Johnson-Sampson Construction Co. v. Casterline Grain & Seed, Inc.

252 P.2d 893, 173 Kan. 763, 1953 Kan. LEXIS 250
CourtSupreme Court of Kansas
DecidedJanuary 24, 1953
Docket38,764
StatusPublished
Cited by5 cases

This text of 252 P.2d 893 (Johnson-Sampson Construction Co. v. Casterline Grain & Seed, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson-Sampson Construction Co. v. Casterline Grain & Seed, Inc., 252 P.2d 893, 173 Kan. 763, 1953 Kan. LEXIS 250 (kan 1953).

Opinion

The opinion of the court was delivered by

Harvey, C. J.:

The appeal here is from an order of the district court overruling plaintiff’s motion for judgment on the answers to special questions made by the jury notwithstanding their general verdict. We shall speak of the parties as they appeared in the trial court. Each is a Kansas corporation. Plaintiff has its headquarters in Salina and is engaged in the building and construction business. Defendant has its headquarters at Dodge City, where it has an elevator for the handling and storage of grain. It decided to build an addition thereto sufficient to store 340,000 bushels of grain. After some preliminary negotiations, and as of the date of September 6, 1950, the parties entered into a written contract in which plaintiff agreed to furnish material and labor and construct the building for the sum of $108,810, which included the cost of a performance bond required to be given by plaintiff. The contract contained provisions common in such contracts, and with respect to the time of completion contained this clause:

“The contractor shall endeavor to have elevator completed to a point where it will handle grain by November 30, 1950.”

From the preliminary negotiations defendant had advised plaintiff of the importance to it of having the building completed by the middle or last of November, this for the reason that in the area *764 served by defendant a large quantity of maize is grown, the harvest of which begins in November. The plaintiff drew the contract and the specifications for the building and sent them to defendant. There were material omissions in the contract as first drawn, to which defendant called plaintiff’s attention. The contract and specifications appear to have been completed to the satisfaction of both parties, with the result that the contract was finally executed September 25, and soon thereafter the work was started. The building was completed so that it could be used for handling grain on December 29,1950, and it was first used for that purpose on January 2, 1951. The contract provided that certain payments of $10,000 or more each were to be made at stated periods while the structure was being built. Defendant made these payments as called for in the contract in a sum aggregating $100,000. Plaintiff brought this suit to recover the balance of $8,810. Defendant answered admitting that sum had not been paid under the contract and by cross petition alleged that it has been damaged by the failure of plaintiff to complete the elevator so it could handle grain by November 30 in the sum of $8,500.81, and alleged specific acts of negligence or unreasonable delay on plaintiff’s part. In plaintiff’s reply and answer to the cross petition it was alleged that the delays of which defendant complained were caused by the failure and neglect of defendant and the agencies which were lending defendant money to finance the construction, namely, the Reconstruction Finance Corporation and the Fidelity State Rank at Dodge City.

From the record, which is far from complete, it does appear that defendant, to construct the building, borrowed $100,000 from the Fidelity State Rank at Dodge City, which was furnishing twenty per cent of the loan, and the Reconstruction Finance Corporation, which was furnishing eighty per cent of the loan. That matter was not referred to in the contract executed by the parties, nor in the specifications, nor in the pleadings, other than in plaintiff’s reply and answer to the cross petition.

The pleadings were so framed that the only issues left for trial were those formed by the cross petition and the answer thereto, and primarily the issue was whether defendant was entitled to any of the damages, and if so, how much, because the elevator had not been completed so as to handle grain by November 30, 1950. There was a pretrial conference. A full report of that is not set out, but this much was furnished:

"The Court is making a finding here, first, that on the face of it, that the *765 plaintiff was required under this contract to use due diligence to complete this elevator on November 30, 1950. And if the evidence should show that the elevator was not completed to the point where it would handle grain by November 30, 1950, the defendant will have made out a prima facie case that plaintiff did not use due diligence.”

The court’s instructions have not been set out in full, but perhaps the pertinent ones are set out and read as follows:

“2. You are instructed that the plaintiff is entitled to judgment against the defendant for the sum of $8,810.00 in this case on its petition. You will then proceed to determine whether or not the defendant is entitled to judgment against the plaintiff on its cross-petition.
“3. You are instructed that the evidence in this case shows that the elevator was not completed to the point where it would handle grain by November 30, 1950.
“4. It is the contention of the plaintiff that it used due diligence in the construction of the storage elevator, and although the same was not completed by November 30, 1950, that the failure to complete it was occasioned by the acts of the defendant in delaying in signing the contract and of the defendant’s loaning agencies in failing and neglecting to finally approve the plans and specifications, including the contract, and to advise plaintiff of such approval, and thereby prevented the plaintiff from commencing the construction and from completing the elevator by said date. <
“In this connection you are instructed that the burden is upon the plaintiff to show by a preponderance or greater weight of the evidence that it was delayed in the commencement of the construction of said storage elevator by these acts of the defendant, and that it did use due diligence.
“It is tlie contention of the defendant that any delay in commencing the construction of said storage elevator and in the completion of the same was a result of the plaintiff’s own acts in that it did not start construction as soon as it learned that it had been awarded the contract; that plaintiff was incompetent, inefficient and its equipment inadequate; that it did not pay standard wages and changed superintendents; and that defendant was damaged in the total sum of $8,500.81 on account of the plaintiff’s failure to use reasonable diligence and to have said storage by November 30, 1950.
“In this connection you are instructed that if you find that the plaintiff did not sustain the burden of proving by the preponderance or greater weight of the evidence that it used due diligence in commencing and constructing said storage, then the burden is upon the defendant to show by a preponderance or greater weight of the evidence that it was damaged thereby and the amount of its damage.
“5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'BRIEN v. General Motors Acceptance Corporation
362 P.2d 455 (Wyoming Supreme Court, 1961)
Grigsby v. Jenkins
331 P.2d 284 (Supreme Court of Kansas, 1958)
Unruh v. Kansas Turnpike Authority
313 P.2d 286 (Supreme Court of Kansas, 1957)
Beye v. Andres
296 P.2d 1049 (Supreme Court of Kansas, 1956)
King v. Vets Cab, Inc.
295 P.2d 605 (Supreme Court of Kansas, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
252 P.2d 893, 173 Kan. 763, 1953 Kan. LEXIS 250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-sampson-construction-co-v-casterline-grain-seed-inc-kan-1953.