I.O.A. Leasing Corp. v. Merle Thomas Corp.

272 A.2d 1, 260 Md. 243, 1971 Md. LEXIS 1230
CourtCourt of Appeals of Maryland
DecidedJanuary 5, 1971
Docket[No. 128, September Term, 1970.]
StatusPublished
Cited by23 cases

This text of 272 A.2d 1 (I.O.A. Leasing Corp. v. Merle Thomas Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
I.O.A. Leasing Corp. v. Merle Thomas Corp., 272 A.2d 1, 260 Md. 243, 1971 Md. LEXIS 1230 (Md. 1971).

Opinion

Finan, J.,

delivered the opinion of the Court.

We must decide in this case whether or not the trial judge was correct in his denial of the appellant’s motion for judgment n.o.v. or, in the alternative, for a new trial. The facts are complicated and lengthy, involving, as they do, a computer leasing contract, so for the benefit of those with little perseverance we state at the outset that we affirm the lower court. The facts which the jury had to consider were as follows:

On April 13, 1967, the appellant (I.O.A.), a computer leasing company, entered into a contract with the appellee Merle Thomas Corporation (M.T.C.), a company in *245 the business of renting time on its computers to individual customers. Under the terms of the contract, I.O.A. was to lease to M.T.C. an IBM 1401 computer system consisting of a central processing unit and eight auxiliary pieces of equipment. There were no warranties as to the condition of the computer in the contract, and no statement that time was to be of the essence. The contract did state that the monthly rental would be 20 % less than the price charged by IBM for the same system, and that M.T.C. would not be required to pay any overtime charges for use of the system. Normal IBM maintenance was to be paid by I.O.A., and the overtime or “second shift” maintenance charges were to be paid by M.T.C. I.O.A. was to pay the shipping charges for delivery of the system to M.T.C. and also the charges for having the system installed; however, the contract was silent as to which party was actually responsible for installation.

The total monthly rental for the system was $6,448.00, of that sum $3,088.00 was payment for the central processing unit, and $3,360.00 for the eight auxiliary pieces of equipment. Rental payments were to commence on May 15, 1967, “subject to the date of delivery.” I.O.A. had purchased the 1401 central processing unit from a bank in Worcester, Massachusetts for $72,000.00 and undertook to make the delivery on May 15,1967.

There was a delay caused by a trucking strike, and the central processing unit was not delivered to M.T.C. until May 30, 1967. Notwithstanding the fact that the system in question was under an IBM maintenance contract, the physical condition of the central processing unit which was delivered left much to be desired, and was described by various witnesses as “filthy,” “dirty,” “greasy,” “grimy,” “a mess,” and “full of dents.” In spite of their reservations about the condition of the unit and its ability to perform, the individuals responsible at M.T.C. accepted delivery of it because they apparently had no other available source from which to get this particular computer system.

It is not clear from the contract who was responsible *246 for getting IBM to install the system, and it is not clear from the record who actually made the initial attempts at having the machine installed in early June of 1967, but the attempts were unsuccessful. A meeting between the parties and their attorneys was held in New York City on June 19, 1967, in an effort to resolve the problems which had arisen. What is clear from the record is that after this meeting, I.O.A. was the party which in fact was attempting to get the unit installed with the same unimpressive results as were produced by the earlier efforts. In any event, M.T.C. allocated time for installation of the unit on four or five occasions between early June, 1967 and June 27, 1967, and nobody ever appeared to do the work. 1 This, coupled with the appearance of the unit, and late and partial delivery, was causing great annoyance to Mr. Merle Thomas (the President of M.T.C.). On June 27, 1967, I.O.A. telephoned and asked M.T.C. to allocate time on the next day (June 28th) instead of June 29th as had previously been planned. This was apparently the proverbial straw which broke, in this case, the appellee’s back. Because of the inconvenience which would result to its customers and the short time element involved, M.T.C. decided that it could not make such a change and terminated the contract, thereby leaving I.O.A. with one used data processing unit worth approximately $72,000.00 which appeared to be everybody’s “ugly duckling.” 2 Thus began the parties’ journey to this Court.

On September 15, 1967, M.T.C. filed suit in the Circuit Court for Montgomery County. After preliminary *247 motions were disposed of I.O.A. filed an answer and counterclaim on June 19, 1968. On December 8, 1969, a jury trial was commenced and at the close of all the evidence I.O.A. moved for a directed verdict. Its motion was denied and the jury awarded M.T.C. a verdict of $21,561.00 on December 9, 1969. On December 12, 1969, the appellant filed a motion for judgment n.o.v. or for a new trial in the alternative. This motion was denied at a hearing on January 16, 1970, and a remittitur of the verdict to an amount of $17,961.55 was granted and agreed to by the appellee. From a denial of its motion for judgment n.o.v. or for a new trial, I.O.A. brings this appeal.

Appellant’s primary contention is that as a matter of law, M.T.C. could not, with impunity, cancel the contract without ever having had the computer installed to see whether or not it would work, and that any evidence as to the delivery or condition of the computer was not relevant. Appellant argues that there was an implied condition precedent which required M.T.C. to “plug in” or “hook up” the unit. In appellant’s view of the case, the issue is “whether or not the machine would perform,” and it compares the case at bar to an automobile lease, and hypothesizes a situation wherein the lessee receives a dirty and dented automobile and rescinds the rental contract without ever having tried to start the car. The analogy is appealing in its simplicity, but not quite accurate. Had the lessee of the automobile in the hypothetical situation received a car which was not only dirty and dented, but also without gasoline, wheels, doors, or windows, the analogy would have been more complete. In such a case it could hardly be said that, as a matter of law, he would have to turn the key in the ignition before he could consider the contract to be at an end.

Appellant’s argument not only assumes that M.T.C. was responsible for the installation of the system (which issue was hotly contested throughout the trial and the resolution of which was left for the determination of the jury), but also ignores the fact that there must first have been a delivery “under the terms of the contract,” as noted by Judge Miller in his instructions to the jury. *248 Judge Miller elaborated on that phrase by instructing that the appellant had to show that it “delivered the goods that were intended to be delivered by the parties when they entered into the contract or lease agreement,” and that the jury might consider, relative to the question of delivery, the reasonableness of the time of the delivery, and the “condition of the equipment.” He continued that if the jury found that there was not a complete delivery, they should then apply the doctrine of substantial performance, unless they were of the opinion that there was a “material failure to deliver,” in which case the verdict would be for the plaintiff (appellee).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Retina Grp. of Wash., P.C. v. Crosetto
183 A.3d 873 (Court of Special Appeals of Maryland, 2018)
Attorney Grievance Commission v. Alston
53 A.3d 1142 (Court of Appeals of Maryland, 2012)
Carter v. Senate Masonry, Inc.
846 A.2d 50 (Court of Special Appeals of Maryland, 2004)
Bowden v. Caldor, Inc.
710 A.2d 267 (Court of Appeals of Maryland, 1998)
Johns Hopkins University v. Ritter
689 A.2d 91 (Court of Special Appeals of Maryland, 1997)
Mallard v. Earl
665 A.2d 287 (Court of Special Appeals of Maryland, 1995)
Bartholomee v. Casey
651 A.2d 908 (Court of Special Appeals of Maryland, 1994)
Market Tavern, Inc. v. Bowen
610 A.2d 295 (Court of Special Appeals of Maryland, 1992)
Standiford v. Standiford
598 A.2d 495 (Court of Special Appeals of Maryland, 1991)
Alexander v. Montgomery County
589 A.2d 563 (Court of Special Appeals of Maryland, 1991)
Montgomery County v. Voorhees
586 A.2d 769 (Court of Special Appeals of Maryland, 1991)
Thodos v. Bland
542 A.2d 1307 (Court of Special Appeals of Maryland, 1988)
G.C. Murphy Co. v. Greer
541 A.2d 996 (Court of Special Appeals of Maryland, 1988)
Fouche v. Masters
420 A.2d 1279 (Court of Special Appeals of Maryland, 1980)
Walker v. Hall
369 A.2d 105 (Court of Special Appeals of Maryland, 1977)
Keene v. Insley
337 A.2d 168 (Court of Special Appeals of Maryland, 1975)
Moran v. Fabergé, Inc.
332 A.2d 11 (Court of Appeals of Maryland, 1975)
Moran v. Williams
313 A.2d 527 (Court of Special Appeals of Maryland, 1974)
Tippett v. Quade
309 A.2d 481 (Court of Special Appeals of Maryland, 1973)
Lloyd v. Bowles
273 A.2d 193 (Court of Appeals of Maryland, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
272 A.2d 1, 260 Md. 243, 1971 Md. LEXIS 1230, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ioa-leasing-corp-v-merle-thomas-corp-md-1971.