Jack B. Parson Construction Co. v. State Ex Rel. Department of Transportation

725 P.2d 614, 41 Utah Adv. Rep. 19, 1986 Utah LEXIS 864
CourtUtah Supreme Court
DecidedSeptember 12, 1986
Docket19673
StatusPublished
Cited by6 cases

This text of 725 P.2d 614 (Jack B. Parson Construction Co. v. State Ex Rel. Department of Transportation) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jack B. Parson Construction Co. v. State Ex Rel. Department of Transportation, 725 P.2d 614, 41 Utah Adv. Rep. 19, 1986 Utah LEXIS 864 (Utah 1986).

Opinion

AMENDED OPINION ON REHEARING

ZIMMERMAN, Justice:

Plaintiff Jack B. Parson Construction Co. (“Parson”) appeals from a declaratory judgment holding it in breach of a road construction contract with the Utah Department of Transportation (“UDOT”). The trial court found that UDOT had not made misleading statements upon which Parson reasonably relied and which resulted in Parson’s being unable to perform the contract. We conclude that UDOT did make misleading statements and remand for a determination whether Parson’s reliance on those statements was reasonable.

UDOT advertised for bids to pave a portion of Interstate 70 in Emery County, Utah. It furnished all prospective bidders, including Parson, with a bound set of documents labeled “Plans.” The documents included in this volume were selected for inclusion by UDOT employees and were to furnish a basis for bids. Among the documents was “sheet 2B,” which showed the location and boundaries of two borrow pits labeled “prospect No. 1” and “prospect No. 2.” The sheet described the contents of the prospects as “limestone ledge rock” and set out the results of certain tests run on the material in the pits to determine whether it met the contract specifications. Another document included in the bound volume was a special provision labeled “sheet 44.” It described the prospects in some detail and included the statement that each had been used previously for base and surface course on 1-70 projects. Although bidders could request permission to use other sources, these two prospects were the only economically feasible sources of paving materials in the general area of the project. All those who actually bid on the project specified these prospects as their proposed source.

Paragraph 102.05 of the State of Utah Standard Specifications for Road and Bridge Construction (1970 ed.) (“Utah Standard Specifications”) requires bidders to visit the prospective material site and visually inspect it. Two of Parson’s employees did visit the prospects. They concluded that the materials were consistent with the test data on sheet 2B and would be suitable.

Parson submitted the low bid for the project and was awarded the contract. After Parson had crushed some materials from prospect No. 2 and had laid some of the asphalt, inspection revealed that the asphalt did not meet contract specifications because of the poor quality of the crushed rock. Adjustments were made in the crushing process and blend sand was added, but to no avail. Some four months after starting work, Parson shut down the operation. Although attempts were made by UDOT and Parson to negotiate a solution, an impasse was reached when Parson insisted on changes in the contract that *616 UDOT would not or could not make. UDOT ordered Parson to perform. When it refused, UDOT terminated the contract as provided by its terms.

Parson sought both a declaratory judgment construing the terms of the contract and damages against UDOT, claiming breach of contract or negligent and/or intentional misrepresentation. After trial, the court entered extensive findings of fact and conclusions of law. It rejected Parson’s claims and ruled that Parson, not UDOT, had breached the contract.

On appeal, Parson does not challenge the findings of fact; instead, it contends that the trial court drew erroneous conclusions from those facts. Parson relies principally on our decision in Thorn Construction Co. v. Utah Department of Transportation, 598 P.2d 365 (Utah 1979), arguing that under Thorn, UDOT's representations are actionable as a matter of law. UDOT’s response calls for us to abandon the reasoning of the majority in Thorn and adopt the rationale of the dissent. This we decline to do. Therefore, if the trial court is to be upheld, it must be because liability has not been proven under Thorn.

In Thorn, this Court quoted with approval the following language from the case of Souza & McCue Construction Co. v. Superior Court, 57 Cal.2d 508, 370 P.2d 338, 339-40, 20 Cal.Rptr. 634, 635-36 (1962):

A contractor of public works who, acting reasonably, is misled by incorrect plans and specifications issued by the public authorities as the basis for bids and who, as a result, submits a bid which is lower than he would have otherwise made may recover [damages] in a contract action. ...

598 P.2d at 368. The Thorn Court then held that if affirmative representations made are inaccurate, and the inaccuracies make the plans and specifications misleading, the contractor can recover damages caused by reasonable reliance upon them. 598 P.2d at 367-69.

Applying this analysis to the present case, the first question is whether the documents containing the allegedly misleading information were part of the plans and specifications upon which Parson was entitled to rely. The trial court found that sheet 44 was part of the contract documents. The more critical document, however, was sheet 2B. The trial court found that sheet 2B was included within the bound set of documents marked “Plans” and furnished to Parson. However, the court concluded that sheet 2B was not part of the plans and specifications for the job because it did not fall within the technical definition of the word “plans” set forth in the Utah Standard Specifications.

This approach to the term “plans and specifications” is contrary to the spirit of Thorn. The quotation from Souza does use those words, and much of the rest of the Thorn Court’s discussion is also in terms of “plans”; however, the whole focus of that opinion is on the accuracy of the foundation material provided the bidder. There is nothing in Thorn that suggests such cases should turn on whether some bit or piece of information can be artfully defined out of the term “plans and specifications.” To the contrary, in Thorn, the Court permitted liability to be imposed for an oral statement made regarding the suitability of a borrow source that was wholly without parallel in the written plans and specifications. As a matter of practical construction, then, sheet 2B was plainly part of the plans and specifications: it was furnished to the bidder by UDOT to provide foundation material for the bid and, as such, was something upon which the bidder was entitled to rely and which must be scrutinized for accuracy.

The next question is whether sheet 2B and sheet 44 contained misleading assertions. The trial court answered this question in the negative. We disagree. Sheets 2B and 44 plainly suggested that satisfactory borrow could be taken readily from the two designated prospects. For example, the bore hole test results listed on sheet 2B showed that the material met contract specifications. In addition, the “Local Material Sources” subsection of the Utah Standard Specifications, referred to on sheet 2B, expressly provided that the “quality of materials in such deposits will *617 be acceptable in general.” However, the clear impression conveyed by these sheets was false, as information in the possession of UDOT showed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morris
1999 SD 95 (South Dakota Supreme Court, 1999)
Frontier Foundations, Inc. v. Layton Construction Co.
818 P.2d 1040 (Court of Appeals of Utah, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
725 P.2d 614, 41 Utah Adv. Rep. 19, 1986 Utah LEXIS 864, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jack-b-parson-construction-co-v-state-ex-rel-department-of-utah-1986.