Joseph L. DeClerk & Associates, Inc. v. United States

38 Cont. Cas. Fed. 76,312, 26 Cl. Ct. 35, 1992 U.S. Claims LEXIS 176, 1992 WL 82015
CourtUnited States Court of Claims
DecidedApril 22, 1992
DocketNo. 649-88C
StatusPublished
Cited by10 cases

This text of 38 Cont. Cas. Fed. 76,312 (Joseph L. DeClerk & Associates, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph L. DeClerk & Associates, Inc. v. United States, 38 Cont. Cas. Fed. 76,312, 26 Cl. Ct. 35, 1992 U.S. Claims LEXIS 176, 1992 WL 82015 (cc 1992).

Opinion

OPINION

HORN, Judge.

Plaintiff, Joseph L. DeClerk and Associates, Inc. (JDC), seeks judgment against the defendant, the United States, to recover the bid preparation costs it incurred in responding to a government solicitation for the fielding of a Single Channel Ground and Airborne Radio System (“SINCGARS”), as well as lawful interest, and reasonable attorney’s fees. Plaintiff alleges that the defendant breached its contractual duty to judge fairly all bids submitted in response to the solicitation for bids, and that an implied contract existed between plaintiff and defendant. Plaintiff further alleges that the defendant violated the Competition in Contracting Act of 1984, 41 U.S.C. § 253 (1988), by certain actions, inactions and misrepresentations, which, according to the plaintiff, resulted in the arbitrary and capricious award of the contract to a party other than the plaintiff.

During the trial, at the close of the plaintiff’s case, but prior to the presentation' of the defendant’s case, the defendant made a Motion to Dismiss, pursuant to former Rule 41(b) of the Rules of the United States Claims Court (RUSCC),1 on the grounds that the plaintiff had shown no right to relief upon the facts and law, as presented at trial. Based on a review of the submissions of the parties, the evidence presented during the plaintiff’s case at trial, and a review of the relevant facts and legal precedent, the court granted the defendant’s motion. Upon request, the court has reduced its oral Opinion to writing below.

BACKGROUND

Plaintiff is a New Jersey Corporation, which engages in business related to engineering, computer and fielding services for government and private entities.2

On May 29, 1985, the United States Army Communications-Electronics Command (“CECOM”), Fort Monmouth, New Jersey, issued Solicitation No. DAAB0785-R-K040 (Solicitation K-040). Contract DAAB07-86-CR005 was ultimately awarded. At first, Solicitation K-040 called for a twelve month contractor effort to field the SINCGARS, with an option for six additional months of work related to the same task. The performance period subsequently was changed to an eleven month base period, with a twelve month option period. The procurement was specifically designated as a one-hundred percent set-aside for small business. Solicitation K-040 directed interested parties to submit their proposals on or before July 1, 1985. Modification No. 0003 to Solicitation K-040 notified interested contractors that the closing date for proposals was extended to July 8, 1985.

The government solicited offers from fifty-three contractors. Three contractors responded in a timely manner by the July 8, 1985 deadline: the plaintiff, Joseph L. DeClerk & Associates, Inc., Nations, Inc. and Eagle Technology, Inc.

The proposers under Solicitation K-040 were asked to address the base effort and [38]*38the option effort. According to the Joint Stipulation of Facts submitted by the parties, selection was to be based upon the best overall proposal, with consideration given to technical, cost and management factors. Technical factors were to be given greater weight than the other two factors combined. The announced point system under which the proposals were evaluated had a potential total of 100 points, distributed as follows:

1. Technical (65 points)
(1) Technical approach (35 points)
(a) Feasibility of approach (20 points)
(b) Understanding of problems (10 points)
(c) Completeness (5 points)
(2) Personnel (15 points)
(3) Material and facilities (5 points)
(4) Technical man-hours (10 points)
2. Cost (25 points)
(1) Cost Proposal (15 points)
(2) Cost Realism (10 points)
3. Management (10 points)
(1) Past Performance (10 points)

Technical evaluations were performed by the Source Selection Evaluation Board (SSEB), which was chaired by Lieutenant Colonel John A. Reid of the Readiness Directorate of CECOM. Cost evaluations were performed by the Procurement Branch of CECOM.

The Procurement Branch of CECOM was notified on August 2, 1985 that the initial technical evaluations of the three proposals were complete and submitted by the SSEB. Plaintiff, DeClerk, at first received an overall “susceptible” rating. Eagle received an overall “acceptable” rating. Nations received an overall “superior” rating. On the seven categories evaluated and rated, plaintiff received three “acceptable” ratings, three “susceptible” ratings and one “unacceptable” rating. The initial ratings of the three proposals were as follows:

NATIONS JDC EAGLE TECHNOLOGY
Feasibility of Approach Superior Susceptible Acceptable
Understanding of Problem Superior Susceptible Acceptable
Completeness Acceptable Susceptible Acceptable
Personnel Superior Acceptable Susceptible
Materials and Facilities Acceptable Acceptable Acceptable
Technical Manhours Superior Unacceptable Acceptable
Management Superior Acceptable Acceptable
OVERALL SUPERIOR SUSCEPTIBLE ACCEPTABLE

By letter dated August 13, 1985, E.T. Kofron, the government contracting officer for this project, notified plaintiff of thirteen technical Items for Negotiation (IFN) and invited plaintiff to provide responses to the areas of concern identified on or before August 26, 1985. Plaintiff submitted its revisions on time, and the Readiness Directorate performed a second technical evaluation of DeClerk’s- proposal. The contracting officer then advised plaintiff of certain items in need of still further clarification. Plaintiff responded on or about October 24, 1985.

A revised technical evaluation of the proposals of plaintiff, Eagle Technology and [39]*39Nations, Inc. was completed on November 20, 1985. In particular, the government stated that DeClerk’s proposal “conflicts itself” regarding travel expense projections and indicated that if plaintiff was awarded the contract, the government would have to engage in a significant amount of training of plaintiff in material fielding. The second evaluation stated in full:

OFFEROR: Joseph L. DeClerk & Associates (JDC)
1. The graduated man loading proposed by JDC would provide for adequate personnel to support the FY 86 level of effort for SINCGARS. The evaluation projects that three (3) MFT’s should be sufficient to execute the FY 87 fieldings.
2. Page 4 of the proposal states that the solicitation is deficient in that travel requirements are not an evaluation factor. It is the understanding of the evaluation team that the opposite is in fact correct. All other offerors presented detailed travel projections.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rochester City Lines Co. v. City of Rochester
897 N.W.2d 792 (Court of Appeals of Minnesota, 2017)
Raytheon Company v. United States
121 Fed. Cl. 135 (Federal Claims, 2015)
Systems Plus, Inc. v. United States
69 Fed. Cl. 757 (Federal Claims, 2006)
Sullivan v. Ltv Aerospace and Defense Company, Ltv
82 F.3d 1251 (Second Circuit, 1996)
Sullivan v. LTV Aerospace & Defense Co.
82 F.3d 1251 (Second Circuit, 1996)
A-Transport Northwest Co., Inc. v. United States
36 F.3d 1576 (Federal Circuit, 1994)
Shields Enterprises, Inc. v. United States
38 Cont. Cas. Fed. 76,526 (Federal Claims, 1993)
A-Transport Northwest Co. v. United States
38 Cont. Cas. Fed. 76,440 (Federal Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,312, 26 Cl. Ct. 35, 1992 U.S. Claims LEXIS 176, 1992 WL 82015, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-l-declerk-associates-inc-v-united-states-cc-1992.