John W. Daniel & Co. v. Janaf, Inc.

169 F. Supp. 219, 1958 U.S. Dist. LEXIS 2299
CourtDistrict Court, E.D. Virginia
DecidedMarch 20, 1958
DocketCiv. A. No. 2466
StatusPublished
Cited by4 cases

This text of 169 F. Supp. 219 (John W. Daniel & Co. v. Janaf, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John W. Daniel & Co. v. Janaf, Inc., 169 F. Supp. 219, 1958 U.S. Dist. LEXIS 2299 (E.D. Va. 1958).

Opinion

WALTER E. HOFFMAN, District Judge.

The defendant corporation (hereinafter called Janaf) is, for the purpose of this proceeding, a real estate development company engaged in the construction and sale of numerous houses in a section known as Admiralty Acres, Princess Anne County, Virginia, on property owned by Janaf. Plaintiff (hereinafter referred to as Daniel) is a contractor employed by Janaf for the purpose of performing certain work and furnishing materials in the construction of the houses in said housing project of defendant. It was originally contemplated that Daniel would build approximately thirty houses for Janaf, but by March 1, 1955, when Daniel left the project, only five houses had been completed. In the instant controversy we are not concerned with the reasons for Daniel’s action in not completing the thirty houses as the parties entered into a subsequent contractual agreement dated March 24, 1955, and thereafter entered into an arbitration agreement dated August 1, 1955; the latter being modified by letter dated February 3, 1956, signed by Daniel and Janaf.

When Daniel left the job on or about March 1, 1955, a considerable sum of money was due by Janaf. In order to clarify the understanding between the parties, Daniel wrote a letter to Janaf under date of March 24, 1955, which letter was confirmed and agreed to by Janaf. After reciting that Daniel had furnished materials and performed work in connection with the construction of houses, .streets, water and land improvements on the twelve acre tract known as Admiralty Acres, as well as land improvements on an adjoining tract, the contract provides in part as follows:

“2. All work performed and materials furnished by us in the past or in the future have been and shall be on the basis of cost plus six percent profit. The word ‘cost’ includes the actual cost of labor, material, subcontracts and equipment rental, and in addition thereto a sum equal to ten percent of our payroll for insurance and social security on wages, a sum equal to two percent of our payroll for office overhead, a sum equal to one percent of the material purchased, and a one and one-half percent markup on subcontracts and equipment rental. In allocating costs to a single house there shall be included, on a footage basis, a proportionate part of the costs incurred in connection with the street, water and land improvements.
“3. As of February 1, 1955, you were indebted to us in the approximate amount of $101,715.87, together with a 6% profit thereon, aggre[221]*221gating approximately $107,818.82. Unless said amount is paid in full on or before May 1, 1955, the unpaid balance thereof will bear interest at 6% per annum from May 1, 1955, until paid. Bills for costs (and profit thereon) incurred after February 1, 1955, are due and payable when presented, and if not paid within sixty days after presentment shall bear interest at the rate of 6% per annum from said sixty-day period until paid.
“4. We shall furnish such assistance in supervising and advising as is reasonably necessary to the completion of the houses on the 12-Acre Tract, and we shall have the privilege of maintaining a supervisor on the job. In addition thereto, until the construction of said houses (approximately 30) is completed, we shall advance such construction costs (on a cost plus 6% profit, as aforesaid) as will be reasonably necessary to effect the completion of said houses, provided, however, that we shall not be obligated to make any further advances unless (a) all costs, expenses, contracts and subcontracts, relating to any house in respect of which we are asked to make advances shall have been approved by us, and (b) the proposed advance, together with all other such advances made by us after the date hereof will not exceed two-thirds of the aggregate amount which we have been paid by you to the date of the proposed advance.
**#•**#
“6. All obligations hereunder shall be fully satisfied when we have been paid all sums owing us to date, in accordance with this agreement.
•X- ¿r ■i? . ■X* ‘X- •X’
“8. This letter contains the entire agreement existing between us and supersedes and annuls any and all prior agreements.”

During April, 1955, Janaf paid Daniel the sum of $10,000. No further payments were made and the arbitration agreement was subsequently entered into on August 1, 1955 1.

The arbitration agreement recites that Daniel claims an indebtedness in the sum of $136,328.86 for which it had filed a mechanic’s lien against Janaf’s property; that Janaf, while not admitting the indebtedness, agreed to pay $90,000 unconditionally, and the balance of said claim conditionally; that the mechanic’s lien would be released by Daniel and all rights to enforce same waived; and that the claim would be satisfied as follows:

(1) Janaf to give a note dated May 1, 1955, in the sum of $57,-000.00, plus interest, payable on November 1, 1955, secured by a deed of trust on certain of Janaf’s property.
(2) Janaf to give a note dated May 1, 1955, in the sum of $33,000.-00, plus interest, payable on January 1, 1956, secured by a deed of trust on certain of Janaf’s property.
(3) Janaf to give a note dated May 1, 1955, in the sum of $46,328.-86, plus interest, payable on January 1, 1956, secured by a deed of trust on certain of Janaf's property; but the due date and amount due, if any, under this note is made specifically subject to arbitration as specified in said agreement.

The agreement provides for the appointment of two arbitrators, one by each party, with the arbitrators appointing an umpire. It is further stated:

“The two arbitrators and umpire shall constitute a Board of Arbitration, shall review Daniel’s entire claim of $136,328.86, and shall deter[222]*222mine what part thereof (if less than all) is properly due and owing. If, after allowing the credits provided for in subparagraph (a) of this paragraph, the Board of Arbitration finds that less than $136,328.86 (adjusted for said credits) is properly due and owing, the difference between $136,328.86 (as adjusted) and the amount determined by the Board of Arbitration, whose determination shall be conclusive upon the parties hereto, shall be charged against the Arbitrable Balance, and the amount actually payable under the $46,328.-86 note shall be deemed reduced accordingly ; but if such difference exceeds the Arbitrable Balance, such excess shall be ignored, it being expressly understood and agreed that said notes of $57,000 and $33,000, aggregating $90,000, are absolutely payable hereunder, only the Arbitra-ble Balance being subject to adjustment by arbitration.”

It is likewise specified that if the Board did not arrive at a decision on or before January 1, 1956, the due date for payment of the $46,328.86 note would be postponed until the Board rendered its decision, and if the decision was not rendered by February 1, 1956, a new umpire would be appointed every thirty days until a decision was made. The parties also agreed that, subject to certain exceptions not pertinent herein, all the rights and obligations against and to each other were settled by the agreement, and that each party released the other from all claims, of every kind and nature, in respect of any matter theretofore transpiring between them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prudential-Bache Securities, Inc. v. U.S. Optical Frame Co.
534 So. 2d 793 (District Court of Appeal of Florida, 1988)
Rushton v. Howard Sober, Inc.
198 F. Supp. 337 (W.D. Michigan, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
169 F. Supp. 219, 1958 U.S. Dist. LEXIS 2299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-w-daniel-co-v-janaf-inc-vaed-1958.