J. Leo Johnson, Inc. v. Carmer

156 A.2d 499
CourtSupreme Court of Delaware
DecidedDecember 21, 1959
StatusPublished
Cited by15 cases

This text of 156 A.2d 499 (J. Leo Johnson, Inc. v. Carmer) is published on Counsel Stack Legal Research, covering Supreme Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. Leo Johnson, Inc. v. Carmer, 156 A.2d 499 (Del. 1959).

Opinion

156 A.2d 499 (1959)

J. LEO JOHNSON, INC., a corporation of the State of Vermont, et al., Defendants Below, Appellants,
v.
Dana E. CARMER, Plaintiff Below, Appellee.

Supreme Court of Delaware.

December 21, 1959.

Harold Schmittinger, Dover, for defendant below, appellant.

Herbert L. Cobin, Wilmington, for plaintiff below, appellee.

SOUTHERLAND, C. J., and WOLCOTT and BRAMHALL, JJ., sitting.

*500 BRAMHALL, Justice.

The question in this case relates to the alleged existence of the relationship of joint adventurers and the responsibility of the parties in the furtherance of the enterprise.

Plaintiff with one Norman C. Hicks and Leslie Fenwick negotiated with the Pennsylvania Railroad Company for the purchase of ballast and ties on the northbound track of the "Cape Charles line". It at once became apparent that the Railroad Company would enter into a contractual relationship only with a corporation. The president of the corporate defendant (hereafter defendant) was approached by Fenwick with a request that on behalf of plaintiff, Hicks and Fenwick, it enter into a contract with the Railroad Company for the purchase and removal of the ballast and ties. A contract was entered into, dated January 20, 1956, between defendant and the Railroad Company, under which defendant purchased from the Railroad the ties and ballast from one section of the tract for a consideration of $5,000. Although in the contract there was no reference to any other section, plaintiff claims that it was understood that if the work on the first section was performed satisfactorily, the defendant would be permitted by the Railroad Company to purchase on behalf of plaintiff and the others the second section of track. Under the same date a contract was executed between defendant and plaintiff, in which it was agreed that plaintiff and defendant were to remove the ballast and ties and that plaintiff would pay to defendant and defendant to the Railroad Company the sum of $5,000 which defendant had obligated to pay the Railroad.

It was also agreed that plaintiff would indemnify the defendant from loss by reason of its obligation to the Railroad. Under paragraph 12 of the agreement all money received was to be deposited in the Middletown Branch of the Delaware Trust Company and withdrawn only upon the joint signatures of plaintiff and James E. Knapp, defendant's agent. The proceeds were to be divided on a 50-50 basis "after the expense of the $5,000 payment insurance storage by the provisions above". Later plaintiff *501 testified that he understood that he was to receive a "third right down the line for putting up all the money on the first section, $32,000. I was to receive one-third of the second section regardless of their interest in it". At the trial plaintiff pressed his claim only for a one-third of the profits and the Chancellor found in his favor for that percentage thereof. The difference between the amount to which plaintiff is entitled under the written agreement and the 331/3% for which he has pressed his claim is of no importance in this suit.

Hicks and Fenwick had an arrangement with defendant whereby each was to receive one-third of defendant's share of 50%. Hicks for a time had charge of the operation of the work. When he became ill, plaintiff took over its supervision. Plaintiff in the performance of the work was compelled to advance substantial sums of money for the furtherance of the enterprise. Shortly before the first section was completed Fenwick, on behalf of defendant, without the knowledge of plaintiff, obtained from the Railroad Company a contract in the form of an "Order for Extra Work" for the purchase of the second section. Fenwick testified that plaintiff disclaimed any interest in the second section, but this testimony was denied by plaintiff and was specifically rejected by the Chancellor, who held that plaintiff was entitled to an interest in the second section and to an accounting therefor. This appeal is by defendant from the order of the Chancellor directing that defendant account to plaintiff for a one-third interest in the joint adventure with respect to section two.

Plaintiff contends that the parties entered into a joint adventure for the completion of the whole section. Defendant contends that there was no joint adventure but only a contractual relationship relative to the first section and that plaintiff therefore is entitled to an accounting only for the first section. The basis of defendant's contention is that the agreement between plaintiff and defendant does not provide for the sharing of losses.

The agreement between plaintiff and defendant provides that the defendant shall retain 50% of the net profits from the sale of the ballast and ties. Defendant contends that in addition to the agreement failing to provide for the sharing of losses, the agreement in several of its paragraphs is strongly suggestive that the parties intended that in no event should defendant bear any share of the loss. Defendant calls attention to the fact that paragraph 3 of this agreement provides that if the contractor employed by plaintiff to restore the property as required by the Railroad failed to do so, plaintiff would indemnify defendant for the cost and expense of such restoration; that under paragraph 4, providing that if certain safety measures required by the Railroad were not followed and the Railroad requested defendant to provide a flagman, plaintiff would reimburse defendant for the expense of such flagman; that in paragraph 5 thereof plaintiff agrees to indemnify defendant against any and all losses which defendant may suffer by reason of the removal of the ties and grading operation by plaintiff; that plaintiff should carry substantial insurance for the protection of defendant and the Railroad Company.

It will be observed that all of the paragraphs relied upon by defendant relate, in the first agreement, to the indemnification of the Railroad by defendant and, in the second, by plaintiff to defendant, for any failure to comply with the requirements of the Railroad. There is no provision of any kind in the event the enterprise should prove to be unprofitable. Where plaintiff's responsibility to the Railroad and to defendant relating to the conduct of the work is set forth in such detail, it would seem that, if it was intended by the parties that defendant should not be responsible for any loss because of the fact that the venture was unprofitable, it would have been so specified in the agreement.

A comparison of the agreement between plaintiff and defendant with the agreement executed immediately prior thereto between defendant and the Railroad Company shows *502 clearly that the paragraphs of the agreement above referred to between plaintiff and defendant and relied upon by defendant do not relate in any manner to the division of losses upon completion of the transaction. Except as these paragraphs in the second agreement apply to plaintiff rather than the Railroad Company, the corresponding paragraphs in the two agreements are practically identical. What the Railroad Company was looking for in these paragraphs of its agreement was indemnification; what was intended in the corresponding paragraphs in the agreement between plaintiff and defendant was indemnification of defendant by plaintiff to cover the indemnification by defendant to the Railroad Company in the prior agreement. Certainly the Railroad Company was not interested in the slightest in the division of profits or losses between plaintiff and defendant, or even whether or not there were any.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christopher Lundgren v. Alex Brola
Court of Chancery of Delaware, 2025
Principal Growth Strategies, LLC v. AGH Parent LLC
Court of Chancery of Delaware, 2024
Metro Storage International LLC v. Harron
Court of Chancery of Delaware, 2022
Otto Candies, LLC v. KPMG, LLP
Court of Chancery of Delaware, 2020
Lloréns v. Arribas
184 P.R. 32 (Supreme Court of Puerto Rico, 2011)
José C. Lloréns v. Rafael Arribas
2011 TSPR 204 (Supreme Court of Puerto Rico, 2011)
Haley v. Talcott
864 A.2d 86 (Court of Chancery of Delaware, 2004)
Thorpe by Castleman v. Cerbco, Inc.
676 A.2d 436 (Supreme Court of Delaware, 1996)
McMahon v. New Castle Associates
532 A.2d 601 (Court of Chancery of Delaware, 1987)
Mount Vernon Fire Insurance Co. v. Pied Piper Kiddie Rides, Inc.
445 A.2d 949 (Superior Court of Delaware, 1982)
Warren v. Goldinger Bros., Inc.
414 A.2d 507 (Supreme Court of Delaware, 1980)
In Re Arthur Treacher's Fish & Chips of Ft. Lauderdale, Inc.
386 A.2d 1162 (Court of Chancery of Delaware, 1978)
Sheppard v. Carey
254 A.2d 260 (Court of Chancery of Delaware, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
156 A.2d 499, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-leo-johnson-inc-v-carmer-del-1959.