Joseph E. Eason III and Catherine Weil v. Deering Construction, Inc. D/B/A DK Construction

CourtCourt of Appeals of Texas
DecidedDecember 3, 2020
Docket02-19-00310-CV
StatusPublished

This text of Joseph E. Eason III and Catherine Weil v. Deering Construction, Inc. D/B/A DK Construction (Joseph E. Eason III and Catherine Weil v. Deering Construction, Inc. D/B/A DK Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph E. Eason III and Catherine Weil v. Deering Construction, Inc. D/B/A DK Construction, (Tex. Ct. App. 2020).

Opinion

In the Court of Appeals Second Appellate District of Texas at Fort Worth ___________________________ No. 02-19-00310-CV ___________________________

JOSEPH E. EASON III AND CATHERINE WEIL, Appellants

V.

DEERING CONSTRUCTION, INC. D/B/A DK CONSTRUCTION, Appellee

On Appeal from County Court at Law No. 3 Tarrant County, Texas Trial Court No. 2017-002610-3

Before Gabriel, Birdwell, and Bassel, JJ. Memorandum Opinion by Justice Gabriel MEMORANDUM OPINION

Appellants Joseph “Trey” Eason III and Catherine Weil 1 appeal the trial court’s

judgment awarding appellee Deering Construction $9,449.74 in damages and $30,000

in attorney’s fees. Because the evidence is factually insufficient to support the amount

of damages awarded, we suggest a remittitur of $2,734.74. And because we hold the

evidence is factually insufficient to uphold the attorney’s fees award, we reverse that

portion of the judgment and remand the fee issue to the trial court for reconsideration

in light of Rohrmoos Venture v. UTSW DVA Healthcare, LLP, 578 S.W.3d 469 (Tex.

2019).

I. BACKGROUND FACTS

A. THE PARTIES’ AGREEMENT

In February 2016, Trey contacted Brad Deering,2 a general contractor

specializing in residential renovations, to inquire about a possible kitchen renovation

in the Easons’s 1930s Tudor-style home. Deering met with Trey at the house, where

Trey showed him a basic drawing of what the Easons wanted, including vaulted

ceilings and new appliances, fixtures, countertops, and flooring. After two more walk-

1 For simplicity and in accordance with their own brief, we will refer to the appellants collectively as the Easons. 2 Deering’s company is Deering Construction, Inc. d/b/a DK Construction, the named appellee. We will refer to Brad Deering and his company collectively as Deering.

2 throughs, Deering put together a proposal estimating an overall cost of $112,610.04,

including 18% for his overhead and profit.

The Easons hired Deering to perform the work, but when the project costs

exceeded the original proposal, it became clear that they and Deering disagreed about

the character of their agreement. While the Easons viewed it as a fixed-price

agreement, with Deering agreeing to cover any overages beyond the initial quote of

$112,610.04, Deering adamantly denied ever making such a promise and characterized

their agreement as a cost-plus arrangement. In fact, Deering testified that in over 20

years of business he had never entered into a fixed-price contract for a project and

described how doing so would be nearly impossible as there were too many

unknowns—the Easons had not selected finishings and fixtures and Deering could

not predict what additional work may be needed due to the age of the house. Deering

denied ever telling the Easons that $112,610.04 would be the maximum cost.

B. PROBLEMS AND OVERAGES

Deering began work in October 2016. Soon after Deering began working on

the home, he discovered some of the problems that are typical in older homes,

including termite damage, structural issues, and plumbing problems, which required

additional costs to repair. And, according to Deering, the Easons chose fixtures that

resulted in additional expenses beyond the planned allowances.

3 1. Flooring and Ceilings

Over the years, past owners had laid multiple layers of flooring over the

original hardwood floors. Those layers had to be removed and, once gone, it was

clear that the hardwood was unsalvageable, so it had to be removed and replaced.

Though the cost to replace the hardwood floors came in under budget, replacing the

damaged subfloor beneath it incurred additional costs that were not included in the

original proposal.

Deering also found structural problems in the ceiling, caused by termite

damage and poor past-renovation work. The ceiling was sagging because a wall had

been removed but a proper header had not been installed. Deering testified that they

had not known about it until they began work because it was not visible from below.

Repairing the damaged floors and ceiling incurred an additional $1,800 cost beyond

the original proposal.

2. Painting

Painting and trim work also cost more than expected—originally budgeted at

$7,800, the final cost was $11,658. Deering alleged that Trey instructed the painter to

strip the paint on the doors to the bedroom and hallway—tasks that were not

included in the original proposal—and that the painter stripped cabinets that he

should not have, causing extra work. When it came to trim work, Deering alleged that

the Easons asked for items outside the original scope of work, including “modifying

4 the pantry door [and] install[ing] glass in it.” Trey denied requesting any additional

painting or trim work.

When Deering invoiced the Easons for the painting and trim work, he only

charged them $7,800 but noted on the invoice: “Actual invoice amount was

$11,658.00, will reconcile at end of project.” He explained at trial that he had hoped

that shortages in other areas of the project would cover that additional expense.

3. Countertops and Tiling

Deering also averred that some of the Easons’s choices for materials and

fixtures exceeded the originally planned allowances. Deering had allowed $7,380 for

countertops, including labor and installation, but the Easons’s choices exceeded that

amount in the materials cost alone. Trey even admitted at trial that their countertop

choices exceeded the allowance without accounting for labor and installation.

Similarly, the Easons chose tiles that had to be individually cut and laid, causing

five more days of labor to install than initially expected. Deering testified that the

original allowance for tile-installation labor was $400 but the end cost was $1,440.

Trey testified that Deering never indicated that the installation would be more costly.

4. Appliances

The appliances also cost more than originally expected, and Deering averred

that Trey approved the appliance invoices before they were ordered. Whereas the

5 proposal provided $10,711.24, the appliances actually cost $13,611.23.3 The Easons

argued that they paid these costs in response to two invoices by Deering charging

$12,024.70 and $1,421.28 for appliance costs.

5. Design Work

Deering testified that design work for drawing cabinet and pantry plans cost

$2,475.00 and was not billed at the time it was completed in November. He also

averred that the Easons approved the design work.

C. DEERING’S OFFER TO FOREGO PROFIT

In early December, when the Easons raised concerns about staying on budget,

Deering offered to stop billing his overhead and profit—an offer the Easons

accepted. Deering testified that the Easons never mentioned not paying for overages,

but instead paid every invoice up until the “very end of the project.” In all, the

Easons paid Deering $113,722.

D. THE EASONS’S REFUSAL TO PAY FOR OVERAGES

After the work was finished, Deering met with the Easons in early

February 2017 to discuss two unpaid invoices—invoices 4899 and 4830. Invoice

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Willis v. Donnelly
199 S.W.3d 262 (Texas Supreme Court, 2006)
Central Ready Mix Concrete Co. v. Islas
228 S.W.3d 649 (Texas Supreme Court, 2007)
Guevara v. Ferrer
247 S.W.3d 662 (Texas Supreme Court, 2007)
Hernandez v. Lautensack
201 S.W.3d 771 (Court of Appeals of Texas, 2006)
City of Fort Worth v. GENE HILL EQUIPMENT CO.
761 S.W.2d 816 (Court of Appeals of Texas, 1988)
Anderson v. City of Seven Points
806 S.W.2d 791 (Texas Supreme Court, 1991)
Pool v. Ford Motor Co.
715 S.W.2d 629 (Texas Supreme Court, 1986)
Truly v. Austin
744 S.W.2d 934 (Texas Supreme Court, 1988)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
Findlay v. Cave
611 S.W.2d 57 (Texas Supreme Court, 1981)
Uniroyal Goodrich Tire Co. v. Martinez
977 S.W.2d 328 (Texas Supreme Court, 1998)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Garza v. Alviar
395 S.W.2d 821 (Texas Supreme Court, 1965)
Sage Street Associates v. Northdale Construction Co.
863 S.W.2d 438 (Texas Supreme Court, 1993)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)
Guillermo Garza D/B/A Wilhome Builders & Construction v. Jesse Cantu
431 S.W.3d 96 (Court of Appeals of Texas, 2013)
Super Ventures, Inc. and Abu Tuarb Tariq v. Saiqa S. Chaudhry
501 S.W.3d 121 (Court of Appeals of Texas, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Joseph E. Eason III and Catherine Weil v. Deering Construction, Inc. D/B/A DK Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-e-eason-iii-and-catherine-weil-v-deering-construction-inc-dba-texapp-2020.