J.L. Manta, Inc. v. Braun

376 N.W.2d 466
CourtCourt of Appeals of Minnesota
DecidedJanuary 17, 1986
DocketC1-85-821, C4-85-957
StatusPublished
Cited by3 cases

This text of 376 N.W.2d 466 (J.L. Manta, Inc. v. Braun) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.L. Manta, Inc. v. Braun, 376 N.W.2d 466 (Mich. Ct. App. 1986).

Opinion

OPINION

HUSPENI, Judge.

The Commissioners of the Departments of Transportation and Administration (the State) and Rainbow, Inc. appeal from an order permanently enjoining the State from awarding a specific bridge painting contract to any person or business other than Manta, Inc. and from rejecting all bids for the project. The State and Rainbow contend that the trial court erroneously applied MinmStat. § 16B.09, subd. 2 (1984), and that it is without authority to enjoin the State from awarding the contract to any person or business other than Manta and from rejecting all bids. We affirm in part and reverse in part.

FACTS

The Minnesota Commissioner of Transportation advertised for bids on a bridge painting project. Manta and Rainbow were among the contractors who submitted bids, which were publicly opened on March 22, 1985. Manta had the lowest bid at $301,-749. Rainbow’s was the next lowest bid at $332,100. Manta’s bid contained two altered prices on. line three of the bid form. Manta’s price bid for traffic control during the painting project was originally $4,088 but was changed by a Manta vice president to $4,082 in both the unit price and the extended price columns on the bid form. The numeral “2” was written over the “8” in both columns. The changes were made before the bid was submitted. Neither change was initialed. There was no change in the total bid price.

Manta’s bid was rejected by the Commissioner because line three was altered without proper acknowledgment. The State accepted Rainbow’s bid of $332,215. Before *468 the contract was executed with Rainbow, Manta sought injunctive relief and a writ of mandamus. Rainbow intervened. The trial court found that Manta’s bid was clear but did not comply with the technical requirements of specification 1206 of the State’s Standard Specifications for Construction (1983) because the changes on the bid were neither crossed out nor initialed by the person signing the bid. It also found that the alteration was made in good faith and for the purpose of submitting a correct bid. Finally, it found that Manta substantially complied with the bidding requirements and the State’s refusal to award the contract to Manta was arbitrary and unreasonable.

The trial court permanently enjoined the State both from entering into a contract for painting the bridge with a person or business other than Manta and from rejecting all bids for the project. In its accompanying memorandum, the court noted that, if Manta had not corrected its bid, the State would have done so by changing the total just as it changed the total in Rainbow’s bid because of error. It cited the State’s failure to call Manta in to permit it to make a proper alteration and the State’s alteration of Rainbow’s bid as evidence of arbitrariness.

ISSUES

1. Does the evidence support the trial court’s conclusion that the State was arbitrary in its treatment of Manta’s and Rainbow’s bids?

2. Does the trial court have the authority to enjoin the State from awarding the contract to any person or business other than Manta?

3. Does the trial court have the authority to enjoin the State from rejecting all bids?

ANALYSIS

1. Regardless of the method used when letting public contracts, it is for the courts to determine whether officials in the exercise of their discretion have applied the method used in an arbitrary, capricious or unreasonable manner. Griswold v. Ramsey County, 242 Minn. 529, 535, 65 N.W.2d 647, 651-52 (1954). In this case the trial court concluded that the State was arbitrary in the way it treated the bid alterations. We agree.

Minn.Stat. § 16B.09, subd. 2 governs alterations in bids. That subdivision provides:

A bid containing an alteration or erasure of any price contained in the bid which is used in determining the lowest responsible bid must be rejected unless the alteration or erasure is corrected pursuant to this subdivision. An alteration or erasure may be crossed out and the correction printed in ink or typewritten adjacent to it and initialed in ink by the person signing the bid.

MinmStat. § 16B.09, subd. 2 (1984). The same restrictions are incorporated into specifications 1206 and 1301 of the State’s Standard Specifications for Construction (1983).

Manta’s bid was altered in two spots on line three of the bid form. A number “2” was superimposed on the number “8” altering the unit price bid for traffic control from $4,088 to $4,082. The same alteration was made to the extended price. The corrected extended price plus the extended prices on lines one and two equaled the bid subtotal of $301,749. Thus, Manta conformed its unit prices and extended prices to the subtotal which remained unchanged. The bid was rejected because the change was not acknowledged as required by Minn.Stat. § 16B.09, subd. 2.

Rainbow’s bid was $332,100. When Rainbow submitted its bid, the spaces for the unit price bid for mobilization and traffic control were left blank on the bid form. After the bids were read, State personnel filled in the blank spaces with the amounts which were listed in the extended amount bid column for mobilization and traffic control. State personnel also crossed out the amount listed for painting and filled in a new amount above the crossed-out figure. The State made this change because Rain *469 bow provided an estimate of square footage which was less than that called for in the specifications and thus, the extended amount for painting was understated by $115. The total bid amount was also changed to reflect the change in the amount for painting. Rainbow’s bid was accepted.

The trial court found that Manta made its alterations in good faith and for the purpose of submitting a correct bid. Since the amount changed on Manta’s bid was merely $6 on a bid of over $300,000 and the next nearest bid was for over $30,000 more, the change was de minimus. “De minimus in the law has always been taken to mean trifles — matters of few dollars or less.” Hehl v. Chippewa & Red Cedar Valley Carpenters' District Council, 4 Wisc.2d 629, 635, 91 N.W.2d 226, 229 (1958) (quoting National Labor Relations Board v. Suburban Lumber Co., 121 F.2d 829, 832 (3rd Cir.), cert. denied, 314 U.S. 693, 62 S.Ct. 364, 86 L.Ed. 554 (1941)). Six dollars is a matter of a few dollars.

State personnel changed Rainbow’s bid by $115 dollars. By making that change, State personnel converted a technically nonresponsive bid into a responsive one. State personnel also filled in the unit price which is the governing price in state highway bids. None of these changes are permitted under Minn.Stat. § 16B.09, subd. 2, because none of them were initialed by the person signing the bid.

Rainbow argues that the State’s actions after bid opening were not impermissible alterations, rather its actions were permitted by section 1301 of the specifications. This section states in part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Willoughby v. Grim
1998 SD 68 (South Dakota Supreme Court, 1998)
J.L. Manta, Inc. v. Braun
393 N.W.2d 490 (Supreme Court of Minnesota, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
376 N.W.2d 466, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jl-manta-inc-v-braun-minnctapp-1986.