Jocelyn Rouse v. City of Pittsburgh

CourtCourt of Appeals for the Third Circuit
DecidedMarch 23, 2018
Docket17-2587
StatusUnpublished

This text of Jocelyn Rouse v. City of Pittsburgh (Jocelyn Rouse v. City of Pittsburgh) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jocelyn Rouse v. City of Pittsburgh, (3d Cir. 2018).

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT ________________

No. 17-2587 ________________

JOCELYN ROUSE, an adult individual; ROAC, INC., a Pennsylvania Corporation,

Appellants

v.

CITY OF PITTSBURGH; MAURA KENNEDY, Director of the City of Pittsburgh’s Department of Permits, Licenses and Inspections ________________

Appeal from the United States District Court for the Western District of Pennsylvania (Civ. Action No. 2:16-cv-00608) District Judge: Honorable Nora B. Fischer ________________

Submitted Under Third Circuit L.A.R. 34.1(a) March 15, 2018

Before: JORDAN, SHWARTZ, and KRAUSE, Circuit Judges

(Opinion filed: March 23, 2018) ________________

OPINION* ________________

* This disposition is not an opinion of the full Court and pursuant to I.O.P. 5.7 does not constitute binding precedent. KRAUSE, Circuit Judge

Appellants ROAC, Inc. and Jocelyn Rouse, ROAC’s Vice-President (collectively

“ROAC”), appeal the District Court’s grant of summary judgment in favor of the City of

Pittsburgh and Maura Kennedy (collectively “the City”), contending they were arbitrarily

debarred without process by the City in violation of both the Due Process Clause and the

Equal Protection Clause. We perceive no error in the District Court’s ruling and

therefore will affirm.

I. Background

ROAC is a minority-owned demolition contractor licensed by the City that, in

November 2015, “caused damage” to the wrong building while carrying out a demolition

contract. Appellants’ Br. 3. Following the incident, ROAC completed other demolition

contracts for the City that it had already been awarded, but over the next several months,

despite submitting the lowest bid on several new projects, ROAC was not awarded any

new contracts by the City. Throughout those months, ROAC contacted the City to ask

why it was not winning any contracts, and while that inquiry did initiate a string of

internal communications among City employees relating to ROAC’s status as “not a

responsible bidder,” App. 180, none of those employees advised ROAC of that status or

otherwise explained to ROAC why its bids were failing.

Understandably frustrated at the lack of response, ROAC filed a complaint in the

Allegheny County Court of Common Pleas, alleging that the City had arbitrarily and

unlawfully debarred ROAC, and that in doing so the City discriminated against ROAC.

Four days after the complaint was filed, the City finally sent ROAC a letter explaining

2 that ROAC had not been debarred, but rather had been deemed a “non-responsible

contractor.” App. 98. The City subsequently removed to the District Court for the

Western District of Pennsylvania, and the parties filed cross-motions for summary

judgment; the District Court granted summary judgment in favor of the City.

This appeal followed.

II. Jurisdiction and Standard of Review

The District Court had jurisdiction under 28 U.S.C. § 1331, and we have

jurisdiction under 28 U.S.C. § 1291. We exercise plenary review over a district court’s

grant of summary judgment.1 Reedy v. Evanson, 615 F.3d 197, 210 (3d Cir. 2010).

Summary judgment is appropriate “if the movant shows that there is no genuine dispute

as to any material fact and the movant is entitled to judgment as a matter of law,” Thomas

v. Cumberland County, 749 F.3d 217, 222 (3d Cir. 2014) (quoting Fed. R. Civ. P. 56(a)),

and we “view the record in the light most favorable to the non-moving party,” id. We

may affirm the District Court based on “any ground supported by the record.” Azubuko

v. Royal, 443 F.3d 302, 303 (3d Cir. 2006) (per curiam).

III. Discussion

On appeal, ROAC contends that the District Court erred in concluding that:

(1) ROAC was not arbitrarily debarred without the process to which it was entitled; and

1 ROAC also purports to appeal the District Court’s denial of ROAC’s motion for partial summary judgment, but because a denial of summary judgment is not a “final decision[],” we lack jurisdiction to review it. See Rivas v. City of Passaic, 365 F.3d 181, 191 (3d Cir. 2004).

3 (2) ROAC failed to establish it was discriminated against based on race, or based on any

other reason.2 We address these issues in turn.

A. Arbitrary Debarment and Due Process

The District Court concluded that ROAC lacked standing to bring a due process

challenge because, under Pennsylvania law, “one who bids on a public contract has no

legitimate expectation of receiving it until the contract is actually awarded,” and therefore

ROAC “ha[d] not been deprived of a property interest that warrants procedural due

process protection.” Rouse v. City of Pittsburgh, No. 16-608, 2017 WL 2672291, at *5

(W.D. Pa. June 21, 2017) (quoting Indep. Enters. Inc. v. Pittsburgh Water & Sewer Auth.,

103 F.3d 1165, 1178 (3d Cir. 1997)). ROAC contends that, because the City deemed it a

non-responsible bidder based on a “one-time determination that applied to all future City

contracts,” ROAC was constructively debarred and its standing is revived. Appellants’

Br. 19; see Berlanti v. Bodman, 780 F.2d 296, 300 (3d Cir. 1985) (concluding that New

Jersey law creates “a property interest in not being arbitrarily debarred . . . [that] entitled

[a contractor] to some procedural protection under the due process clause”). ROAC’s

claim fails, however, because it was not debarred, constructively or otherwise.

Under the Pittsburgh City Code, debarment prevents a contractor “from bidding on

and participating in City contracts.” Pittsburgh City Code § 161.22(b). Debarment

2 ROAC also claims on appeal that the District Court erred in concluding that the due process claim was not ripe and that Maura Kennedy was entitled to qualified immunity. Because we conclude ROAC was not debarred, we need not reach the ripeness issue. And because we determine that ROAC failed to establish a genuine dispute of material fact with respect to the underlying constitutional issues, we need not reach the question of qualified immunity. 4 occurs for a “definitely stated period of time,” id. § 161.22(d)(3), is imposed subject to a

variety of procedural safeguards, id. § 161.22(e), and requires the “termination” of

contracts entered into with a debarred entity, id. § 161.22(g). But ROAC, by its own

admission, was not prevented from bidding on subsequent contracts, and it continued to

work on City contracts even after it claims to have been debarred. Likewise, ROAC was

not prevented from winning a contract for a fixed period of time; rather, as the City

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reedy v. Evanson
615 F.3d 197 (Third Circuit, 2010)
Kierski v. Township of Robinson
810 A.2d 196 (Commonwealth Court of Pennsylvania, 2002)
Lawrence Thomas v. Cumberland County
749 F.3d 217 (Third Circuit, 2014)
Rivas v. City of Passaic
365 F.3d 181 (Third Circuit, 2004)
Hill v. City of Scranton
411 F.3d 118 (Third Circuit, 2005)
Berlanti v. Bodman
780 F.2d 296 (Third Circuit, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
Jocelyn Rouse v. City of Pittsburgh, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jocelyn-rouse-v-city-of-pittsburgh-ca3-2018.