Joseph Lande & Son, Inc. v. Wellsco Realty, Inc.

34 A.2d 418, 131 N.J.L. 191, 1943 N.J. LEXIS 301
CourtSupreme Court of New Jersey
DecidedNovember 4, 1943
StatusPublished
Cited by15 cases

This text of 34 A.2d 418 (Joseph Lande & Son, Inc. v. Wellsco Realty, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph Lande & Son, Inc. v. Wellsco Realty, Inc., 34 A.2d 418, 131 N.J.L. 191, 1943 N.J. LEXIS 301 (N.J. 1943).

Opinion

The opinion of the court was delivered by

Heher, J.

The complaint is in four counts, only two of which are Involved in this appeal. The trial judge directed a verdict for plaintiff on the third count and a verdict for *192 defendant on the fourth count. These rulings constitute the subject-matter of the cross-appeals.

By the third count, a subcontractor pleads a cause of action against the owner on a stop-notice served and filed on Oeto'ber 14th, 1941, under R. S. 2:60-116; 2:60-118. The defendant owner interposed, inter alia, the plea of nil debet; and one of the questions mooted at the trial was whether the owner had made advance payments for which it was liable under R. S. 2:6 0-124. The trial judge resolved it in the affirmative as a matter of law and therefore directed a verdict for plaintiff; and therein he fell into error.

The principal contract was made on May 29th, 1941. It provided for the construction of four duplex houses (eight families) and attached garages for the defendant owner on or before the ensuing September 1st. It was filed on June 2d, 1941, pursuant to section 2:60-115. The contract price was $30,000, subject to an allowance of $5,064 for certain materials and equipment to be supplied by the owner. There was a provision for “progress pajonents.” The owner undertook to pay the contract price as follows: “On or about the 1st and 15th day of each month 85 per cent, of-the value, based on the contract prices, of labor and materials incorporated in the wdrk and of materials suitably stored at the site thereof up to that day of that month, as estimated by the architect, less the aggegrate of previous payments; and upon Substantial completion of the entire work, a sum sufficient to increase the total payments to 85 per cent, of the contract price. Final payment shall be due 30 days after substantial completion of the work provided .the work be then fully completed and the contract fully performed.”

By contract with the general contractor, plaintiff agreed to install the heating units for $2,160. It maintains that it fully performed the subcontract; and it seeks the recovery of $1,660, the balance of the contract price remaining unpaid.

The general contractor discontinued work before full performance of its contract; and the buildings were completed by another contractor engaged by the owner. The proofs established that the moneys paid to the general contractor, and for completion after its default, are in excess of the con *193 t fact price; and the question is whether there were payments to the general contractor “in advance of the terms” of the contract.

Evidence was adduced tending to show that about 80 per cent, of the work provided for in the main contract had been done when the general contractor 'abandoned the contract; and it was the trial judge’s view that, since the owner had made payments in excess of 80 per cent, of the contract price, less the retained percentage, there were advance payments for which it was debarred from credit in this action under sections 2:60-119 and 2:60-124, supra. Plaintiff’s contention is that, at the time of the service and filing of the stop-notice, the general contractor was entitled to but 80 per cent, of the contract price, less the retained percentage of 15 per cent., or the net sum of $16,956.48, thus making an overpayment more than sufficient to cover its claim. The owner proved by its architect and other witnesses that payments were in fact made on the basis of 85 per cent, of the cost of labor and materials; and this testimony stood uncontroverted.

films, the question is one of construction and intent as manifested in the contract. Is it the fair purport of the forms used that the installment payments should have been made on the basis of percentage of the whole work completed? AVe find no such intendment. As was true of the contract considered in the case of Post v. Geldziler, 105 N. J. L. 370, nothing was said about “percentage of completion.” In that case, it was provided that no payments should he made “for more than 85 per cent, of the work completed, materials furnished and actually installed in the building;” and this court declared that “if the contractor agrees to a lump sum on a losing basis, he may still, under this clause, legitimately obtain certificates for eighty-five per cent, of fair cost of work done and materials furnished, and exhaust the contract price before the work is completed.” The clause was construed to have reference to the “cost of the work” done, irrespective of the relation of the work done to the entire undertaking.

But it is said in opposition that the contract in the ease at hand provides for payments of “85 per cent, of the value, *194 based on the contract prices, * * * as estimated by the architect,” and “upon substantial completion of the entire work, a sum sufficient to increase the total payments to 85 per cent, of the contract price/3 and that thereby “the 85 per cent, payments are tied in directly and specifically to the contract price,” and therefore the case of Post v. Geldziler, supra, is not apposite. But we think the case at bar is stronger for the owner than was the cited case. There, the clause read: “* * * 85 per cent, of the work completed, materials furnished and actually installed in the building.” Here, the term “contract prices” is in the ¡dural and plainly has reference to the price to the contractor of labor performed and materials furnished in the work done rather than the whole contract price. Moreover, the price of “materials suitably stored at the site” of the construction work is also to be considered. The last clause thus cited by respondent evidently refers only to the final payment, if the contract price is not exhausted before full performance of the contract, and it does not thereby become inoperative. The language employed is obviously not appropriate to the indubitable expression of a purpose to render installment payments on the basis of “percentage of completion.” There was no evidence, in aid of interpretation, of the customary practice under such a clause. The engineer who acted as inspector of the construction work, on behalf of a bank which had loaned money on the project, testified that he “estimated the value of the work completed and its relation to the entire job,” but he later said he considered “the value of the work done” and that the whole contract price did not enter into his calculations.

Thus, the ruling of the trial judge on the third count was based upon a misconception of the contract, and so was erroneous.

In this view, we have no occasion to determine whether the sum claimed in the stop-notice was in excess of the amount actually due, and the stop-notice was therefore void-.

And we are of opinion that the trial judge erred in directing a verdict for defendant on the fourth count. The evidence adduced in relation to the cause therein pleaded raised a factual issue.

*195

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oscar v. Simeonidis
800 A.2d 271 (New Jersey Superior Court App Division, 2002)
Duffy v. Charles Schwab & Co., Inc.
123 F. Supp. 2d 802 (D. New Jersey, 2000)
Patterson v. Katt
791 S.W.2d 466 (Missouri Court of Appeals, 1990)
Gronlund v. Church & Dwight Co., Inc.
514 F. Supp. 1304 (S.D. New York, 1981)
Drew Brown Limited v. Joseph Rugo, Inc.
436 F.2d 632 (First Circuit, 1971)
Schindeler v. Seldin Construction Co.
28 Fla. Supp. 172 (Miami-Dade County Circuit Court, 1967)
Summer v. Fabregas
145 A.2d 659 (New Jersey Superior Court App Division, 1958)
Anthony v. Jersey Central Power & Light Co.
143 A.2d 762 (New Jersey Superior Court App Division, 1958)
Ross v. Realty Abstract Co.
141 A.2d 319 (New Jersey Superior Court App Division, 1958)
Massey v. Del-Valley Corp.
134 A.2d 802 (New Jersey Superior Court App Division, 1957)
Tumarkin v. Goldstein
109 A.2d 435 (New Jersey Superior Court App Division, 1954)
The CITY NAT. BANK & TRUST CO. OF SALEM v. Hassler
75 A.2d 546 (New Jersey Superior Court App Division, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
34 A.2d 418, 131 N.J.L. 191, 1943 N.J. LEXIS 301, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-lande-son-inc-v-wellsco-realty-inc-nj-1943.