J. Clancy, Inc. v. Khan Comfort, LLC

982 N.W.2d 35, 2022 S.D. 68
South Dakota Supreme Court·Decided November 9, 2022·No. 29876·Published

Opinion

#29876-a-SRJ 2022 S.D. 68

IN THE SUPREME COURT

OF THE

STATE OF SOUTH DAKOTA

****

J. CLANCY, INC., Plaintiff and Appellee, v.

KHAN COMFORT, LLC, previously known as KHAN DEVELOPMENT, LLC; GHAZANFAR KHAN, individually; Defendants and Appellants,

and

FIRST INTERSTATE BANK, a Montana Banking Corporation; BLACK HILLS COMMUNITY ECONOMIC DEVELOPMENT, INC., a South Dakota Non-Profit Corporation; UNITED STATES SMALL BUSINESS ADMINISTRATION; BKM ENTERPRISES, INC. d/b/a WATCO POOLS, a Montana Corporation; RAPID FIRE PROTECTION, INC., a South Dakota Corporation; and LAWRENCE COUNTY, a political subdivision of the State of South Dakota, Defendants.

****

APPEAL FROM THE CIRCUIT COURT OF THE FOURTH JUDICIAL CIRCUIT LAWRENCE COUNTY, SOUTH DAKOTA

****

THE HONORABLE MICHELLE K. COMER Judge

****

CONSIDERED ON BRIEFS

AUGUST 30, 2022

OPINION FILED 11/09/22

****

SCOTT SUMNER Rapid City, South Dakota Attorney for defendants and appellants.

TIMOTHY J. BARNAUD Belle Fourche, South Dakota Attorney for plaintiff and appellee.

JENSEN, Chief Justice [¶1.] J. Clancy, Inc. (J. Clancy) filed this action against Ghazanfar Khan and Khan Comfort, LLC (Khan), alleging claims for nonpayment under a contract for renovations of a Spearfish, South Dakota, hotel. Khan answered and filed a counterclaim alleging J. Clancy had failed to complete all the renovations. The circuit court determined following a trial that J. Clancy had breached a series of implied-in-fact contracts by failing to substantially perform the work and awarded Khan a judgment against J. Clancy for overpayment. On appeal, this Court reversed, concluding as a matter of law that J. Clancy and Khan had entered into an express contract for the renovations (Contract). J. Clancy, Inc. v. Khan Comfort, LLC, 2021 S.D. 9, ¶ 45, 955 N.W.2d 382, 397 (J. Clancy I). [¶2.] On remand, the circuit court found, based upon the original trial record, that J. Clancy had fully performed under the terms of the Contract and that Khan had breached the Contract by failing to make timely payments. The court entered a judgment in favor of J. Clancy. Khan appeals the circuit court’s decision on remand, asserting that differences between the circuit court’s initial findings of fact and conclusions of law and those entered on remand necessarily amount to clear error and abuse of discretion. We affirm.

Factual and Procedural Background [¶3.] In reversing the circuit court’s decision in J. Clancy I, we observed that “the terms of the series of implied-in-fact contracts found by the trial court were not the same as the express terms of the [Contract]. This vital distinction change[d] how a party may be found to be in breach and the remedies available to the parties.”

Id. ¶ 28 n.8, 955 N.W.2d at 392 n.8. We explained the parties’ responsibilities under the Contract as follows: “J. Clancy had the right to demand progress payments from [Khan], after providing invoice statements. Notably, [Khan] did not have authority to hold back progress payments even if the goods were not yet delivered. Further, if [Khan] did not provide J. Clancy progress payments within ten days, J. Clancy had the right to immediately stop construction.” Id. ¶ 28, 955 N.W.2d at 392. [¶4.] We remanded for the circuit court to consider the factual questions of whether either party had breached the Contract and the amount of damages. In so doing, we specifically authorized the circuit court to “rely upon the existing evidence in the record regarding the materials and labor found to have been provided by J. Clancy, and the sums [Khan] paid for the agreed-upon items.” Id. ¶ 29 n.10, 955 N.W.2d at 392 n.10. We further authorized the court to “adopt or modify its original findings, or enter new findings as the court deems necessary, to conform with our determination that the duties and obligations of the parties are governed by the express terms of the written contract.” Id. (emphasis added). [¶5.] On remand, the court and parties agreed to rely on the existing trial record. Neither party sought to offer additional evidence. The parties then submitted written briefs and proposed findings of fact and conclusions of law. On October 8, 2021, the circuit court entered its findings of fact and conclusions of law (findings of fact on remand), determining that Khan’s failure to timely pay invoices

billed by J. Clancy was a material breach of the Contract. 1 The court found that J. Clancy fully performed the work and provided the goods and materials required by the Contract. On the question of J. Clancy’s performance under the Contract, the court found Mr. Clancy and his foreman, Mr. Moore, to be more credible than Mr. Khan. In particular, the court found that Khan had failed to provide timely notice of any unsatisfactory or incomplete work at the time of the final walkthrough with the foreman, as required by the Contract, and had failed to complain about any workmanship on the project for months thereafter. [¶6.] On the question of damages, the court found that the two mechanic’s liens filed by J. Clancy accurately reflected the outstanding balances owed under the Contract and under the terms of an earlier agreement for replacement of vanities and fitness equipment at the hotel. The circuit court entered a judgment in favor of J. Clancy for breach of contract and foreclosure of the mechanic’s liens in the amount of $105,135.33, plus prejudgment interest and attorney fees and costs. [¶7.] Khan raises several issues on appeal, which we restate as follows:

1. Whether the circuit court’s findings of fact on remand as to J. Clancy’s performance were clearly erroneous because they differ from the initial findings of fact.

2. Whether the circuit court’s findings of fact on remand as to Khan’s breach of payment obligations were clearly

1. J. Clancy started the project in September and began submitting invoices for payment to Khan on November 7, 2012, for material and labor it claimed exceeded the initial 50% down payment of $154,000. Following numerous subsequent invoices and J. Clancy’s demands for payment, Khan sent J.

Clancy two $35,000 checks on December 4, 2012. Khan did not make further payments. J. Clancy continued working and paying subcontractors until it left the project in February 2013.

erroneous because they differ from the initial findings of fact.

3. Whether the circuit court’s judgment for foreclosure of the mechanic’s liens and award of attorney fees in favor of J.

Clancy was an abuse of discretion because it previously determined on the same record that Khan prevailed.

Standard of Review

[¶8.] We examine findings of fact for clear error. Eagle Ridge Ests. Homeowners Ass’n v. Anderson, 2013 S.D. 21, ¶ 12, 827 N.W.2d 859, 864; SDCL 15- 6-52(a). “[T]he credibility of the witnesses, the import to be accorded their testimony, and the weight of the evidence must be determined by the trial court, and we give due regard to the trial court’s opportunity to observe the witnesses and examine the evidence.” Anderson, 2013 S.D. 21, ¶ 12, 827 N.W.2d at 864 (quoting Hubbard v. City of Pierre, 2010 S.D. 55, ¶ 26, 784 N.W.2d 499, 511). “[T]he amount of damages to be awarded is a factual issue to be determined by the trier of fact.” Peska Props., Inc. v. N. Rental Corp., 2022 S.D. 33, ¶ 20, 976 N.W.2d 749, 755 (alteration in original) (citation omitted). The “[circuit] court’s findings on damages will not be disturbed on appeal unless they are clearly erroneous.” Id. (citation omitted). “Doubts about whether the evidence supports the court’s findings of fact are to be resolved in favor of the successful party’s ‘version of the evidence and of all inferences fairly deducible therefrom which are favorable to the court’s action.’” Osman v. Karlen & Assocs., 2008 S.D. 16, ¶ 15, 746 N.W.2d 437, 443 (citations omitted).

Analysis and Decision

Free access — add to your briefcase to read the full text and ask questions with AI

J. Clancy, Inc. v. Khan Comfort, LLC, 982 N.W.2d 35, 2022 S.D. 68 (S.D. 2022).

982 N.W.2d 35 (J. Clancy, Inc. v. Khan Comfort, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Eagle Ridge Estates Homeowners Ass'n v. Anderson
2013 S.D. 21 (South Dakota Supreme Court, 2013)
Gluscic v. Avera St. Luke's
2002 SD 93 (South Dakota Supreme Court, 2002)
Osman v. Karlen and Associates
2008 SD 16 (South Dakota Supreme Court, 2008)
Hubbard v. CITY OF PIERRE
2010 SD 55 (South Dakota Supreme Court, 2010)
Johnson Farms v. McEnroe
2002 ND 122 (North Dakota Supreme Court, 2003)
State v. Piper
2014 SD 2 (South Dakota Supreme Court, 2014)
State v. Berget
2014 SD 61 (South Dakota Supreme Court, 2014)
ISG, Corp. v. PLE, Inc.
917 N.W.2d 23 (South Dakota Supreme Court, 2018)
Taylor v. Taylor
928 N.W.2d 458 (South Dakota Supreme Court, 2019)
Taylor v. Taylor
2019 S.D. 27 (South Dakota Supreme Court, 2019)
Peska Properties, Inc. v. Northern Rental Corp.
2022 S.D. 33 (South Dakota Supreme Court, 2022)