J.I. Hass Co. v. Jones-Teer

755 F.2d 1264, 1985 U.S. App. LEXIS 29276
CourtCourt of Appeals for the Sixth Circuit
DecidedMarch 6, 1985
DocketNos. 83-5719, 83-5761
StatusPublished
Cited by1 cases

This text of 755 F.2d 1264 (J.I. Hass Co. v. Jones-Teer) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.I. Hass Co. v. Jones-Teer, 755 F.2d 1264, 1985 U.S. App. LEXIS 29276 (6th Cir. 1985).

Opinion

PHILLIPS, Senior Circuit Judge.

This breach of contract litigation arose out of the construction by the United States Army Corps of Engineers of the Smithland Dam on the Ohio River, at Smithland, Kentucky. The prime contractor was Jones-Teer, a joint venture of the J.A. Jones Construction Company and Nel-lo L. Teer Co., Inc. Jones-Teer was required by the provisions of its contract to do all work necessary to complete the project.

This case involves a subcontract between Jones-Teer and J.I. Hass Company (Hass) providing for the painting by Hass of the steel gates of the dam.

I

Jones-Teer originally had engaged All-State Contracting Company to paint the gates. All-State commenced the painting work in 1977 and continued until the end of the painting season in 1978. All-State and Jones-Teer had a dispute concerning the performance of All-State’s work and All-State removed itself from the project.1 Hass contracted to do the painting job for $471,000.00. After Hass began painting, defects were discovered in painting work done by All-State. The Corps of Engineers required performance of a considerable amount of remedial work. Hass contended that it was entitled to extra compensation for corrective work. Jones-Teer declined to pay the claims of Hass for additional compensation, upon the ground that the subcontract required Hass to complete all the painting at its own expense.

Hass contends that before it began painting, it attempted to inspect the painting that had been done by All-State, but was unable to do so; and it was informed by Jones-Teer and by American States Insurance Company, surety for All-State, that the completed painting was satisfactory.

This litigation followed. Two suits were filed. Hass brought the first action in the United States District Court for New Jersey for a declaratory judgment that it was entitled to extra compensation under the subcontract for corrective work, and to damages for Jones-Teer’s breach of contract for denying such payments. Hass filed the second action in the United States District Court for the Western District of Kentucky under the Miller Act, 40 U.S.C. §§ 270a-270f, against Jones-Teer and the surety on its bond, claiming $500,000 in damages against Jones-Teer, and $500,000 in damages and one million dollars in punitive damages against American States Insurance Company, surety for All-State Contracting Company. Jones-Teer counterclaimed against Hass, on a charge of breach of contract, claiming $850,000 in damages.

The New Jersey action was transferred to the Western District of Kentucky, where the two suits were consolidated for trial before District Judge Edward H. John-stone, sitting without a jury. Judge John-stone filed comprehensive findings of fact and conclusions of law and a memorandum opinion.

Judge Johnstone held that the subcontract was a complete delegation to Hass of all the requirements for painting contained in the prime contract, including any and all corrective work necessary to conform to the provisions of the prime contract; that Hass assumed the risk of the corrective work; and that unforseen difficulties alleged by Hass were no excuse for noncompliance with the subcontract. The Court further held that Hass had affirmed the subcontract, after it learned the extent of the corrective work, by its performance of the profitable parts of the contract while refusing to perform unprofitable portions.

[1266]*1266Judgment was rendered in favor of Hass against Jones-Teer for $17,920.00 for work performed by Hass under the subcontract before its termination, plus all unpaid amounts retained by Jones-Teer. All other claims of Hass were dismissed. The counterclaim of Jones-Teer against Hass and all other claims made by the parties were dismissed with, prejudice.

Jones-Teer appeals and Hass cross-appeals We affirm.

II

The .printed terms of the subcontract between Jones-Teer and Hass provided.

Subcontractor shall furnish all labor ... to prosecute and complete the work identified and described in Schedule A attached hereto (“the Work”), being a portion of the work required of Contractor under the General Contract (the “Contract”) between Owner and Contractor. The Work shall be performed by Subcontractor in a good and workmanlike manner strictly in accordance with the contract documents listed in Schedule B and incorporated herein by reference.

„ , , , , , . . ,. , Schedule A was a typed insertion which defmed work as follows:

Furnishing all labor, materials (except as noted in Schedule F), equipment, sup-phes, insurance, supervision, etc., to com-Píete, the surface preparation and field painting work for Bid Item 66, in strict accordance with the contract documents, completing the Work which was begun by All-State Contracting Company under Subcontract No 74-285-014, starting with the job conditions left bY All-State 1979 wh^ were exlstmS as of 7’

The printed terms of the subcontract also provided that “Subcontractor shall be bound by all the terms of the [general] Contract and assumes all the obligations of Contractor as stated therein which are applicable to this subcontract.”

Section 7(d) of the prime contract provided:

All material and work covered by progress payments made shall thereupon become the sole property of the Govern-ment, but this provision shall not be con-strued as relieving [Jones-Teer] from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work, or as waiving the right of the Government to require the fulfillment of all terms °f the contract.

Judge Johnstone construed the foregoing language of the subcontract and prime con-^ract as ^Hows.

As Hass progressed in the painting, it was determined by the Corps that much of the work of All-State required repair. ■ The Parties ^agreed as to whether Hass was re(Iuired under the subcontract to correct the work of the Prior PainterJones-Teer contends that Hass was to complete the work begun by All-State, whicb was to Produce a Painted dam! since Hass was to start with existinS Job conditions, corrective work was required in order that tbe Paintin£ could be exPleted- Hass contends that since it was to start with the conditions existing on May 7,1979, its obligation was only to go forward ^ ¿ complete, the job begun by All-State....
We preliminaril ruled at the close 0f the &st phage of the trial that the sub. contract wag ambiguous witb respect to of work and¡ based upon the evidence presented, that Hass was re-ible Qnly for goi forward with the inti jones-Teer, in its post-trial brfef hag requested that we reexamine Qur ruling. We have done and now fínd that the 8 of work stated in the subcontract is unambiguous.
Hass was to complete the painting, in accordance with the Corps’ speeifications, starting with the job conditions left by ¿be prj0r subcontractor. To place upon the word “complete” a mere quantitative requirement, as Hass contends with its go forward connotation, would be unreasonable in light of the qualitative mandates imposed by the incorporat[1267]*1267ed specifications. Clearly, the work could not be completed unless the specifications were satisfied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.I. Hass Company, Inc. v. Jones-Teer
755 F.2d 1264 (Sixth Circuit, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
755 F.2d 1264, 1985 U.S. App. LEXIS 29276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ji-hass-co-v-jones-teer-ca6-1985.