Jay Miller & Sundown, Inc. D/B/A Sundown Construction (Appellant/Cross Appellee) v. Camp, Dresser & McKee, Inc. D/B/A CDM (Appellee/Cross Appellant)

381 S.W.3d 635, 2012 Tex. App. LEXIS 6776, 2012 WL 3322645
CourtCourt of Appeals of Texas
DecidedAugust 15, 2012
Docket04-11-00056-CV
StatusPublished
Cited by7 cases

This text of 381 S.W.3d 635 (Jay Miller & Sundown, Inc. D/B/A Sundown Construction (Appellant/Cross Appellee) v. Camp, Dresser & McKee, Inc. D/B/A CDM (Appellee/Cross Appellant)) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jay Miller & Sundown, Inc. D/B/A Sundown Construction (Appellant/Cross Appellee) v. Camp, Dresser & McKee, Inc. D/B/A CDM (Appellee/Cross Appellant), 381 S.W.3d 635, 2012 Tex. App. LEXIS 6776, 2012 WL 3322645 (Tex. Ct. App. 2012).

Opinion

OPINION

Opinion by: STEVEN C. HILBIG, Justice.

Jay Miller & Sundown, Inc. (“Sundown”) appeals the summary judgment granted in favor of Camp Dresser & McKee Inc. (“CDM”) on the ground that Sundown’s claim for tortious interference with contract was barred by the statute of limitations. Sundown argues that the statute of limitations was not available to CDM as a defense because CDM was properly joined in the action as a responsible third party pursuant to chapter 33 of the Texas Civil Practice and Remedies Code. CDM contends that Sundown misinterprets and misapplies Chapter 33. CDM argues alternatively in a cross-point that the trial court erred in denying its motion to dismiss the suit pursuant to section 150.002 of the Civil Practice and Remedies Code because Sundown did not file a certificate of *637 merit. We hold the trial court erred in granting the summary judgment and that under the law applicable to Sundown’s claim, no certifícate of merit was required. We therefore reverse the trial court’s judgment and remand for further proceedings.

Background

CDM is an engineering firm that contracted with the City of Del Rio to provide design and construction administrative services for a project to replace and improve parts of the City’s water distribution system. CDM designed the project, managed the bidding process, and provided construction administrative services after construction began. In April 2003, the City contracted with Sundown to be the general contractor on the project. The contract required Sundown to construct water lines throughout the city, install a booster pump station, and construct an elevated storage tank. Sundown began work in June 2003, and the contract required the project be substantially complete within 365 days and be complete for final payment by July 8, 2004. The contract contained a liquidated damages clause and a provision that if the City, the project engineer or others performing work for the City or for whom the City was responsible, delayed, disrupted, or interfered with the performance or progress of the work, then Sundown was entitled to an equitable adjustment in the contract price, the contract times, or both. CDM was not a party to the contract between Sundown and the City, and Sundown did not have a separate contract with CDM. The City terminated CDM’s contract at the end of 2004. Because of numerous delays, the project was not finally complete until January 2005.

Sundown sued the City in February 2007 for breach of contract and violation of the Prompt Payment Act. Sundown alleged the City, through its employees and agents, delayed, disrupted, and interfered with performance of the work, resulting in additional work, expense, and overhead and significantly delaying the completion date. Sundown sought unpaid sums due under the contract, including change orders and additional work, delay damages, interest, and attorney’s fees. In October 2009, Sundown amended its petition to add a claim under the Texas Tort Claims Act for property damage caused by the City’s negligent operation or use of water pumping equipment. Sundown alleged the City’s improper operation of the water pumps that supplied pressure to water lines caused some lines to burst, causing flooding of the project site and damage to Sundown’s work and property. Sundown further alleged that had the City not improperly interfered with and delayed the work, Sundown would have progressed beyond the site of the flooding when the pipes burst and its damages would have been less.

The City amended its answer, pleading that to the extent Sundown’s negligence allegations against the City were found to be true, CDM was a responsible third party within the meaning of section 33.011(6) of the Texas Civil Practice and Remedies Code. At the same time, the City filed an unopposed motion for leave to designate CDM a responsible third party pursuant to section 33.004 of the Civil Practice and Remedies Code. The trial court signed an order granting the motion. 1 In December 2009 and within sixty *638 days of the designation, Sundown filed-an amended petition, joining CDM as a defendant, and alleging causes of action against CDM for tortious interference with contract, negligent misrepresentation, and fraud.

Sundown later settled -with and nonsuit-ed the City. CDM filed a motion to dismiss, alleging Sundown had not filed a certificate of merit as required by chapter 150 of the Civil Practice and Remedies Code. CDM also filed a motion for summary judgment on the ground that Sundown’s causes of action were barred by the statute of limitations. The trial court heard arguments on the motions and took them under advisement. At the next hearing in the case, the trial court orally rendered its rulings granting summary judgment on the tortious interference claim, denying summary judgment on the fraud and negligent misrepresentation claims, and denying CDM’s motion to dismiss. On the same day, Sundown filed its fourth amended petition, naming CDM as the sole defendant and dropping the fraud and negligence claims. The court then signed a final judgment.

Sundown appeals the summary judgment. CDM argues in a cross-point that the trial court should have dismissed the suit for failure to file a certificate of merit.

Statute of Limitations

The parties agree the statute of limitations on Sundown’s tortious interference claim is two years and that Sundown joined CDM as a defendant more than two years after CDM’s last involvement in the project. CDM’s motion for summary judgment asserted the claim is barred by limitations. Sundown contends the trial court erred in granting the motion because former section 33.004(e) 2 of the Texas Civil Practice and Remedies Code authorizes it to pursue the claim even though it would otherwise be barred by limitations. Applicable law and standard of review

As a defendant moving for summary judgment on the affirmative defense of limitations, CDM had the burden to conclusively establish the defense. See Rhone-Poulenc, Inc. v. Steel, 997 S.W.2d 217, 223 (Tex.1999). We review summary-judgments and issues of statutory construction de novo. Molinet v. Kimbrell, 356 S.W.3d 407, 411 (Tex.2011); Carreras v. Marroquin, 339 S.W.3d 68, 71 (Tex.2011). The court’s “primary objective in construing statutes is to give effect to the Legislature’s intent.” Molinet, 356 S.W.3d at 411 (citing Galbraith Eng’g Consultants, Inc. v. Pachucha, 290 S.W.3d 863, 867 (Tex.2009)). “The plain meaning of the text is the best expression of legislative intent unless a different meaning is apparent from the context or the plain meaning leads to absurd or nonsensical results.” Id.

Chapter 33 of the Civil Practice and Remedies Code is the “complex statutory scheme for the comparative apportionment of responsibility among parties in most tort actions in Texas.” Galbraith Eng’g,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
381 S.W.3d 635, 2012 Tex. App. LEXIS 6776, 2012 WL 3322645, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jay-miller-sundown-inc-dba-sundown-construction-appellantcross-texapp-2012.