Johnson Controls, Inc. v. Rowland Tompkins Corp.

585 F. Supp. 969
CourtDistrict Court, S.D. New York
DecidedMay 11, 1984
Docket82 Civ. 122 (MJL)
StatusPublished
Cited by6 cases

This text of 585 F. Supp. 969 (Johnson Controls, Inc. v. Rowland Tompkins Corp.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson Controls, Inc. v. Rowland Tompkins Corp., 585 F. Supp. 969 (S.D.N.Y. 1984).

Opinion

MEMORANDUM OPINION AND ORDER

LOWE, District Judge.

BACKGROUND

On July 13, 1983, this Court rendered a Memorandum Opinion and Order addressing three motions in this case. First, was the motion by the Power Authority of the State of New York (PASNY) to dismiss the third-party complaint brought against it by Johnson Controls, Inc. (JCI), the plaintiff and third-party plaintiff in this action, respecting counterclaims asserted against JCI by the defendant Rowland Tompkins Corporation (RTC). The Court denied PAS-NY’s motion, finding that: 1) as a procedural matter, Rule 14(b) of the Federal Rules of Civil Procedure permits a plaintiff to implead a third party who may be liable to him for indemnity or contribution on defendant’s counterclaims; and 2) the plaintiff had stated a claim for indemnity or contribution. PASNY’s motion for rear-gument on this motion is presently pending before the Court and will be considered herein.

The second motion decided in the Court’s July Opinion was RTC’s motion, made pursuant to Rule 13(g) of the Federal Rules of Civil Procedure, for leave to cross-claim against PASNY for contribution or indemnity. The Court denied RTC’s motion on the ground that as a third-party defendant, PASNY was not a “co-party” of the defendants within the meaning of Rule 13(g). RTC subsequently moved to serve a third-party complaint on PASNY pursuant to Rule 14(a), and that motion will also be addressed in the instant Opinion.

The final motion decided by the Court in July was plaintiff’s motion for partial summary judgment, which was denied by the Court on the ground that there were genuine issues of material facts which had to be tried.

FACTS

On November 29, 1978, defendant RTC, the contractor, entered into a contract with *971 PASNY for construction of certain mechanical and electrical work for the Additional Facilities at Indian Point Unit No. 3, located in Buchanan, New York. Defendant Federal Insurance Company (“FIC”), as surety, issued to PASNY, as obligee, a labor and materials bond conditioned for the payment due to all persons furnishing labor and materials to defendant RTC in the prosecution of construction of the project.

On January 15, 1979, defendant RTC subcontracted to JCI the furnishing and installation of all control work required by the plans and specifications for the project. In the subcontract the subcontractor agreed to be bound by all applicable provisions of the prime contract between RTC and PASNY. The prime contract provided that, “Nothing contained in this contract shall create any contractual relation between any subcontractor and the Authority.”

In its complaint JCI alleges that it performed and completed all of the work it was required to do under the subcontract and labor and materials bond, and was then due to receive the adjusted contract price of $766,158.00. JCI received $715,157.00 of that sum, which left a balance of $51,-001.00. JCI alleges that defendant RTC has refused to pay it the money allegedly due and owing. JCI further alleges that defendant RTC breached the contract because it:

(1) prevented JCI from performing its work on time;

(2) hampered, interfered with, retarded, and impeded JCI’s performance in completion of the work; and

(3) failed to properly coordinate the work of the various subcontractors.

JCI submits that because of RTC’s actions, JCI was prevented from performing its work in the normal and economical manner contemplated and otherwise possible, and that it was forced to proceed by haphazard and nonsequential procedures which increased its cost of operations and extended the time of performance. JCI requests $208,849.48 to cover the increased costs, expenses, and damages for labor, materials, equipment, field overhead, and office overhead.

On February 16, 1982, RTC filed an Answer denying any balance due and asserted counterclaims against JCI for $1,034,089.51 in damages allegedly suffered as a result of the “reckless and wrongful” filing of a mechanic’s lien by plaintiff. RTC alleges that JCI caused a mechanic’s lien in the amount of $241,971.51 to be filed against all moneys due, or to become due from PASNY to RTC under the primary contract. Therefore, PASNY was prevented from paying monies due RTC, and as a result defendant RTC was allegedly forced to incur expenses to obtain a bond and an Order discharging said lien and suffered damages in the amount of $34,089.51. RTC also seeks a million dollars in damages for humiliation and injury to its reputation which resulted from the filing of the lien.

JCI then commenced a third-party action against PASNY alleging that if RTC succeeds in its counterclaims regarding the lien, such “will have been caused by reason of the ... Power Authority’s ... failure to pay monies” to RTC, under its contract with PASNY. JCI therefore seeks indemnification or contribution from PASNY. As previously noted, PASNY currently seeks reargument on its motion to dismiss JCI’s third-party claims. In addition, RTC seeks leave to serve a third-party complaint on PASNY seeking contribution or indemnity.

For the reasons set forth below, the Court concludes that RTC should be granted leave to bring a third-party claim for contribution, but not indemnity, against PASNY, and that JCI’s third-party claims against PASNY should be dismissed.

RTC’s Motion to Serve a Third-Party Complaint on PASNY

As mentioned above, JCI, in the main action, seeks to recover final payment allegedly due under its subcontract with RTC and increased and additional costs allegedly arising out of delays and hindrances in the *972 performance of the subcontract work. RTC takes the position that to the extent it is found liable to plaintiff on either of plaintiffs claims, PASNY will be liable to it (RTC) for all or part of the recovery. The claims asserted by RTC against PASNY in the proposed third-party complaint are precisely the same claims as those asserted by JCI against RTC in the main action. RTC emphasizes that since the main claims and the proposed third-party claims arise out of the same construction project and the related transactions and occurrences among the parties, the third-party action will introduce no unrelated issues nor unduly complicate the original suit.

PASNY opposes RTC’s motion to serve a third-party complaint on the ground that under the applicable substantive law (the law of New York), PASNY cannot be liable to RTC for either contribution or indemnity. On the issue of contribution, PASNY argues that because PASNY indisputedly owes no duty to the plaintiff JCI, no claims for contribution may be validly asserted against PASNY by RTC. With respect to indemnity, PASNY contends that such a claim is improper since JCI’s claim against RTC alleges that RTC’s liability arises out of its own wrongdoing, i.e., RTC’s breach of the JCI/RTC subcontract. A claim for indemnity, argues PASNY, arises only where the indemnitor is wholly responsible for the plaintiff's injury and the indemnitee is secondarily liable as a result of his relationship to the active wrongdoer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aetna Casualty & Surety Co. v. Spartan Mechanical Corp.
738 F. Supp. 664 (E.D. New York, 1990)
Epstein v. Haas Securities Corp.
731 F. Supp. 1166 (S.D. New York, 1990)
Minpeco, S.A. v. Conticommodity Services, Inc.
677 F. Supp. 151 (S.D. New York, 1988)
Arden Way Associates v. Boesky
664 F. Supp. 863 (S.D. New York, 1987)
Barrett v. United States
651 F. Supp. 611 (S.D. New York, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
585 F. Supp. 969, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-controls-inc-v-rowland-tompkins-corp-nysd-1984.