J.I. Hass Company, Inc. v. Jones-Teer

755 F.2d 1264
Court of Appeals for the Sixth Circuit·Decided March 6, 1985·No. 83-5719·Published

Opinion

755 F.2d 1264

J.I. HASS COMPANY, INC., and Seaboard Surety Company,
Plaintiffs-Appellees, Cross-Appellants,
v.
JONES-TEER, a joint venture of J.A. Jones Construction Co.,
and Nello L. Teer Co., Defendants-Appellants,
Cross-Appellees,
and
American States Insurance Co., Defendant-Cross-Appellee.

Nos. 83-5719, 83-5761.

United States Court of Appeals,
Sixth Circuit.

Argued Nov. 27, 1984.
Decided March 6, 1985.

John B. Tacke (argued), Hudson, Creyke, Koehler & Tacke, Washington, D.C., Richard C. Roberts, Whitlow, Roberts, Houston & Russell, Paducah, Ky., for defendants-appellants, cross-appellees.

Alan W. Roles, Louisville, Ky., Robert S. Peckar (argued) Peckar & Abramson, Bruce D. Meller, Lawrence Levey, Hackensack, N.J., for plaintiffs-appellees, cross-appellants.

John David Cole (argued) Cole, Harned & Broderick Bowling Green, Ky., for defendant-cross-appellee.

Before EDWARDS* and KEITH, Circuit Judges, and PHILLIPS, Senior Circuit Judge.

PHILLIPS, Senior Circuit Judge.

This breach of contract litigation arose out of the construction by the United States Army Corps of Engineers of the Smithland Dam on the Ohio River, at Smithland, Kentucky. The prime contractor was Jones-Teer, a joint venture of the J.A. Jones Construction Company and Nello L. Teer Co., Inc. Jones-Teer was required by the provisions of its contract to do all work necessary to complete the project.

This case involves a subcontract between Jones-Teer and J.I. Hass Company (Hass) providing for the painting by Hass of the steel gates of the dam.

* Jones-Teer originally had engaged All-State Contracting Company to paint the gates. All-State commenced the painting work in 1977 and continued until the end of the painting season in 1978. All-State and Jones-Teer had a dispute concerning the performance of All-State's work and All-State removed itself from the project.1 Hass contracted to do the painting job for $471,000.00. After Hass began painting, defects were discovered in painting work done by All-State. The Corps of Engineers required performance of a considerable amount of remedial work. Hass contended that it was entitled to extra compensation for corrective work. Jones-Teer declined to pay the claims of Hass for additional compensation, upon the ground that the subcontract required Hass to complete all the painting at its own expense.

Hass contends that before it began painting, it attempted to inspect the painting that had been done by All-State, but was unable to do so; and it was informed by Jones-Teer and by American States Insurance Company, surety for All-State, that the completed painting was satisfactory.

This litigation followed. Two suits were filed. Hass brought the first action in the United States District Court for New Jersey for a declaratory judgment that it was entitled to extra compensation under the subcontract for corrective work, and to damages for Jones-Teer's breach of contract for denying such payments. Hass filed the second action in the United States District Court for the Western District of Kentucky under the Miller Act, 40 U.S.C. Secs. 270a-270f, against Jones-Teer and the surety on its bond, claiming $500,000 in damages against Jones-Teer, and $500,000 in damages and one million dollars in punitive damages against American States Insurance Company, surety for All-State Contracting Company. Jones-Teer counterclaimed against Hass, on a charge of breach of contract, claiming $850,000 in damages.

The New Jersey action was transferred to the Western District of Kentucky, where the two suits were consolidated for trial before District Judge Edward H. Johnstone, sitting without a jury. Judge Johnstone filed comprehensive findings of fact and conclusions of law and a memorandum opinion.

Judge Johnstone held that the subcontract was a complete delegation to Hass of all the requirements for painting contained in the prime contract, including any and all corrective work necessary to conform to the provisions of the prime contract; that Hass assumed the risk of the corrective work; and that unforseen difficulties alleged by Hass were no excuse for noncompliance with the subcontract. The Court further held that Hass had affirmed the subcontract, after it learned the extent of the corrective work, by its performance of the profitable parts of the contract while refusing to perform unprofitable portions.

Judgment was rendered in favor of Hass against Jones-Teer for $17,920.00 for work performed by Hass under the subcontract before its termination, plus all unpaid amounts retained by Jones-Teer. All other claims of Hass were dismissed. The counterclaim of Jones-Teer against Hass and all other claims made by the parties were dismissed with prejudice.

Jones-Teer appeals and Hass cross-appeals. We affirm.

II

The printed terms of the subcontract between Jones-Teer and Hass provided:

Subcontractor shall furnish all labor ... to prosecute and complete the work identified and described in Schedule A attached hereto ("the Work"), being a portion of the work required of Contractor under the General Contract (the "Contract") between Owner and Contractor. The Work shall be performed by Subcontractor in a good and workmanlike manner strictly in accordance with the contract documents listed in Schedule B and incorporated herein by reference.

Schedule A was a typed insertion which defined "work" as follows:

Furnishing all labor, materials (except as noted in Schedule F), equipment, supplies, insurance, supervision, etc., to complete the surface preparation and field painting work for Bid Item 66, in strict accordance with the contract documents, completing the Work which was begun by All-State Contracting Company under Subcontract No. 74-285-014, starting with the job conditions left by All-State and which were existing as of May 7, 1979.

The printed terms of the subcontract also provided that "Subcontractor shall be bound by all the terms of the [general] Contract and assumes all the obligations of Contractor as stated therein which are applicable to this subcontract."

Section 7(d) of the prime contract provided:

All material and work covered by progress payments made shall thereupon become the sole property of the Government, but this provision shall not be construed as relieving [Jones-Teer] from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work, or as waiving the right of the Government to require the fulfillment of all of the terms of the contract.

Judge Johnstone construed the foregoing language of the subcontract and prime contract as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

J.I. Hass Company, Inc. v. Jones-Teer, 755 F.2d 1264 (6th Cir. 1985).

755 F.2d 1264 (J.I. Hass Company, Inc. v. Jones-Teer) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sanford Construction Co. v. S & H CONTRACTORS, INC.
443 S.W.2d 227 (Court of Appeals of Kentucky (pre-1976), 1969)
Hampton v. Suter
330 S.W.2d 402 (Court of Appeals of Kentucky (pre-1976), 1959)
Codell Construction Co. v. Commonwealth
566 S.W.2d 161 (Court of Appeals of Kentucky, 1977)
Dunn v. Tate
268 S.W.2d 925 (Court of Appeals of Kentucky (pre-1976), 1954)
Allgier v. Brush
551 S.W.2d 262 (Court of Appeals of Kentucky, 1977)
J.I. Hass Co. v. Jones-Teer
755 F.2d 1264 (Sixth Circuit, 1985)