Jerry Duncan Ford, Inc. v. J. Roy Frost, d/b/a Frost Construction Company

CourtCourt of Appeals of Tennessee
DecidedDecember 29, 1999
DocketE1998-00535-COA-R3-CV
StatusPublished

This text of Jerry Duncan Ford, Inc. v. J. Roy Frost, d/b/a Frost Construction Company (Jerry Duncan Ford, Inc. v. J. Roy Frost, d/b/a Frost Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jerry Duncan Ford, Inc. v. J. Roy Frost, d/b/a Frost Construction Company, (Tenn. Ct. App. 1999).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE

AT KNOXVILLE FILED December 29, 1999

Cecil Crowson, Jr. Appellate Court Clerk

E1998-00535-COA-R3-CV JERRY DUNCAN FORD, INC., ) C/A NO. 03A01-9808-CH-00266 ) Plaintiff-Appellee, ) v. ) ) ) J. ROY FROST d/b/a FROST ) CONSTRUCTION COMPANY, ) ) Defendant-Appellant. ) ) ) J. ROY FROST d/b/a FROST ) CONSTRUCTION COMPANY, ) ) Plaintiff-Appellant, ) ) v. ) ) APPEAL AS OF RIGHT FROM THE JERRY DUNCAN FORD, INC., ) ROANE COUNTY CHANCERY COURT ) Defendant-Appellee. ) ) ) CUSTOMER SERVICE ELECTRIC ) SUPPLY, INC., ) ) Plaintiff-Appellant, ) ) v. ) ) JERRY DUNCAN FORD, INC., ) J. ROY FROST d/b/a FROST ) CONSTRUCTION CO., M. JERRY ) DUNCAN and wife, JUDY C. ) DUNCAN, ) ) HONORABLE FRANK V. WILLIAMS, III Defendants-Appellees.) CHANCELLOR

For Appellant Frost For Appellees Jerry Duncan Ford, Inc., M. Jerry Duncan and Judy WILSON S. RITCHIE C. Duncan WALTER B. JOHNSON, II Ritchie & Johnson, PLC J. POLK COOLEY Knoxville, Tennessee JENNIFER E. RABY Cooley, Cooley & Agee For Appellant Customer Service Rockwood, Tennessee Electric Supply, Inc.

WILLIAM A. NEWCOMB Harriman, Tennessee

1 O P I N IO N

AFFIRMED AND REMANDED Susano, J. This case is a consolidation of three breach of

contract actions, each of which arose out of disputes regarding

major renovations and additions to a commercial building in

Harriman housing an automobile dealership owned by Jerry Duncan

Ford, Inc. (“Jerry Duncan Ford”). Jerry Duncan Ford filed an

action against the general contractor in charge of the project,

J. Roy Frost, doing business as Frost Construction Company

(“Frost”), after terminating Frost’s services because of

unsatisfactory performance. Frost in turn filed an action

against Jerry Duncan Ford for breach of contract. The third

action was filed by Customer Service Electric Supply, Inc.

(“Customer Service”), against Jerry Duncan Ford, Frost, M. Jerry

Duncan (“Mr. Duncan”), and Judy C. Duncan (“Judy Duncan”),

seeking payment for certain exterior light fixtures that it had

installed at the dealership. After a bench trial, the court

awarded Jerry Duncan Ford damages reflecting the difference

between the total cost of the construction and $313,200, a

“ceiling” that -- as found by the trial court -- Frost had

guaranteed. The trial court also awarded Customer Service

damages against Frost, but denied the former’s request for a

judgment against Jerry Duncan Ford and the Duncans. Frost

appeals, raising the following issues for our consideration:

1. Did the trial court err in admitting parol evidence to vary the terms of the written contract?

2. Does the evidence preponderate against the finding of an oral agreement of a guaranteed maximum price?

2 3. Is Frost, rather than Jerry Duncan Ford, entitled to breach of contract damages due to the dealership’s failure to give Frost notice and an opportunity to cure any defects in construction?

Customer Service appeals the trial court’s dismissal of its

complaint against Jerry Duncan Ford and the Duncans.

I.

In December, 1995, the Duncans, as owners and corporate

officers of Jerry Duncan Ford, discussed with Frost the

possibility of doing major renovations and additions to the

dealership’s building. Upon Frost’s recommendation, Mr. Duncan

contacted Randy Denton (“Denton”), an engineer, who, after

meeting with Mr. Duncan and Frost, drafted a floorplan detailing

the plans for the anticipated work.

In early January, 1996, Frost gave Mr. Duncan a one-

page estimate showing the projected cost of the construction to

be $100,136.1 Mr. Duncan reviewed this estimate but noted that

it did not reflect everything that he wanted done. Mr. Duncan

told Frost that he wanted a list of everything that was to be

done and what each item would cost. On January 20, 1996, Frost

met with the Duncans at their home and gave them a revised

estimate. The four-page document shows detailed costs for the

construction, including the cost of (1) building a new service

building and new office area; (2) remodeling of the showroom and

1 Frost denies that he showed Mr. Duncan this one-page estimate, but Duncan testified to the contrary.

3 the existing office area; (3) remodeling of the exterior; and (4)

miscellaneous items, such as pouring concrete slabs, renovating

restrooms, patching the asphalt of the parking lot, and replacing

the exterior lights. For each renovation phase described, Frost

included a subtotal reflecting the addition of ten percent of the

estimated cost for profit and overhead and 2.5% of the estimated

cost for workers’ compensation and liability insurance. Every

page is signed by Frost and dated January 20, 1996. The last

page contains the line: “total projected cost for complete

project: $313,200.” The trial court found that, at the January

20, 1996, meeting, Frost orally guaranteed that the cost of the

project would not exceed $313,200.

Frost and his crew began work at the dealership the

following week and continued for several months. About once a

month, Frost submitted groups of invoices to Mr. Duncan for

payment. These invoices included the cost of materials and labor

plus the agreed-upon ten percent for overhead and profit and 2.5%

for workers’ compensation and liability insurance. The record

reflects that Jerry Duncan Ford made four payments to Frost

totaling $134,706.93. In addition, the dealership paid

$92,857.09 directly to several subcontractors and suppliers.

By February, 1996, the Duncans began to notice problems

with Frost’s work. First, there were deviations from the

original plans. The parties had initially agreed that additional

concrete would be poured on the existing concrete floors in

several areas of the building before tile or carpet was laid.

Frost, however, installed wood strips and plywood instead of

4 concrete in these areas. As a result, these floors squeaked,

moved, and in some places, swelled. The plans also called for

the two existing restrooms to be renovated and made wheelchair-

accessible in accordance with the Americans with Disabilities Act

(“ADA”). However, the restrooms were not renovated in accordance

with the ADA. Consequently, a unisex restroom, which is ADA

compliant, had to be built between the two existing restrooms.

The Duncans also experienced problems when changes were

made to the original plans. In the shop area, the original plans

called for a two-foot drain in the center of the room. Within

the drain, PVC pipe was to be installed for an exhaust system to

hook up to cars being serviced. Mr. Duncan decided instead to

install the exhaust system within the concrete that would be

poured for the floor. The exhaust ports were to be installed 30

feet from the wall on each side of the shop area. Mr. Duncan

discussed the change in plans with Frost before the concrete was

poured. However, after the exhaust system was installed, Mr.

Duncan noticed that on one side of the building, the exhaust

ports were only 15 feet from the wall. Mr. Duncan testified that

the misplacement of the exhaust ports made access to the ports

difficult and time-consuming.

Other problems developed as well. A wall in a hallway

was bowed, causing the tile on the floor to be laid out of

square. Shelving installed in the storage area collapsed due to

inadequate bracing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Massengale v. Massengale
915 S.W.2d 818 (Court of Appeals of Tennessee, 1995)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Castelli v. Lien
910 S.W.2d 420 (Court of Appeals of Tennessee, 1995)
Bowman v. Bowman
836 S.W.2d 563 (Court of Appeals of Tennessee, 1991)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
Bokor v. Holder
722 S.W.2d 676 (Court of Appeals of Tennessee, 1986)
Tennessee Valley Kaolin Corp. v. Perry
526 S.W.2d 488 (Court of Appeals of Tennessee, 1974)
GRW Enterprises, Inc. v. Davis
797 S.W.2d 606 (Court of Appeals of Tennessee, 1990)
Campbell v. Florida Steel Corp.
919 S.W.2d 26 (Tennessee Supreme Court, 1996)
McReynolds v. Cherokee Insurance Co.
815 S.W.2d 208 (Court of Appeals of Tennessee, 1991)
Tri-Cities Forklift Co. v. Conasauga River Lumber Co.
700 S.W.2d 548 (Court of Appeals of Tennessee, 1985)
Peoples Bank of Elk Valley v. Conagra Poultry Co.
832 S.W.2d 550 (Court of Appeals of Tennessee, 1991)
Myers v. Taylor
64 S.W. 719 (Tennessee Supreme Court, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
Jerry Duncan Ford, Inc. v. J. Roy Frost, d/b/a Frost Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jerry-duncan-ford-inc-v-j-roy-frost-dba-frost-cons-tennctapp-1999.