Kinetic Systems v. Ri Industrial Facilities Corp., 02-0616 (2003)

CourtSuperior Court of Rhode Island
DecidedAugust 1, 2003
DocketM.P. No. KM 02-0616
StatusPublished

This text of Kinetic Systems v. Ri Industrial Facilities Corp., 02-0616 (2003) (Kinetic Systems v. Ri Industrial Facilities Corp., 02-0616 (2003)) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kinetic Systems v. Ri Industrial Facilities Corp., 02-0616 (2003), (R.I. Ct. App. 2003).

Opinion

DECISION
Plaintiff, Kinetic Systems, Inc. ("Kinetic") filed a petition to enforce a mechanics' lien against the Defendants, Rhode Island Industrial Facilities Corporation ("RIIFC") and Rhodes Technologies, Inc. ("Rhodes"). Kinetic seeks to recover for work done and materials furnished to RIIFC, the owner, and Rhodes, the lessee, in connection with contractual work performed on the project known as the "Building 5 Expansion Project" located at 498 Washington Street, Coventry, RI. ("Project"). This Project encompassed a multi-million dollar pharmaceutical plant expansion, originally estimated to cost approximately $30 million, but which eventually exceeded $90 million. Kinetic provided certain process piping work on the Project, which was originally estimated to cost approximately $10.8 million but which eventually exceeded $18 million.

The Defendants answered the case and asserted two counterclaims alleging breach of contract and fraud and misrepresentation. Kinetic answered the counterclaim and amended its complaint to add claims for breach of contract and quantum meruit. All such matters were tried before the Court over several weeks during the period from January through May of 2003.

The Court will address the various theories of recovery in the following order:

• Kinetic's mechanics' lien petition against Defendants.

• Kinetic's breach of contract and quantum meruit claims against Rhodes.

• Rhodes' breach of contract and fraud and misrepresentation claims against Kinetic.

I. KINETIC'S MECHANICS' LIEN PETITION AGAINST DEFENDANTS
Rhodes challenges the constitutionality of the Rhode Island Mechanics' Lien statute, R.I.G.L. 34-28-1, et seq. ("Mechanics' Lien Statute"). Rhodes relies on the decision of the Honorable Michael Silverstein inSells/Green bldg. Co., Inc. v. Rossi, C.A. No. PB 02-1019, consolidated with Gem Plumbing Heating Co., Inc. v. Rossi, C.A. No. PB 02-2778 (R.I. Super. Ct. April 23, 2003). In that decision, Judge Silverstein found that the Mechanics' Lien Statute lacks a provision for a hearing to determine the validity of a lien until after the filing of a petition, implicates a significant private property interest, and represents a substantial risk of erroneous deprivation of said interest. Relying on those conclusions and pertinent holdings of the United States Supreme Court, Judge Silverstein held that the Mechanics' Lien Statute is unconstitutional beyond a reasonable doubt. Sells/Green Bldg. Co., Inc. at 28. This Court agrees with Judge Silverstein's well-reasoned decision and finds that the Mechanics' Lien Statute is unconstitutional in derogation of the United States Constitution and Rhode Island Constitution.

II. KINETIC'S BREACH OF CONTRACT AND QUANTUM MERUIT CLAIMS AGAINST RHODES
A. TYPE OF CONTRACT

Kinetic and Rhodes entered into a contract ("Contract") in connection with the Project. (Exhibit K-7B.) It is clear that the Contract is a cost-reimbursable time and materials contract. The Contract did contemplate that the Project could be converted to a lump sum or guaranteed maximum price contract ("GMAX"). Such conversion, however, never occurred, largely due to Rhode's refusal to negotiate or accept such a contract. The Contract did contain a target price, so-called, but the contract language made it clear that such price was in fact an estimate that would not account for factors outside Kinetic's control. (Exhibit K-7B, section 3.2.1.)

Rhodes' attempt to rebut the cost-reimbursable time and materials payment provisions set forth in the Contract is not persuasive. The testimony of Dan Flood ("Flood"), a Kinetic official, supports the contention that the Contract was never converted from a cost-reimbursable time and material basis. His testimony suggests that the reason a lump sum provision was not negotiated was because Rhodes wished to avoid a project on which it might be required to pay a bonus. Rhodes attempts to suggest that the word "target price" as used in the contract has special meaning. Rodney Cameron ("Cameron"), an expert engaged by Rhodes who had also provided services to SUITT Construction Company ("SUITT"), one of two construction managers used by Rhodes on the project, expressed the view that target price means something more than "estimate." That line of testimony was vague and affords no basis for departing from the clear language of the Contract, which established payment on a cost-reimbursable time and materials basis.

B. RHODE'S ACTIONS THAT IMPACTED KINETIC'S PERFORMANCE
Several actions by Rhodes and/or it agents during the course of the Project negatively impacted Kinetic's performance under the Contract.

(1) Delivery of the Project Design and Structure

Rhodes initially contracted with PFI Construction Corporation ("PFI") as a construction manager for the Project to perform all engineering, procurement, and construction management ("EPCM"). Rhodes, however, opted to engage PFI without a written contract outlining PFI's duties and obligations. PFI never completed the design, which was supposed to have been provided to Kinetic in September of 2000. As a result, Kinetic had to complete a substantial portion of the design documents. These documents were not completed until November of 2001, over a year late. Kinetic's original work plan of having all isometric drawings ("Isometrics") to offsite piping fabricators so that all piping could be fabricated and returned to the site before installation was thereby thwarted. (Exhibit K-167). Kinetic was thus projected into a reactive mode where it could install only what was delivered as it was delivered.

The late delivery of the building structure several months after the planned completion date had an equally negative impact on Kinetic's original work plan. The lack of structure caused many practical problems, including the need to tent around and create ambient warmth prior to welding joints. Moreover, because the building's civil, structural and architectural elements ("Building Elements") had not been completed in a timely manner, Kinetic was prevented from field verifying Isometrics prior to fabrication. Repeated references in the Contract to field verification of the isometric drawings make it clear that the parties intended that the existing structural conditions would be in place to allow field verification. Again, rather than being able to proceed in an orderly fashion, Kinetic was compelled to proceed reactively where it could install only in those areas to which it could gain access, such areas often being crowded with tradesmen other than its own pipefitters.

(2) Rhodes' Replacement of the EPCM Manager

Rhodes' EPCM problems were exacerbated by its decision to change construction managers during the course of the Project. PFI initially held all authority over EPCM, which, as previously noted, was originally estimated at $30 million, but eventually exceeded $90 million. Rhodes, also as previously noted, never entered into a written agreement with PFI to define its responsibilities or obligations. By February of 2001, with the delivery of the Building Elements already several months late, Rhodes began to consider PFI's termination. James Becica ("Becica"), a Rhodes' consultant, acknowledged that a delay of three to six months might ensue if in fact PFI were replaced with another contractor. (Exhibit K-140/Exhibit K-169, Becica Presentation, p. 45).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schiro-Del Bianco Enterprises v. Nsl
765 So. 2d 1087 (Louisiana Court of Appeal, 2000)
Walsh Services, Inc. v. Feek
274 P.2d 117 (Washington Supreme Court, 1954)
Centerville Builders, Inc. v. Wynne
683 A.2d 1340 (Supreme Court of Rhode Island, 1996)
Fondedile, S.A. v. C.E. Maguire, Inc.
610 A.2d 87 (Supreme Court of Rhode Island, 1992)
Joe Bonura, Inc. v. Hiern
419 So. 2d 25 (Louisiana Court of Appeal, 1982)
Travers v. Spidell
682 A.2d 471 (Supreme Court of Rhode Island, 1996)
Cliftex Clothing Co. v. Di Santo
148 A.2d 273 (Supreme Court of Rhode Island, 1959)
John W. Daniel & Co. v. Janaf, Inc.
169 F. Supp. 219 (E.D. Virginia, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
Kinetic Systems v. Ri Industrial Facilities Corp., 02-0616 (2003), Counsel Stack Legal Research, https://law.counselstack.com/opinion/kinetic-systems-v-ri-industrial-facilities-corp-02-0616-2003-risuperct-2003.