JDL Construction, Inc. v. United States

34 Cont. Cas. Fed. 75,502, 14 Cl. Ct. 825, 1988 U.S. Claims LEXIS 105, 1988 WL 58047
CourtUnited States Court of Claims
DecidedJune 7, 1988
DocketNo. 184-88C
StatusPublished
Cited by3 cases

This text of 34 Cont. Cas. Fed. 75,502 (JDL Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JDL Construction, Inc. v. United States, 34 Cont. Cas. Fed. 75,502, 14 Cl. Ct. 825, 1988 U.S. Claims LEXIS 105, 1988 WL 58047 (cc 1988).

Opinion

MEMORANDUM OPINION

ROBINSON, Judge.

This case is before the court on plaintiff’s application for a temporary restraining order and preliminary injunction. After a hearing on plaintiffs application, held on May 11, 1988, the court informed the parties orally that it would not issue an injunction. This opinion incorporates the substance of the court’s reasoning.

Facts

On July 29, 1987, the U.S. Department of the Air Force issued Invitation for Bid F04626-87-B-O069 for the installation of new windows in existing structures at Tra[826]*826vis Air Force Base (Travis IFB). Plaintiff, a Washington corporation qualifying as a small business pursuant to 15 U.S.C. Section 632, submitted the low bid. However, on October 19, 1987, the contracting officer issued a Determination of Non-Responsibility, finding plaintiff to be non-responsible on the grounds that it had an unsatisfactory record of capacity. Pursuant to 15 U.S.C. Section 637(b)(7), the contracting officer referred the proposed rejection to the SBA to allow plaintiff to file an application for a Certificate of Competency (COC).

Plaintiff submitted to the SBA a completed COC application with supporting data on November 5, 1987. On November 30, 1987, the SBA advised plaintiff that “[t]he performance history of JDL Construction does not provide conclusive evidence that the firm has overcome the contracting officer’s non-responsibility determination.” The contracting officer sent notice on March 2, 1988, to plaintiff that its bid on the Travis IFB was rejected because the SBA declined to issue to plaintiff a Certificate of Competency. On March 10, 1988, the contracting officer awarded the contract on the Travis IFB to the next lowest bidder.

On January 21, 1988, plaintiff was found to be the low bidder in response to U.S. Department of the Air Force Invitation for Bid F04612-88-B-0002 for the installation of new windows and siding in existing structures at Mather Air Force Base (Mather IFB). The contracting officer determined plaintiff to be “non-responsible for credit and capacity reasons.” Again, the contracting officer referred the proposed rejection to the SBA to allow plaintiff to file an application for a COC. Plaintiff submitted to the SBA a timely, completed COC application.

Plaintiff filed on March 21, 1988, its complaint for declaratory judgment and injunctive relief and its application for a temporary restraining order and preliminary injunction. The plaintiff seeks to enjoin the defendant from awarding the contracts on the Travis IFB and the Mather IFB to any entity other than plaintiff. In the event that either contract has been awarded, plaintiff seeks to restrain the defendant from directing or permitting performance of any work under the contract. In addition, plaintiff seeks to enjoin the SBA from withholding a COC without a hearing. Finally, plaintiff requests from this court a declaratory judgment naming it the rightful low bidder.

On March 21, 1988, the court held an informal conference with the parties’ counsel at which defendant’s counsel advised the court that the Air Force would not award the contract on the Mather IFB until the SBA had completed its review of plaintiff’s COC application. Defendant’s counsel also confirmed that the contracting officer for the Travis IFB awarded the contract to the next lowest bidder on March 10, 1988.

Plaintiff amended its complaint for declaratory judgment on March 25, 1988. In its amended complaint, plaintiff claims defendant breached an implied-in-fact contract to consider fairly plaintiff’s low bid on the Travis IFB. Plaintiff seeks its bid preparation costs and anticipated profits. On March 30, 1988, defendant moved for dismissal of several of plaintiff’s claims in the amended complaint for lack of subject matter jurisdiction.

Also on March 25, 1988, a grand jury in the United States District Court for the Eastern District of California indicted plaintiff for making a false claim and making a false statement on a contract with McClellan Air Force Base in violation of 18 U.S.C. Sections 287 and 1001. As a result of the indictment, the Air Force suspended plaintiff from competition for any contracts with any agency in the Executive Branch of the United States Government until completion of the criminal proceedings against it. See generally 48 CFR Section 9.407. Also as a result of the indictment, the SBA informed the contracting officer for the Mather IFB on May 5, 1988, that the award of the contract could proceed.

Defendant filed on May 9, 1988, its response to plaintiff’s application for temporary restraining order and preliminary injunction and motion for summary judgment. Defendant contends that plaintiff cannot satisfy the requirements for injunc-[827]*827tive relief. Further, defendant argues that since there exists a rational basis for each of the contracting officers’ determinations of non-responsibility, the defendant did not breach an implied-in-fact contract to fairly consider plaintiff’s bids. Thus, defendant contends that it is entitled to summary judgment against plaintiff.

The court held another informal conference with both counsel on May 9, 1988. Defendant’s counsel agreed to request the Mather Air Force Base contracting officer to voluntarily delay the award of that contract for an additional three days to allow plaintiff an opportunity for a hearing on its application for a temporary restraining order and preliminary injunction. The court scheduled the hearing for May 11, 1988. On May 11, 1988, plaintiff filed a reply to defendant’s response to its application for preliminary injunction. In its reply, plaintiff requests a temporary injunction enjoining the Air Force from proceeding with the award of the Mather Air Force Base contract pending the conclusion of the trial in USA v. JDL Construction, Inc., et al., No. 588-091EJG (E.D.Ca). Plaintiff also seeks a stay of these proceedings pending conclusion of the criminal matter, or until June 30, 1988, whichever is later. Plaintiff contends that it is entitled to the injunction because the Air Force’s suspension operates as an unconstitutional bill of attainder which excludes plaintiff from furnishing its services to the government.

Discussion

I. Jurisdiction of this court

This court’s jurisdiction to entertain claims and to grant relief depends upon, and is circumscribed by, the extent to which the United States has waived its sovereign immunity. United States v. Sherwood, 312 U.S. 584, 586, 61 S.Ct. 767, 769-70, 85 L.Ed. 1058 (1941). The Tucker Act, 28 U.S.C. Section 1491, is the central provision granting the government’s consent to be sued in this court. United States v. Testan, 424 U.S. 392, 96 S.Ct. 948, 47 L.Ed.2d 114 (1976); Aetna Casualty & Surety Co. v. United States, 228 Ct.Cl. 146, 151, 655 F.2d 1047, 1051 (1981).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Level 3 Communications, LLC v. United States
129 Fed. Cl. 295 (Federal Claims, 2016)
Contracting, Consulting, Engineering LLC v. United States
104 Fed. Cl. 334 (Federal Claims, 2012)
Advanced Seal Technology, Inc. v. Perry
873 F. Supp. 1144 (N.D. Illinois, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,502, 14 Cl. Ct. 825, 1988 U.S. Claims LEXIS 105, 1988 WL 58047, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jdl-construction-inc-v-united-states-cc-1988.