Jonathan Burke Skelton v. Freese Construction Company, Inc.

CourtCourt of Appeals of Tennessee
DecidedDecember 9, 2013
DocketM2012-01935-COA-R3-CV
StatusPublished

This text of Jonathan Burke Skelton v. Freese Construction Company, Inc. (Jonathan Burke Skelton v. Freese Construction Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jonathan Burke Skelton v. Freese Construction Company, Inc., (Tenn. Ct. App. 2013).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE September 24, 2013 Session

JONATHAN BURKE SKELTON v. FREESE CONSTRUCTION COMPANY, INC.

Direct Appeal from the Chancery Court for Rutherford County No. 90031CV Robert E. Corlew, III, Chancellor

No. M2012-01935-COA-R3-CV - Filed December 9, 2013

This appeal involves the enforceability of an arbitration agreement between the parties. The trial court found the agreement was not unconscionable, but that the defendant had waived its right to enforce the agreement. We reverse the decision of the chancery court and we remand for entry of an order compelling arbitration.

Tenn. R. App. P. 3; Appeal as of Right; Judgment of the Chancery Court Reversed and Remanded

A LAN E. H IGHERS, P.J., W.S., delivered the opinion of the Court, in which D AVID R. F ARMER, J., joined, and H OLLY M. K IRBY, J., concurred in result only.

J. Timothy Crenshaw, Nashville, Tennessee, for the appellant, Freese Construction Company, Inc.

Timothy H. Nichols, Nashville, Tennessee, for the appellee, Jonathan Burke Skelton OPINION

I. F ACTS & P ROCEDURAL H ISTORY

This appeal involves the enforceability of an arbitration agreement between the parties. The defendant, Freese Construction Company, Inc. (“Defendant” or “Freese”), acted as the general contractor for construction of the Murfreesboro Medical Clinic. In 2008, Outdoors Unlimited, LLC entered into a Subcontract Agreement with Freese to provide landscaping and irrigation improvements for the project.

The Subcontract Agreement identified “Outdoors Unlimited, LLC” as the “Subcontractor” and Freese as the “Contractor[,]” and it included the following arbitration clause:

Notwithstanding any dispute clauses contained in the General Conditions or the contract with the Owner, the Subcontractor agrees that in the event of a dispute between the Subcontractor and Contractor, the dispute may be submitted to arbitration at the sole option of Contractor. Arbitration shall be binding and held in accordance with rules and procedures to be agreed by the parties. If no agreement can be reached within twenty (20) days of demand, the arbitration will be held in accordance with the Construction Industry Rules of the American Arbitration Association which are in effect at the time the demand for arbitration is filed. Once Contractor has chosen arbitration and so advised Subcontractor in writing, should either party refuse or neglect to appear or participate in arbitration proceedings, the arbitrators are empowered to decide the controversy in accordance with whatever evidence is presented. The arbitrators are authorized to award any party or parties such sums as such arbitrators shall deem proper for the time, expense and trouble of arbitration, including attorneys’ fees and other litigation expenses. In the event of a dispute over the arbitrability of a dispute, the arbitrator has exclusive jurisdiction to decide the arbitrability of the dispute.

In the event of litigation or arbitration to enforce any of the terms and provisions of this Agreement, the prevailing party shall be entitled to receive all reasonable litigation expenses, including attorneys’ fees, incurred therein (including fees and expenses for appeals) together with the costs and disbursements. In no event shall said attorneys’ fees be based on a contingency fee bases. Attorneys’ fees shall be computed on an hourly basis.

-2- A dispute arose regarding the sufficiency of work performed by Outdoors Unlimited, LLC and payment for that work. On January 12, 2009, Jonathan Burke Skelton, individually, filed a “Verified Complaint to Enforce Mechanics’ and Materialmen’s Lien” (“Complaint”) against Freese, among others. The Complaint identified Mr. Skelton as “the owner of Outdoors Unlimited . . . , which is a sole proprietorship[.]” In the Complaint, Mr. Skelton asserted numerous claims against Freese, and he sought, among other things, a judgment of $144,916.98.

Before any of the defendants filed an answer, Mr. Skelton filed an Amended Complaint, on February 20, 2009, to add a defendant and to replace his “mechanics’ and materialmen’s lien” claim with a “claim against payment bond.”

On June 2, 2009, Freese filed a “Motion to Dismiss Jonathan Burke Skelton’s Complaint or, in the Alternative, for Judgment on the Pleadings[.]” Freese argued that Mr. Skelton, who was not a party to the Subcontract Agreement, lacked standing to assert claims against Freese. Freese’s motion was scheduled to be heard on August 12, 2009. However, according to the affidavit testimony of Freese’s attorney, J. Timothy Crenshaw, when the case was called at the August 12, 2009 hearing, Mr. Skelton’s counsel requested that he be allowed to amend his complaint a second time. Freese did not oppose the motion, and the trial court granted Mr. Skelton ten days in which to file an amended complaint and it stated that Freese could then re-set its motion to dismiss.

Mr. Skelton, however, did not file an amended complaint within ten days of the hearing. Counsel for the various defendants lodged a proposed order with the trial court in October 2009, which the trial court entered on November 5, 2009. The Order directed Mr. Skelton to file an amended complaint within ten days, and it stated that Freese, thereafter, could re-set its motion to dismiss for hearing. Mr. Skelton, however, again failed to file an amended complaint.

On January 29, 2010, Mr. Skelton’s counsel filed a Motion to Withdraw, which was scheduled to be heard on March 4, 2010. It appears that no action was taken, and Mr. Skelton’s counsel filed a second Motion to Withdraw on September 2, 2010. The second motion was heard on September 17, 2010, after which the trial court entered an Order to Withdraw, directing Mr. Skelton to secure replacement counsel within thirty days.

It appears that no further action was taken in the case until March 29, 2011, when Freese filed a Notice of Hearing scheduling its previously-filed Motion to Dismiss for a hearing on April 7, 2011. Along with its Notice of Hearing, Freese also filed a “Supplemental Memorandum in Support of Motion to Dismiss” raising Mr. Skelton’s failure to comply with the November 5, 2009 order directing the filing of an amended complaint and

-3- his failure to prosecute the suit as additional grounds for dismissal.

On April 6, 2011, one day before Freese’s Motion to Dismiss was scheduled to be heard, Timothy H. Nichols filed a Notice of Appearance as Mr. Skelton’s counsel. That same day, Mr. Skelton filed a Response in opposition to Freese’s Motion to Dismiss as well as a Second Amended Complaint naming “Jonathan Burke Skelton d/b/a Outdoors Unlimited, LLC and d/b/a Outdoors Unlimited” as the plaintiff. Attached to his Second Amended Complaint was the Affidavit of Jonathan Burke Skelton, which stated in part:

Prior to January 15, 2008, I filed papers with the Tennessee Secretary of State to form a single member Tennessee limited liability company called “Outdoors Unlimited, LLC,” with myself as a sole member of that entity. As of January 15, 2008, I believed that Outdoors Unlimited, LLC had, in fact, been successfully formed. However, unbeknownst to me, issues with the paperwork submitted by me to form Outdoors Unlimited, LLC caused the Secretary of State to reject the papers submitted to form Outdoors Unlimited, LLC.

Operating under the belief that I had successfully formed “Outdoors Unlimited, LLC”, on January 15, 2008, I signed a subcontract . . . with Freese Construction to furnish labor and materials to construct the landscaping and irrigation improvements on a construction project known as the Murfreesboro Medical Clinic . . . on which Freese was the general contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barnes v. Barnes
193 S.W.3d 495 (Tennessee Supreme Court, 2006)
Taylor v. Butler
142 S.W.3d 277 (Tennessee Supreme Court, 2004)
Carolyn B. Beasley Cotton Co. v. Ralph
59 S.W.3d 110 (Court of Appeals of Tennessee, 2000)
Gaston v. Tennessee Farmers Mutual Insurance Co.
120 S.W.3d 815 (Tennessee Supreme Court, 2003)
Haun v. King
690 S.W.2d 869 (Court of Appeals of Tennessee, 1984)
Jenkins Subway, Inc. v. Jones
990 S.W.2d 713 (Court of Appeals of Tennessee, 1998)
Buraczynski v. Eyring
919 S.W.2d 314 (Tennessee Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Jonathan Burke Skelton v. Freese Construction Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/jonathan-burke-skelton-v-freese-construction-compa-tennctapp-2013.