Carolyn B. Beasley Cotton Co. v. Ralph

59 S.W.3d 110, 2000 Tenn. App. LEXIS 712
CourtCourt of Appeals of Tennessee
DecidedOctober 25, 2000
StatusPublished
Cited by18 cases

This text of 59 S.W.3d 110 (Carolyn B. Beasley Cotton Co. v. Ralph) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carolyn B. Beasley Cotton Co. v. Ralph, 59 S.W.3d 110, 2000 Tenn. App. LEXIS 712 (Tenn. Ct. App. 2000).

Opinion

OPINION

DAVID R. FARMER, J.,

delivered the opinion of the court,

in which W. FRANK CRAWFORD, P.J., W.S., and HOLLY K. LILLARD, J., joined.

This appeal arises from a breach of contract between Fanner and Broker. After signing a contract to deliver cotton to Broker, Farmer failed to do so. Broker was then forced to purchase the cotton elsewhere for a substantial loss and brought suit to recover the losses. At the start of the trial, Farmer requested that the trial court dismiss the case and order the parties to proceed to arbitration. Finding that Farmer had waived his rights under the contract to arbitration, the trial court refused. Proceeding with the case, court found that Farmer had breached the contract and awarded damages to Broker. We affirm.

On May 25 and again on June 8, 1995, Kem Ralph entered into written contracts with the Carolyn B. Beasley Cotton Company (Beasley). 1 Each contract stated that Mr. Ralph would sell Beasley 100 bales of cotton during the 1995-96 crop year. The dispute in this case arose sometime between December of 1995 and February of 1996, with each party arguing a different set of facts. Mr. Ralph claims that he informed Beasley in December of 1995 that he would be unable to fulfill his contracts. Beasley claims that it had no notice that Mr. Ralph intended to breach these contracts until it sent demands for delivery in late January and early February of 1996 that went unanswered. It is undisputed, however, that Beasley received no cotton from Mr. Ralph and had to purchase cotton on the open market to fulfill its obligations, resulting in a loss to Beasley of $13,050. Beasley demanded reimbursement from Mr. Ralph for this loss, and upon receiving no reply, filed suit for breach of contract.

Both sides conducted pre-trial discovery before the trial date set in August, 1997. However, at the beginning of this trial, Mr. Ralph moved the court that the case be sent to binding arbitration as provided in the contract. The trial court then delayed the start of the trial and took this request under consideration. Thereafter, the court found that Mr. Ralph, by his failure to request arbitration before the scheduled start of the trial, had waived his right to arbitration and denied the motion. The trial was conducted in March 1999. The court rejected Mr. Ralph’s arguments that the contracts had no set price and were thus unenforceable. It also found that Beasley had acted properly to mitigate its damages. As such, Mr. Ralph was ordered to pay $13,050 in damages, plus prejudgment interest, attorney’s fees and court costs. This appeal followed.

The issues presented by the appellant on appeal, as we perceive them, are as follows:

1. Did the trial court err in denying the motion to transfer this matter to arbitration as provided under the contract?
2. Did the trial court err in faihng to find the contract void due to contradicting terms regarding price?
3. Did the trial court err in failing to reduce the damages through a find *113 ing that Beasley did not act to mitigate its damages?

To the extent that these issues involve questions of fact, our review of the trial court’s ruling is de novo with a presumption of correctness. See Tenn. R.App. P. 13(d). Accordingly, we may not reverse the court’s factual findings unless they are contrary to the preponderance of the evidence. See, e.g., Randolph v. Randolph, 937 S.W.2d 815, 819 (Tenn.1996); Tenn. R.App. P. 13(d). With respect to the court’s legal conclusions, however, our review is de novo with no presumption of correctness. See, e.g., Bell ex rel. Snyder v. Icard, Merrill, Cullis, Timm, Furen and Ginsburg, P.A., 986 S.W.2d 550, 554 (Tenn.1999); Tenn. R.App. P. 13(d). The interpretation of a written contract is a matter of law, and thus, no presumption of correctness in its interpretation exists. See NSA DBA Benefit Plan, Inc. v. Connecticut Gen. Life Ins. Co., 968 S.W.2d 791 (Tenn.Ct.App.1997).

Arbitration

This court recently addressed the question of the waiver of arbitration in Rebound Care Corp. v. Universal Constructors, Inc., No. M1999-00868-COA-R3-CV, 2000 WL 758610, at *1 (Tenn.Ct.App. June 13, 2000) (no perm. app. filed). We stated in that case that

[i]n general, even in those jurisdictions where a contract for arbitration is irrevocable, the right to arbitration under the contract may be waived either by express words or by necessary implication, for example, where the conduct of a party clearly indicates an intent to waive the right to arbitrate. In those cases involving the issue of whether the defendant’s participation in an action constitutes a waiver of the right to arbitrate the dispute involved therein, no general rules are readily apparent for determining waiver other than the general adherence by the courts to the principle that waiver is to be determined from the particular facts and circumstances of each case....

Id. at *7 (citation omitted). Examining further, we noted that “[wjaiver is a matter of fact to be shown by the evidence.” Id. at *6 (quoting Koontz v. Fleming, 17 Tenn.App. 1, 65 S.W.2d 821, 824 (1933)).

The determination of whether Mr. Ralph waived his right to arbitration is a factual determination for the trial court. Thus, we may not reverse the court’s findings in this matter unless it is contrary to the preponderance of the evidence. See, e.g., Randolph v. Randolph, 937 S.W.2d 815, 819 (Tenn.1996); Tenn. RApp. P. 13(d). Upon our examination of the record, we note several actions by Mr. Ralph that suggest he waived his right to arbitration. As stated in the trial court’s opinion denying the motion to proceed to arbitration, Mr. Ralph filed an answer to Beasley’s original Complaint For Damages, as well as an answer to Beasley’s Request for Production of Documents. In addition, Mr. Ralph took pretrial depositions, filed pretrial motions and attended pretrial settlement conferences. Indeed, Mr. Ralph made no mention of the arbitration clause until the original trial court date when he filed a motion to refer the matter to arbitration. With this evidence, we cannot state that the trial court’s ruling is contrary to the preponderance of the evidence. As such, we hereby affirm the trial court’s decision that Mr. Ralph, through his actions surrounding this dispute, waived his right to arbitration under the contract.

Validity of the Contracts

In determining the validity of a contract, the court should “ascertain the intention of the parties from the contract *114 as a whole and ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kevin W. Addis v. Eagle CDI, Inc.
Court of Appeals of Tennessee, 2024
Amanda Paige Ryan-Cothron v. William Michael Cothron
Court of Appeals of Tennessee, 2020
James Montoya, Jr. v. State
Court of Appeals of Texas, 2016
Regions Bank v. Thomas D. Thomas
422 S.W.3d 550 (Court of Appeals of Tennessee, 2013)
In Re Surti
434 B.R. 515 (M.D. Tennessee, 2010)
Trezevant Realty Corporation v. John E. Threlkeld
Court of Appeals of Tennessee, 2008
Lamell Lumber Corp. v. Newstress International, Inc.
182 Vt. 282 (Supreme Court of Vermont, 2007)
Lamell Lumber Corp. v. NEWSTRESS INTERN.
2007 VT 83 (Supreme Court of Vermont, 2007)
Gaston v. Tennessee Farmers Mutual Insurance Co.
120 S.W.3d 815 (Tennessee Supreme Court, 2003)
Urology Associates v. Cigna Healthcare
Court of Appeals of Tennessee, 2002

Cite This Page — Counsel Stack

Bluebook (online)
59 S.W.3d 110, 2000 Tenn. App. LEXIS 712, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carolyn-b-beasley-cotton-co-v-ralph-tennctapp-2000.