Jos. P. Jansen Co. v. Milwaukee Area District Board of Vocational, Technical & Adult Education

312 N.W.2d 813, 105 Wis. 2d 1, 1981 Wisc. LEXIS 3052
CourtWisconsin Supreme Court
DecidedDecember 1, 1981
Docket79-1996
StatusPublished
Cited by30 cases

This text of 312 N.W.2d 813 (Jos. P. Jansen Co. v. Milwaukee Area District Board of Vocational, Technical & Adult Education) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jos. P. Jansen Co. v. Milwaukee Area District Board of Vocational, Technical & Adult Education, 312 N.W.2d 813, 105 Wis. 2d 1, 1981 Wisc. LEXIS 3052 (Wis. 1981).

Opinion

COFFEY, J.

This is a review of a decision of the court of appeals affirming a judgment of the circuit court for Milwaukee county, HON. PATRICK J. MADDEN, presiding. The judgment dismissed the claim of the plaintiff-appellant-petitioner, Joseph P. Jansen Company, Inc., (Jansen) and awarded $17,910.75 to the defendant-respondent, Milwaukee Area District Board of Vocational, Technical and Adult Education (MATC) on its counterclaim. This case involves the application of a written construction contract to a dispute over credits and extras for work done and materials used in filling an excavation (hole) in a building site. Jansen, a building contractor, claimed it was entitled to additional compensation for alleged “extra work” performed under the written construction contract in filling the excavation, and MATC, the owner, claims it is entitled to a credit on its payments to Jansen because of Jansen’s substitution of materials used as fill. The trial court construed the contract as a matter of law and granted MATC’s renewed motion for directed verdict after a jury verdict was rendered in favor of Jansen.

*4 On January 29, 1975, MATC awarded a contract to Jansen to perform general construction work at MATC’s South Campus in Oak Creek, Wisconsin. As part of the contract, Jansen agreed to perform certain earthwork, the specifications for which were contained in Sec. 2200 of the “Project Manual” which is a part of the contract. Jansen’s contract did not cover all the earth and grading work at the construction site. A separate and earlier contract for “site grading” had been awarded to Stoehr Grading, another contractor. The work Stoehr was to perform was specified in Sec. 2210 of the Project Manual and was to be completed before Jansen could perform any work under the contract. The contractual requirements for Jansen’s portion of the earthwork set out in Sec. 2200 were described with reference to the grading work already completed by Stoehr under Sec. 2210. A copy of Sec. 2210 was furnished to Jansen prior to the preparation of its bid, along with an original survey of the site and other information pertinent to the bid. Jansen visited the contruction site prior to submitting its bid and at that time, Stoehr had completed its share of the work relevant to this dispute.

Under Sec. 2210, Stoehr was required to strip all topsoil from the land on which the building was to be erected. 1 Performance of this requirement left a depressed area known as a swale at the building area of the MATC South Campus known as the TI South Wing. Before the building could be constructed, this swale had to be filled with material of sufficient stability to bear the weight of the building. Jansen raised the question of responsibility for filling the swale at a meeting held on *5 March 5, 1975. The architect for MATC responded in a letter indicating that Jansen was obligated to fill the swale area under the express terms of the contract. Jansen stated that it performed the work in order to allow construction to proceed, but maintained that it performed “extra work” not contemplated by the contract when it excavated unsuitable soil from the swale area and placed suitable fill in the area to bring the grade to proper elevation. At no time, however, did Jansen request or receive a change order for the swale work.

After being informed by MATC’s architect that it was responsible to fill the swale area, and before proceeding with construction, Jansen requested permission to substitute “site fill” for “engineered fill” as specified in the contract. A substantial amount of fill was required to bring the swale area to the required elevation. Site fill was considerably less expensive than engineered fill and met relevant contract specifications. MATC agreed to the substitution of fills but there is conflicting evidence as to whether an agreement was reached to credit MATC with the cost savings resulting therefrom. However, a conference memorandum prepared by MATC’s architect indicates that at the meeting held on June 9, 1975, Jansen conceded that there was a value difference between the site fill and select fills and agreed to submit the question to arbitration to determine the amount of credit due the owner, if an agreement could not be reached with the architect.

Jansen and MATC failed to resolve their dispute over the responsibility for excavating and filling the swale area; and, in November of 1977, two years after completion of the building project, Jansen brought this action seeking a reimbursement of $14,625 for the alleged “extra work” it performed. MATC counterclaimed for a *6 credit of $17,910.75 on the contract price due Jansen based on the cost savings resulting from the substitution of fill materials.

The case was tried to a jury on April 16th through 18th, 1977. At the close of plaintiff’s case, MATC moved for dismissal, arguing that liability was determinable solely from the contract. Before submission to the jury, MATC also moved for a directed verdict on the same grounds. The court reserved ruling on each of these motions and submitted the case to the jury. On April 19, 1979, the jury returned a verdict in favor of Jansen. On October 24, 1979, more than 180 days after the jury rendered its verdict, the trial court granted MATC’s motion for a directed verdict and set aside the jury verdict. Judgment was entered on November 29, 1979, awarding MATC the sum of $17,910.75 on their counterclaim.

Jansen appealed this decision, arguing that MATC’s motion for directed verdict should be denied because the trial court did not enter its order granting the motion within the time period specified in sec. 805.16, Stats. (90 days) and, further, that there was credible evidence to support the jury verdict. The court of appeals affirmed the trial court’s judgment, holding that the failure of the trial court to render a timely decision on MATC’s motion was not prejudicial and that the terms of the contract were not ambiguous and thus they required Jansen to excavate and fill the swale.

Issues:

1. Did the trial court commit prejudicial error in failing to act on MATC’s motion for a directed verdict within 90 days of the verdict?

2. Did the court of appeals err in holding that the construction of the construction contract was solely a question of law reviewable ab initio by that court?

*7 Timeliness

Sec. 805.16, Stats., expressly requires that an order granting or denying a motion challenging the sufficiency of the evidence, or for a new trial, must be entered within 90 days of the verdict or the motion shall be deemed denied. 2 Pursuant to the provisions of sec. 805.14, motions to dismiss made at the close of plaintiff’s case and motions for directed verdict are motions challenging the sufficiency of evidence as that term is used in ch. 805, Stats. 3 In this case, more than five months *8 passed from the day the jury rendered its verdict before the trial court entered its decision granting MATC’s motion for a directed verdict.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M & D Truck & Equipment Sales LLC v. Daniel Amarei
Court of Appeals of Wisconsin, 2026
Daniel L. Lamphere v. Ryan Hulback
Court of Appeals of Wisconsin, 2025
Wilhelm v. McCoy Contractors, Inc.
2018 WI App 71 (Court of Appeals of Wisconsin, 2018)
Robert L. Kimble v. Land Concepts, Inc.
2014 WI 21 (Wisconsin Supreme Court, 2014)
State v. Abbott Laboratories
2012 WI 62 (Wisconsin Supreme Court, 2012)
Brandner v. Allstate Insurance
512 N.W.2d 753 (Wisconsin Supreme Court, 1994)
Village of Elm Grove v. T v. John & Son, Inc.
496 N.W.2d 167 (Court of Appeals of Wisconsin, 1992)
In Interest of BJN
469 N.W.2d 845 (Wisconsin Supreme Court, 1991)
Green County Department of Human Services v. H.N.
469 N.W.2d 845 (Wisconsin Supreme Court, 1991)
State v. Scherreiks
451 N.W.2d 759 (Court of Appeals of Wisconsin, 1989)
Watts (Bischoff) v. Watts
448 N.W.2d 292 (Court of Appeals of Wisconsin, 1989)
Anchor Savings & Loan Ass'n v. Coyle
435 N.W.2d 727 (Wisconsin Supreme Court, 1989)
State v. R.A.R.
432 N.W.2d 685 (Court of Appeals of Wisconsin, 1988)
Schoenwald ex rel. L.M.C. v. M.C.
430 N.W.2d 352 (Court of Appeals of Wisconsin, 1988)
In Interest of LMC
430 N.W.2d 352 (Court of Appeals of Wisconsin, 1988)
Anchor Savings & Loan Ass'n v. Coyle
427 N.W.2d 383 (Court of Appeals of Wisconsin, 1988)
Gegan v. Backwinkel
417 N.W.2d 44 (Court of Appeals of Wisconsin, 1987)
Hartford Insurance v. Wales
406 N.W.2d 426 (Wisconsin Supreme Court, 1987)
Manly v. State Farm Fire & Casualty Co.
407 N.W.2d 306 (Court of Appeals of Wisconsin, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
312 N.W.2d 813, 105 Wis. 2d 1, 1981 Wisc. LEXIS 3052, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jos-p-jansen-co-v-milwaukee-area-district-board-of-vocational-wis-1981.