John Allen Construction, LLC v. Jerome Hancock, Sandra Hancock, and Carroll Bank and Trust

CourtCourt of Appeals of Tennessee
DecidedMarch 31, 2010
DocketW2008-02785-COA-R3-CV
StatusPublished

This text of John Allen Construction, LLC v. Jerome Hancock, Sandra Hancock, and Carroll Bank and Trust (John Allen Construction, LLC v. Jerome Hancock, Sandra Hancock, and Carroll Bank and Trust) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Allen Construction, LLC v. Jerome Hancock, Sandra Hancock, and Carroll Bank and Trust, (Tenn. Ct. App. 2010).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON January 21, 2010 Session

JOHN ALLEN CONSTRUCTION, LLC v. JEROME HANCOCK, SANDRA HANCOCK, and CARROLL BANK AND TRUST

Appeal from the Chancery Court for Benton County No. 00-195 Ron Harmon, Chancellor

No. W2008-02785-COA-R3-CV - Filed March 31, 2010

This is a construction case. The defendant landowners entered into an oral contract with the plaintiff contractor to construct a house. When the house was substantially completed, the homeowners terminated the builder, citing defective work. At the time of termination, there were two unpaid invoices. After filing a notice of lien on the landowners’ property, the contractor filed suit for breach of contract and to enforce the lien. The landowners counterclaimed for breach of contract and sought damages stemming from the defective work. After a trial, the trial court entered judgment for the contractor and awarded a portion of the amount sought. The trial court’s order did not address enforcement of the contractor’s lien. The landowners appeal. Because the trial court’s order does not address, among other things, enforcement of the lien, it is not a final judgment, and this Court does not have jurisdiction over the appeal. Therefore, we dismiss the appeal and remand the case to the trial court for further proceedings.

Tenn. R. App. P. 3 Appeal as of Right; Appeal Dismissed and Case Remanded

H OLLY M. K IRBY, J., delivered the opinion of the Court, in which A LAN E. H IGHERS, P.J., W.S., and J. S TEVEN S TAFFORD, J, joined.

J. Brad Scarbrough, Brentwood, Tennessee, for the Defendant/Appellants, Jerome Hancock and Sandra Hancock

John W. Whitworth, Camden, Tennessee, for the Plaintiff/Appellee, John Allen Construction, LLC MEMORANDUM OPINION 1

F ACTS AND P ROCEEDINGS B ELOW

This is the second appeal in a case adjudicating a dispute arising from an oral contract to construct a home. See John Allen Constr., LLC v. Hancock, No. W2004-02920-COA-R3- CV, 2006 WL 473732 (Tenn. Ct. App. Mar. 1, 2006).

In August 1999, Defendant/Appellants Jerome Hancock (“Mr. Hancock”) and his wife Sandra Hancock (“Mrs. Hancock,” collectively “Hancocks”) contacted John Allen (“Mr. Allen”), the managing member of Plaintiff/Appellee John Allen Construction, LLC,2 to inquire about the construction of a house on their property. The Hancocks owned a nearly one acre unimproved tract of land in Big Sandy, Tennessee. The tract includes a steep hill facing a lake, and the Hancocks wanted a luxury lakeside home constructed on the slope of the hill.

Mr. Allen is a second generation carpenter who has worked in the construction industry throughout his career. In 1991, he obtained his contractor’s license and founded his own construction company, performing commercial and residential work. Despite the fact that Mr. Allen’s work included the “niche market” of custom lakeside homes, when he was contacted by Mr. Hancock, Mr. Allen’s contractor’s license was limited to projects costing $110,000 or less.

Not long after their initial contact, Mr. Hancock and Mr. Allen met on Mr. Hancock’s lakefront property to discuss the construction project. Mr. Hancock brought a house plan catalogue to the meeting to show Mr. Allen the type of house he wanted to have constructed on the lot. After examining the basic floor plan in the catalogue, Mr. Allen told Mr. Hancock that he could construct the house in the plan. At Mr. Hancock’s direction, Mr. Allen then ordered the complete house plan from the catalogue.

1 Rule 10. Memorandum Opinion

This Court, with the concurrence of all judges participating in the case, may affirm, reverse or modify the actions of the trial court by memorandum opinion when a formal opinion would have no precedential value. When a case is decided by memorandum opinion it shall be designated “MEMORANDUM OPINION”, shall not be published, and shall not be cited or relied on for any reason in any unrelated case.

TENN . CT . APP . R. 10. 2 This Opinion will use “Mr. Allen” in reference to both John Allen and John Allen Construction, LLC.

-2- The next month, September 1999, Mr. Allen met with Mr. Hancock and Mrs. Hancock. They toured houses that Mr. Allen was constructing at the time, and then went to Mr. Allen’s home to discuss the construction of the Hancocks’ lakefront house. At this second meeting, the parties reached the agreement central to this dispute. After making some modifications to the house plans,3 the parties entered into an oral agreement that Mr. Allen would build the house for the Hancocks, anticipating that construction would be completed by May 2000. Under the oral agreement, the parties agreed that Mr. Allen would bill the Hancocks monthly for the cost of his materials and labor plus an eight percent profit. There was some discussion of the cost of construction totaling $250,000.

In October 1999, construction of the Hancocks’ house began. The side of the hill was cut so as to allow the side of the house facing the lake to stand three stories high, with two stories on the opposite side, or “streetside.” Concrete footings were poured, and the walls of the house were made from concrete poured into commercially designed Styrofoam molds. Later, a wooden flooring system was installed and connected to the concrete walls, and a conventional roof was erected over the structure.

As a prerequisite to obtaining financing for construction near the end of 1999, Mr. Hancock obtained an insurance policy with coverage in the amount of $250,000, with coverage beginning in January 2000. In December 1999, Mr. Hancock apparently obtained a $300,000 loan, secured by a deed of trust, from Carroll Bank and Trust to finance the construction. In February 2000, Mr. Allen had the monetary limit on his contractor’s license raised from $110,000 to $900,000.

Meanwhile, construction on the house continued. Each month, Mr. Allen sent an itemized billing statement to the Hancocks detailing the material and labor expenses for the preceding month. For each monthly statement, Mr. Allen attached photocopies of the material suppliers’ invoices that he had paid and time sheets showing the labor costs for his workers. Each monthly statement also contained the agreed-upon eight percent profit. The Hancocks timely paid each billing statement through the summer of 2000.

By May 2000, the billing statements totaled over $175,000,4 but the construction was not completed. Dismayed at the perceived delay and ballooning cost, Mr. Hancock met with Mr. Allen to discuss the status of the construction. At the May 2000 meeting, Mr. Allen

3 The parties’ testimony conflicts as to whether Mr. Allen had received the complete plans by the time the September 1999 meeting occurred. 4 This number is derived from the billing statements for December 1999 through May 2000 contained in the record.

-3- acknowledged that the project was taking longer than anticipated. When pressed by Mr. Hancock for a total cost of completion, Mr. Allen estimated that it would take an additional $100,000 to finish the house. After the meeting, the parties continued as they had previously: Mr. Allen continued construction and monthly billing, and the Hancocks timely paid his invoice each month.

In July 2000, workers installing drywall in the interior of the house told Mr. Hancock that they had encountered difficulties in the kitchen stemming from problems related to the construction of the ceiling. After that, Mr. Hancock met with Mr. Allen to discuss the kitchen and another issue pertaining to the position of a window in the study. After the meeting, Mr. Allen addressed Mr. Hancock’s concerns by reinforcing ceiling joists in the kitchen and adjusting the study window to ensure that it lay in a straight plane with the wall. Construction continued.

In September 2000, Mr. Hancock terminated Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

COLUMBUS MEDICAL SERVICES, LLC v. Thomas
308 S.W.3d 368 (Court of Appeals of Tennessee, 2009)
Nutt v. Champion International Corp.
980 S.W.2d 365 (Tennessee Supreme Court, 1998)
Hicks v. Cox
978 S.W.2d 544 (Court of Appeals of Tennessee, 1998)
McCormick v. Aabakus Inc.
101 S.W.3d 60 (Tennessee Supreme Court, 2000)
Nashville Ford Tractor, Inc. v. Great American Insurance Co.
194 S.W.3d 415 (Court of Appeals of Tennessee, 2005)
Wells v. Tennessee Board of Regents
9 S.W.3d 779 (Tennessee Supreme Court, 1999)
Johnson v. Johnson
37 S.W.3d 892 (Tennessee Supreme Court, 2001)
Bayberry Associates v. Jones
783 S.W.2d 553 (Tennessee Supreme Court, 1990)
Landers v. Jones
872 S.W.2d 674 (Tennessee Supreme Court, 1994)
Meighan v. U.S. Sprint Communications Co.
924 S.W.2d 632 (Tennessee Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
John Allen Construction, LLC v. Jerome Hancock, Sandra Hancock, and Carroll Bank and Trust, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-allen-construction-llc-v-jerome-hancock-sandr-tennctapp-2010.