James E. McFadden, Inc. v. Baltimore Contractors, Inc.

609 F. Supp. 1102, 1985 U.S. Dist. LEXIS 20230
CourtDistrict Court, E.D. Pennsylvania
DecidedMay 1, 1985
DocketCiv. A. 83-1905
StatusPublished
Cited by16 cases

This text of 609 F. Supp. 1102 (James E. McFadden, Inc. v. Baltimore Contractors, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James E. McFadden, Inc. v. Baltimore Contractors, Inc., 609 F. Supp. 1102, 1985 U.S. Dist. LEXIS 20230 (E.D. Pa. 1985).

Opinion

*1103 MEMORANDUM

GILES, District Judge.

James E. McFadden, Inc. (“McFadden”) brought this diversity action against several defendants to recover monies allegedly due it for construction work performed as a subcontractor at the Limerick Generating Station Project. Named as the principal defendants were Bechtel Power Corporation (“Bechtel”), the general contractor, Baltimore Contractors, Inc. (“Baltimore”), the contractor with whom McFadden entered into the subcontract agreement, and United States Fidelity and Guaranty Company (“USF & G”), a bonding company. A default judgment was entered against Baltimore in July, 1983. Summary judgment was entered in favor of Bechtel in May, 1984. Thus, the only remaining defendant at this juncture is USF & G. 1 USF & G did not bond Baltimore on the Limerick job. However, McFadden has proceeded against USF & G on a theory that USF & G took control of Baltimore in 1980. Under plaintiff’s theory, Baltimore was a mere instrumentality of USF & G and therefore USF & G should be held liable for the debts of Baltimore. USF & G has filed a motion for summary judgment arguing that the undisputed material facts show that Baltimore was not the instrumentality of USF & G. For the reasons which follow, USF & G’s motion shall be granted.

FACTS

USF & G bonded Baltimore for numerous construction projects. However, the Limerick project, on which McFadden worked, was not one of them. Baltimore began experiencing severe financial difficulties in 1979-80 because of a loss it incurred on one of its major projects. During this time, Baltimore and its affiliated company, the Empire Construction Company, had USF & G bonded jobs in various stages of completion, having an aggregate contract amount of $142,000,000. USF & G stood to lose up to $50,000,000 in excess of the remaining contract payments, liquidated damages and claims if it took over the jobs and completed them for Baltimore. In order to minimize its risks, USF & G entered into a Supplemental Agreement with Baltimore on April 22, 1980.

Under this Agreement, USF & G loaned about $20,000,000 to Baltimore to fund Baltimore’s continued operation and the completion of bonded jobs. The agreement contained many conditions that had to be met by Baltimore. It also provided that failure to comply with these conditions could result in USF & G’s terminating further bonding and/or foreclosure. Some of these conditions were:

1. Transferring to USF & G all funds paid to Baltimore under various construction contracts bonded by USF & G.
2. Turning over all profits from any joint venture to USF & G to be applied to reduce the line of credit.
3. Promptly paying all sums due and owing for labor in a manner acceptable to USF & G.
4. Furnishing USF & G with documentation justifying overhead expenses upon requesting USF & G to pay such expenses.
5. Allowing USF & G to pay directly for suppliers’ claims or take whatever action necessary to settle such claims upon Baltimore’s failure to pay them.
6. Allowing USF & G to complete projects it had bonded in Baltimore’s name and at Baltimore’s expense if Baltimore failed to complete them.
7. Providing USF & G prompt access to all project sites bonded by it and to Baltimore’s books, records and other job accounts.
8. Installing an accounting system satisfactory to USF & G and providing monthly financial statements to USF & G.
9. Assigning collateral, listed in an attachment to the agreement, to USF & G.
*1104 10. Providing that USF & G was the holder in due course of certain promissory notes made by Baltimore.
11. Authorizing USF & G to give instructions to subcontractors, suppliers, etc. necessary in USF & G’s opinion to effectuate the provisions of the agreement.
12. Risking foreclosure if it failed to cooperate in the completion of construction contracts bonded by USF & G or attempted to commence bankruptcy proceedings.
13. Promising not to enter into any new construction contracts except cost plus contracts not in excess of $100,000, make any loans or any investments, purchase any real estate, etc.
14. With respect to unbonded work— providing a monthly accounting to USF & G and holding all funds received from unbonded work in trust to (a) pay for labor and materials, etc. used in completing unbonded work, (b) pay for indirect overhead incurred in unbonded work and (c) pay USF & G as a credit against advances made by USF & G for work bonded by it after all existing unbonded work was completed.
Summary Judgment Standard
Summary judgment may be granted if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.

Fed.R.Civ.P. 56; Hollinger v. Wagner Mining Equipment Co., 667 F.2d 402, 405 (3d Cir.1981). See also Continental Insurance Co. v. Bodie, 682 F.2d 436, 438 (3d Cir.1982). Any doubts as to the existence of a genuine issue of fact and any inferences drawn from the evidence submitted must be resolved in favor of the party opposing the motion. Continental Ins. Co., 682 F.2d at 438, quoting Hollinger, 667 F.2d at 405 (other citations omitted). Although summary judgment has been “ ‘[characterized as both a ‘drastic’ and ‘extreme’ remedy,” it should be granted when doing so would “ ‘avoid waste of time and resources of both the litigants and the Court where trial would be a useless formality.’ ” Associated Film Distribution Corp. v. Thornburgh, 520 F.Supp. 971, 977 (E.D.Pa.1981), quoting Hollinger v. Wagner Mining Equipment Corp., 505 F.Supp. 894, 896-98 (E.D.Pa.1981).

DISCUSSION

There is no dispute that USF & G loaned Baltimore $20,000,000 which was memorialized in a Supplemental Agreement that made certain requirements regarding the securing of this loan and the completion of projects bonded by USF & G. There is a dispute whether by imposing these requirements, USF & G took total and actual control over Baltimore, rendering it USF & G’s instrumentality. This dispute is a question of law' to be decided by this court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rice v. First Energy Corp.
339 F. Supp. 3d 523 (W.D. Pennsylvania, 2018)
Wells Fargo Bank v. DeVicaris, J.
Superior Court of Pennsylvania, 2015
MUNICIPAL REVENUE SERVICE, INC. v. Xspand, Inc.
700 F. Supp. 2d 692 (M.D. Pennsylvania, 2010)
In Re iPCS, Inc.
297 B.R. 283 (N.D. Georgia, 2003)
Johnson v. Robinson (In Re Johnson)
292 B.R. 821 (E.D. Pennsylvania, 2003)
Pearson v. Component Technology Corp.
80 F. Supp. 2d 510 (W.D. Pennsylvania, 1999)
Great West Casualty Co. v. Travelers Indemnity Co.
925 F. Supp. 1455 (D. South Dakota, 1996)
Ragan v. Tri-County Excavating, Inc.
62 F.3d 501 (Third Circuit, 1995)
Howard Oaks, Inc. v. Maryland National Bank
810 F. Supp. 674 (D. Maryland, 1993)
Cara Corp. v. Continental Bank (In Re Cara Corp.)
148 B.R. 760 (E.D. Pennsylvania, 1992)
Temp-Way Corp. v. Continental Bank
139 B.R. 299 (E.D. Pennsylvania, 1992)
Blue Line Coal Co., Inc. v. Equibank
683 F. Supp. 493 (E.D. Pennsylvania, 1988)
Irwin & Leighton, Inc. v. W.M. Anderson Co.
532 A.2d 983 (Court of Chancery of Delaware, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
609 F. Supp. 1102, 1985 U.S. Dist. LEXIS 20230, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-e-mcfadden-inc-v-baltimore-contractors-inc-paed-1985.