately had surgery on his back, and on April 12, 1995, he sued HOVIC alleging that his

injuries were a direct result of the negligent supervision by HOVIC of the workplace by conduct including, but not limited to: (a) failing to provide proper tools to dig the holes; (b) refusing to allow the use of a forklift; which would have saved Plaintiff from injury; [and] (c) failing to properly supervise the worksite, knowing that manual labor would be required in the place of a forklift.

(J.A. 29-30.) (Paragraph indentions omitted).

In February of 2000, HOVIC moved for summary judgment on the ground that it was not liable for Joseph’s injuries because his employer, UDCI, was an independent contractor, and HOVIC played no part in supervising Joseph or in deciding which tools he would use in performing his work. In support of its motion, HOVIC pointed to the contract terms which designated UDCI as an independent contractor and which required UDCI to manage the construction. HOVIC also relied on deposition testimony showing that UDCI, not HOVIC, actually controlled and supervised all aspects of Joseph’s work, including the selection of tools to be used in completing the work.

Specifically, HOVIC pointed out that, in his deposition, Joseph testified that when he arrived at work on the day of his injury, he first reported to his supervisor, a UDCI employee. The supervisor instructed Joseph to report to the general foreman, also a UDCI employee, for his job assignment, and the general foreman instructed Joseph to resume digging the hole he had been working in the previous day. According to Joseph, he and his co-worker, John Liburd, then went to UDCI’s onsite warehouse to obtain shovels for their work. Joseph testified that they used shovels to dig, instead of machines,

because they have [underground wire, that’s the reason they don’t send the machine to do it. Tell the men have to do it by the hand. If the machine do it, it could cause the factory to blow up .... They don’t know which part the underground wire is. When we was digging, sometime we get one wire, [sic]

[661]*661(J.A. 303.) When Joseph was asked who decided which type of shovel they would use, he testified: “Me and Liburd decide that... because we had no other choice. They don’t give us nothing so we had to do. [sic]” (J.A. 301-02.) After obtaining the shovels, Joseph and Liburd resumed digging the hole they had been working on the previous day. According to Joseph, the general foreman “always” monitored his work to ensure he was doing it correctly (J.A. 303), and he did not see any HOVIC employees around his work site on that day. Later in his deposition, however, Joseph stated that during the “weeks and months” that he was digging holes, he would see HOVIC supervisors passing by his work site. (J.A. 306.)

Based on this evidence and the deposition testimony of another HOVIC representative who testified that the tool and equipment warehouse “was under the control and management of the UDCI personnel,” (J.A. 106) HOVIC argued that there was no genuine issue as to who controlled the decisions regarding Joseph’s work assignment and the tools he used.

In response to HOVIC’s evidence, Joseph pointed to evidence in the record which, he asserted, showed that HOVIC retained significant control over Joseph’s work, including the decision of which tools he used to perform his job.1 In an affidavit from Leo Ashe, Joseph’s foreman on the day he was injured, Ashe spoke about the control that HOVIC exerted over UDCI’s work:

On a daily basis, the general foreman of our crew... would meet with the Hess people to get a Hess permit that would tell us what work we were allowed to do that day. If the Hess permit did not specify the work then, even if UDCI told us to do it, we could not because it was not permitted by Hess. During the day, we would then follow the work Hess told us to do by the Hess permit____If Hess did not approve the use of equipment on the job, then we could not get the equipment____
[662]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grant v. Witt O'Brien, LLC
Virgin Islands, 2021
Edward v. Genoa Inc.
67 V.I. 210 (Superior Court of The Virgin Islands, 2017)
Coastal Air Transport v. Royer
64 V.I. 645 (Supreme Court of The Virgin Islands, 2016)
Tutein v. Ford Motor Co.
67 V.I. 34 (Superior Court of The Virgin Islands, 2016)
Der Weer v. Hess Oil Virgin Islands Corp.
64 V.I. 107 (Superior Court of The Virgin Islands, 2016)
Antilles School, Inc. v. Lembach
64 V.I. 400 (Supreme Court of The Virgin Islands, 2016)
Brouillard v. DLJ Mortgage Capital, Inc.
63 V.I. 788 (Supreme Court of The Virgin Islands, 2015)
Anduze v. Leader
63 V.I. 347 (Superior Court of The Virgin Islands, 2015)
Donastorg v. Daily News Publishing Co.
63 V.I. 196 (Superior Court of The Virgin Islands, 2015)
Cifre v. Daas Enterprises, Inc.
62 V.I. 338 (Superior Court of The Virgin Islands, 2015)
Hodge v. Virgin Islands Telephone Corp.
60 V.I. 105 (Superior Court of The Virgin Islands, 2014)
Palisoc v. Poblete
60 V.I. 607 (Supreme Court of The Virgin Islands, 2014)
Marsh-Monsanto v. St. Thomas-St. John Board of Elections
60 V.I. 41 (Superior Court of The Virgin Islands, 2014)
Virgin Islands Taxi Ass'n v. Virgin Islands Port Authority
59 V.I. 148 (Superior Court of The Virgin Islands, 2013)
Pollara v. Chateau St. Croix, LLC
58 V.I. 455 (Supreme Court of The Virgin Islands, 2013)
Balbo Corp. v. Enighed Condominiums, LLC
58 V.I. 93 (Superior Court of The Virgin Islands, 2013)
Joseph v. Daily News Publishing Co.
57 V.I. 566 (Supreme Court of The Virgin Islands, 2012)
Brodhurst v. Frazier
57 V.I. 365 (Supreme Court of The Virgin Islands, 2012)
United Corp. v. Tutu Park Ltd.
55 V.I. 702 (Supreme Court of The Virgin Islands, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
54 V.I. 657, 2011 WL 1304611, 2011 V.I. Supreme LEXIS 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-v-hess-oil-virgin-islands-corp-virginislands-2011.