James Cape & Sons Co. v. Mulcahy

2003 WI App 229, 672 N.W.2d 292, 268 Wis. 2d 203, 2003 Wisc. App. LEXIS 1013
CourtCourt of Appeals of Wisconsin
DecidedOctober 30, 2003
Docket02-2817
StatusPublished
Cited by2 cases

This text of 2003 WI App 229 (James Cape & Sons Co. v. Mulcahy) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James Cape & Sons Co. v. Mulcahy, 2003 WI App 229, 672 N.W.2d 292, 268 Wis. 2d 203, 2003 Wisc. App. LEXIS 1013 (Wis. Ct. App. 2003).

Opinion

DEININGER, PJ.

¶ 1. The Wisconsin Department of Transportation and its secretary appeal an order granting summary judgment in favor of James Cape & Sons Company, a road builder. The effect of the order is to release Cape from its $100,000 "proposal guaranty" that the department declared forfeited when Cape refused to perform a road construction contract on which it had submitted the low bid. The State claims Cape is not entitled to summary judgment because the record does not establish that "in making the mistake, error or omission" in its bid, Cape "was free from *206 carelessness, negligence or inexcusable neglect." Wis. Stat. § 66.0901(5) (2001-02). 1

2. The trial court concluded that because Cape notified the department of the error before the department had awarded the contract to Cape, the "free from. . . inexcusable neglect" standard did not apply. Although we agree that the language of Wis. Stat. § 66.0901(5) may reasonably be interpreted in the manner the trial court did, we conclude that the holding of Nelson, Inc. v. Sewerage Comm'n of Milwaukee, 72 Wis. 2d 400, 241 N.W.2d 390 (1976), precludes this interpretation. Based on Nelson, we conclude that Cape was required to show its freedom from "carelessness, negligence or inexcusable neglect." We also conclude, however, that Cape did so on the present record. Accordingly, we affirm the order directing the return of Cape's check for $100,000.

BACKGROUND

¶ 3. The appealed order disposes of cross-motions for summary judgment, and neither party argues that a dispute of material fact bars summary judgment in favor of the other. The parties have therefore effectively stipulated to the material facts. See Lucas v. Godfrey, 161 Wis. 2d 51, 57, 467 N.W.2d 180 (Ct. App. 1991). We derive the key events in the background summary which follows from the parties' submissions on summary judgment.

¶ 4. The department solicited bids for construction of a highway interchange in Milwaukee. The bids were to be opened at 9:00 a.m. on October 10, 2000, as *207 were bids on several other highway projects. As is apparently the custom, prospective bidders, including Cape, assembled personnel in rooms at a Madison hotel on the evening before the bid opening in order to compile and rework bids for submission just before the 9:00 a.m. deadline. Cape's bid team included some eight persons, equipped with several computers and printers, project folders and telephones.

¶ 5. The Cape bid team worked through the evening and into the morning hours, receiving proposals from prospective subcontractors, rejecting or accepting them, and incorporating the accepted proposals into Cape's final bids. Hard copies of the subcontractor proposals are customarily placed in appropriate folders and the figures are also entered into a computer so that comparisons can be made and final bid figures computed. One prospective subcontractor, Zenith Tech, submitted a proposal to Cape at about 6:00 a.m. Cape personnel identified Zenith Tech's bid as the low one for a component of the interchange project and entered the quotation into its bid calculations. At about 8:00 a.m., Zenith Tech discovered an error in the proposals it had submitted to Cape and two other contractors. Accordingly, Zenith Tech notified the three contractors by phone between 8:00 and 8:30 a.m. of an upward revision in its quoted price. Cape personnel compared the revised quotation with a proposal it had received for the item from a different subcontractor and concluded that Zenith Tech was still low for the item.

¶ 6. Revisions from prospective subcontractors are apparently not uncommon during the final bid preparation process, and Cape personnel have several mechanisms available for incorporating last-minute revisions in its final bid, including making handwritten changes on the final bid sheet. The higher figure for *208 Zenith Tech's work did not, however, become a part of the "final schedule" Cape personnel printed out sometime between 8:35 and 9:00 a.m. Cape personnel reviewed the final schedule and made a handwritten change to another item on it, but no change was made to the Zenith Tech item, which continued to reflect Zenith Tech's original, lower quotation. As a result, Cape's bid was $450,450 lower than if the revised Zenith Tech figure had been inserted. The final bids of two other contractors who utilized Zenith Tech for the item in question reflected the revised, higher Zenith Tech quotation.

¶ 7. The parties' subsequent actions and the litigation which followed involve a dispute over the interpretation and application of Wis. Stat. § 66.0901(5). We quote the subsection below in its entirety, but in light of the parties' arguments, we have divided the statutory language into three parts and identified each with a bracketed numeral:

(5) Corrections of errors in bids [1] If a person submits a bid or proposal for the performance of public work under any public contract to be let by a municipality and the bidder claims that a mistake, omission or error has been made in preparing the bid, the bidder shall, before the bids are opened, make known the fact that an error, omission or mistake has been made. If the bidder makes this fact known, the bid shall be returned to the bidder unopened and the bidder may not bid upon the public contract unless it is readvertised and relet upon the readvertisement. [2] If a bidder makes an error, omission or mistake and discovers it after the bids are opened, the bidder shall immediately and without delay give written notice and make known the fact of the mistake, omission or error which has been committed and submit to the municipality clear and satisfactory evidence of the mistake, omission or error and that it *209 was not caused by any careless act or omission on the bidder's part in the exercise of ordinary care in examining the plans or specifications and in conforming with the provisions of this section. [3] If the discovery and notice of a mistake, omission or error causes a forfeiture, the bidder may not recover the moneys or certified check forfeited as liquidated damages unless it is proven before a court of competent jurisdiction in an action brought for the recovery of the amount forfeited, that in making the mistake, error or omission the bidder was free from carelessness, negligence or inexcusable neglect.

Section 66.0901(5) (emphasis added).

¶ 8. Cape's bid was the lowest submitted for the interchange project, and it discovered the erroneous Zenith Tech figure in its bid soon after bid opening.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James Cape & Sons Co. v. Mulcahy
2005 WI 128 (Wisconsin Supreme Court, 2005)
Marine Bank v. Taz's Trucking Inc.
2004 WI App 164 (Court of Appeals of Wisconsin, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2003 WI App 229, 672 N.W.2d 292, 268 Wis. 2d 203, 2003 Wisc. App. LEXIS 1013, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-cape-sons-co-v-mulcahy-wisctapp-2003.