J. Clancy, Inc. v. Khan Comfort, LLC

982 N.W.2d 35, 2022 S.D. 68
CourtSouth Dakota Supreme Court
DecidedNovember 9, 2022
Docket29876
StatusPublished

This text of 982 N.W.2d 35 (J. Clancy, Inc. v. Khan Comfort, LLC) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. Clancy, Inc. v. Khan Comfort, LLC, 982 N.W.2d 35, 2022 S.D. 68 (S.D. 2022).

Opinion

#29876-a-SRJ 2022 S.D. 68

IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA

****

J. CLANCY, INC., Plaintiff and Appellee,

v.

KHAN COMFORT, LLC, previously known as KHAN DEVELOPMENT, LLC; GHAZANFAR KHAN, individually; Defendants and Appellants,

and

FIRST INTERSTATE BANK, a Montana Banking Corporation; BLACK HILLS COMMUNITY ECONOMIC DEVELOPMENT, INC., a South Dakota Non-Profit Corporation; UNITED STATES SMALL BUSINESS ADMINISTRATION; BKM ENTERPRISES, INC. d/b/a WATCO POOLS, a Montana Corporation; RAPID FIRE PROTECTION, INC., a South Dakota Corporation; and LAWRENCE COUNTY, a political subdivision of the State of South Dakota, Defendants.

APPEAL FROM THE CIRCUIT COURT OF THE FOURTH JUDICIAL CIRCUIT LAWRENCE COUNTY, SOUTH DAKOTA

THE HONORABLE MICHELLE K. COMER Judge

CONSIDERED ON BRIEFS AUGUST 30, 2022 OPINION FILED 11/09/22 ****

SCOTT SUMNER Rapid City, South Dakota Attorney for defendants and appellants.

TIMOTHY J. BARNAUD Belle Fourche, South Dakota Attorney for plaintiff and appellee. #29876

JENSEN, Chief Justice

[¶1.] J. Clancy, Inc. (J. Clancy) filed this action against Ghazanfar Khan

and Khan Comfort, LLC (Khan), alleging claims for nonpayment under a contract

for renovations of a Spearfish, South Dakota, hotel. Khan answered and filed a

counterclaim alleging J. Clancy had failed to complete all the renovations. The

circuit court determined following a trial that J. Clancy had breached a series of

implied-in-fact contracts by failing to substantially perform the work and awarded

Khan a judgment against J. Clancy for overpayment. On appeal, this Court

reversed, concluding as a matter of law that J. Clancy and Khan had entered into

an express contract for the renovations (Contract). J. Clancy, Inc. v. Khan Comfort,

LLC, 2021 S.D. 9, ¶ 45, 955 N.W.2d 382, 397 (J. Clancy I).

[¶2.] On remand, the circuit court found, based upon the original trial

record, that J. Clancy had fully performed under the terms of the Contract and that

Khan had breached the Contract by failing to make timely payments. The court

entered a judgment in favor of J. Clancy. Khan appeals the circuit court’s decision

on remand, asserting that differences between the circuit court’s initial findings of

fact and conclusions of law and those entered on remand necessarily amount to

clear error and abuse of discretion. We affirm.

Factual and Procedural Background

[¶3.] In reversing the circuit court’s decision in J. Clancy I, we observed that

“the terms of the series of implied-in-fact contracts found by the trial court were not

the same as the express terms of the [Contract]. This vital distinction change[d]

how a party may be found to be in breach and the remedies available to the parties.”

-1- #29876

Id. ¶ 28 n.8, 955 N.W.2d at 392 n.8. We explained the parties’ responsibilities

under the Contract as follows: “J. Clancy had the right to demand progress

payments from [Khan], after providing invoice statements. Notably, [Khan] did not

have authority to hold back progress payments even if the goods were not yet

delivered. Further, if [Khan] did not provide J. Clancy progress payments within

ten days, J. Clancy had the right to immediately stop construction.” Id. ¶ 28, 955

N.W.2d at 392.

[¶4.] We remanded for the circuit court to consider the factual questions of

whether either party had breached the Contract and the amount of damages. In so

doing, we specifically authorized the circuit court to “rely upon the existing evidence

in the record regarding the materials and labor found to have been provided by J.

Clancy, and the sums [Khan] paid for the agreed-upon items.” Id. ¶ 29 n.10, 955

N.W.2d at 392 n.10. We further authorized the court to “adopt or modify its

original findings, or enter new findings as the court deems necessary, to conform

with our determination that the duties and obligations of the parties are governed

by the express terms of the written contract.” Id. (emphasis added).

[¶5.] On remand, the court and parties agreed to rely on the existing trial

record. Neither party sought to offer additional evidence. The parties then

submitted written briefs and proposed findings of fact and conclusions of law. On

October 8, 2021, the circuit court entered its findings of fact and conclusions of law

(findings of fact on remand), determining that Khan’s failure to timely pay invoices

-2- #29876

billed by J. Clancy was a material breach of the Contract. 1 The court found that J.

Clancy fully performed the work and provided the goods and materials required by

the Contract. On the question of J. Clancy’s performance under the Contract, the

court found Mr. Clancy and his foreman, Mr. Moore, to be more credible than Mr.

Khan. In particular, the court found that Khan had failed to provide timely notice

of any unsatisfactory or incomplete work at the time of the final walkthrough with

the foreman, as required by the Contract, and had failed to complain about any

workmanship on the project for months thereafter.

[¶6.] On the question of damages, the court found that the two mechanic’s

liens filed by J. Clancy accurately reflected the outstanding balances owed under

the Contract and under the terms of an earlier agreement for replacement of

vanities and fitness equipment at the hotel. The circuit court entered a judgment in

favor of J. Clancy for breach of contract and foreclosure of the mechanic’s liens in

the amount of $105,135.33, plus prejudgment interest and attorney fees and costs.

[¶7.] Khan raises several issues on appeal, which we restate as follows:

1. Whether the circuit court’s findings of fact on remand as to J. Clancy’s performance were clearly erroneous because they differ from the initial findings of fact.

2. Whether the circuit court’s findings of fact on remand as to Khan’s breach of payment obligations were clearly

1. J. Clancy started the project in September and began submitting invoices for payment to Khan on November 7, 2012, for material and labor it claimed exceeded the initial 50% down payment of $154,000. Following numerous subsequent invoices and J. Clancy’s demands for payment, Khan sent J. Clancy two $35,000 checks on December 4, 2012. Khan did not make further payments. J. Clancy continued working and paying subcontractors until it left the project in February 2013.

-3- #29876

erroneous because they differ from the initial findings of fact.

3. Whether the circuit court’s judgment for foreclosure of the mechanic’s liens and award of attorney fees in favor of J. Clancy was an abuse of discretion because it previously determined on the same record that Khan prevailed.

Standard of Review

[¶8.] We examine findings of fact for clear error. Eagle Ridge Ests.

Homeowners Ass’n v. Anderson, 2013 S.D. 21, ¶ 12, 827 N.W.2d 859, 864; SDCL 15-

6-52(a). “[T]he credibility of the witnesses, the import to be accorded their

testimony, and the weight of the evidence must be determined by the trial court,

and we give due regard to the trial court’s opportunity to observe the witnesses and

examine the evidence.” Anderson, 2013 S.D. 21, ¶ 12, 827 N.W.2d at 864 (quoting

Hubbard v. City of Pierre, 2010 S.D. 55, ¶ 26, 784 N.W.2d 499, 511). “[T]he amount

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eagle Ridge Estates Homeowners Ass'n v. Anderson
2013 S.D. 21 (South Dakota Supreme Court, 2013)
Gluscic v. Avera St. Luke's
2002 SD 93 (South Dakota Supreme Court, 2002)
Osman v. Karlen and Associates
2008 SD 16 (South Dakota Supreme Court, 2008)
Hubbard v. CITY OF PIERRE
2010 SD 55 (South Dakota Supreme Court, 2010)
Johnson Farms v. McEnroe
2002 ND 122 (North Dakota Supreme Court, 2003)
State v. Piper
2014 SD 2 (South Dakota Supreme Court, 2014)
State v. Berget
2014 SD 61 (South Dakota Supreme Court, 2014)
ISG, Corp. v. PLE, Inc.
917 N.W.2d 23 (South Dakota Supreme Court, 2018)
Taylor v. Taylor
928 N.W.2d 458 (South Dakota Supreme Court, 2019)
Taylor v. Taylor
2019 S.D. 27 (South Dakota Supreme Court, 2019)
J. Clancy, Inc. v. Khan Comfort, LLC
955 N.W.2d 382 (South Dakota Supreme Court, 2021)
Peska Properties, Inc. v. Northern Rental Corp.
2022 S.D. 33 (South Dakota Supreme Court, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
982 N.W.2d 35, 2022 S.D. 68, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-clancy-inc-v-khan-comfort-llc-sd-2022.