Joseph Horne Co. v. Pennsylvania Public Utility Commission

485 A.2d 1105, 506 Pa. 475, 1984 Pa. LEXIS 376
CourtSupreme Court of Pennsylvania
DecidedDecember 19, 1984
Docket34 W.D. Appeal Docket 1984
StatusPublished
Cited by6 cases

This text of 485 A.2d 1105 (Joseph Horne Co. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph Horne Co. v. Pennsylvania Public Utility Commission, 485 A.2d 1105, 506 Pa. 475, 1984 Pa. LEXIS 376 (Pa. 1984).

Opinions

OPINION OF THE COURT

HUTCHINSON, Justice.

Joseph Horne Company (Horne), a ratepayer of the Duquesne Light Company (Duquesne) appeals by allowance a Commonwealth Court order affirming an order of the Pennsylvania Public Utility Commission (PUC) which granted Duquesne a rate increase of $64 million. At issue is the “option order procedure” used by the PUC to grant this increase pending final action on a request for general rate increase. Horne contends that this procedure is violative of both the Public Utility Code (Code), 66 Pa.C.S. §§ 101-3315, and the due process clause of the United States Constitution. In accordance with well recognized principles of judicial restraint we do not consider the due process issue because we must hold, for the reasons which follow, that in this case the PUC allowed an interim rate increase to become effective pending action on a request for a general rate increase contrary to Section 1310(a) of the Public Utility Code. That section expressly disallows temporary rate increases in general rate proceedings. We therefore reverse the order of Commonw ^alth Court.

[479]*479The essential facts are not in dispute. On April 30, 1981, Duquesne filed with the PUC Supplement No. 49 to Tariff-Electric-Pa. PUC No. 14. This supplement, which was to become effective June 29, 1981, contained proposed changes in rates, rules and regulations calculated to produce an increase of $100,432,782 in annual revenues. That amount represented an increase of 15% in Duquesne’s rates, and thus constituted a general rate increase as defined by the Code.1 In support of the supplement Duquesne filed all the supporting data required by 52 Pa.Code § 53.51 et seq. Duquesne supplied counsel for Horne with a copy of the supplement and all supporting data on May 5, 1981.

On June 12, 1981, Horne, along with other commercial ratepayers, filed a formal complaint against Supplement No. 49. The PUC docketed the complaint at R-811470. Duquesne filed a timely answer. On June 29, 1981, the PUC entered a unanimous order (option order) suspending Duquesne’s proposed rates until January 29, 1982,2 unless by order of the PUC they were allowed into effect at an earlier date. The order also instituted an investigation into whether the proposed rates were lawful, just, and reasonable. Finally, the order stated that if Duquesne filed a new tariff supplement on 15 days notice, cancelling and superseding Supplement No. 49 and containing proposed rate changes calculated to produce additional annual revenues of not more than $64,237,000, (option rate) then upon approval by the PUC the lesser increase would be allowed to become effective immediately upon such filing.3 This lesser increase was also subject to the investigation instituted by [480]*480the June 29 order, and any formal complaint filed against Supplement No. 49 would, if not withdrawn, be deemed filed against the lesser tariff supplement.

On Júne 30, 1981, in accordance with this order, Duquesne filed Supplement No. 52 to Tariff No. 14. It proposed to increase rates by $64,192,000. Supplement No. 52 expressly cancelled and superseded Supplement No. 49, and unless itself superseded was to become effective July 15, 1981. The PUC approved Supplement No. 52 by order adopted July 17, 1981, (entered July 20, 1981). This approval was retroactive to July 15, but subject to the same investigation and possibility of refunds as Supplement No. 49.4

[481]*481On December 1, 1981, after eleven (11) days of hearings, an administrative law judge recommended a decision finding the “option” rates set forth in Supplement No. 52 just and reasonable.5 Horne filed exceptions to the recommended decision. In them it specifically challenged the option order procedure under which the supplement was filed and allowed to go into effect. By order adopted April 15, 1982, entered on April 19, the PUC dismissed Horne’s exceptions and adopted the order the administrative law judge had recommended. Horne appealed6 to Commonwealth Court. It affirmed.

The record shows that after a preliminary ex parte investigation of the data supporting the original filing for a $100,000,000 rate increase (Supplement No. 49) the Commission notified Duquesne of the “option” to place the lesser increase of about $64,000,000 into immediate effect. This lesser increase (Supplement No. 52) was made effective before full investigation and hearing. Thereafter, a full investigation was conducted by the PUC with an opportunity for Horne and other interested parties to file complaints and participate in the hearings. If Supplement No. 52 had not received ultimate approval, refunds would have been available. This procedure is not unlike that for the Energy Cost Rate (ECR) which we upheld against a due process challenge in Allegheny Ludlum Steel Corp. v. Pennsylvania Public Utility Commission, 501 Pa. 71, 459 A.2d 1218 (1983). The ECR provided for an automatic adjustment in rates, based on formulae devised by the PUC, in order to [482]*482reflect fuel cost increases to the utilities.7 However, the use of such a procedure with respect to the so-called “option” order does not answer the key question before us, viz., were temporary rates improperly set in violation of the Public Utility Code?

The general rule governing temporary rates is set forth in § 1310(a) of the Code, which provides

§ 1310. Temporary rates,
(a) General rule. — The commission may, in any proceeding involving the rates of a public utility, except a proceeding involving a general rate increase, brought either upon its own motion or upon complaint, after reasonable notice and hearing, if it be of opinion that the public interest so requires, immediately fix, determine, and prescribe temporary rates to be charged by such public utility, pending the final determination of such rate proceeding. Such temporary rates, so fixed, determined, and prescribed, shall be sufficient to provide a return of not less than 5% upon the original cost, less accrued depreciation, of the physical property, when first devoted to public use, of such public utility, used and useful in the public service, and if the duly verified reports of such public utility to the commission do not show such original cost, less accrued depreciation, of such property, the commission may estimate such cost less depreciation and fix, determine, and prescribe rates as hereinbefore provided.

66 Pa.C.S. § 1310(a) (emphasis added). Because the instant case is a general rate case, it is clear that § 1310(a) prohibits the establishment of temporary rates, regardless of the procedure used to set them. Thus, if temporary rates were in fact set in this case through the guise of an option order, they are invalid under the terms of the Code, without [483]*483regard to whether the procedures used , to establish them conformed to general due process standards.

Duquesne’s first filing, Supplement No. 49, constituted a general rate increase, as did its second filing, Supplement No. 52. General rate increases are governed by § 1308(d) of the Code, which provides in relevant part:

(d) General rate increases.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schellhammer v. Pennsylvania Public Utility Commission
629 A.2d 189 (Commonwealth Court of Pennsylvania, 1993)
Masthope Rapids Property Owners Council v. Pennsylvania Public Utility Commission
581 A.2d 994 (Commonwealth Court of Pennsylvania, 1990)
Barasch v. Pennsylvania Public Utility Commission
568 A.2d 276 (Commonwealth Court of Pennsylvania, 1989)
Duquesne Light Co. v. Pennsylvania Public Utility Commission
543 A.2d 196 (Commonwealth Court of Pennsylvania, 1988)
Meléndez Ortiz v. Valdejully
120 P.R. Dec. 1 (Supreme Court of Puerto Rico, 1987)
Joseph Horne Co. v. Pennsylvania Public Utility Commission
485 A.2d 1105 (Supreme Court of Pennsylvania, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
485 A.2d 1105, 506 Pa. 475, 1984 Pa. LEXIS 376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-horne-co-v-pennsylvania-public-utility-commission-pa-1984.