Interstate Fire Protection v. Repal Construction

CourtSuperior Court of Pennsylvania
DecidedDecember 15, 2014
Docket41 WDA 2014
StatusUnpublished

This text of Interstate Fire Protection v. Repal Construction (Interstate Fire Protection v. Repal Construction) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Interstate Fire Protection v. Repal Construction, (Pa. Ct. App. 2014).

Opinion

J-A27029-14

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

INTERSTATE FIRE PROTECTION : IN THE SUPERIOR COURT OF COMPANY, INC., : PENNSYLVANIA : Appellee : : v. : : REPAL CONSTRUCTION COMPANY, : INC., : : Appellant : No. 41 WDA 2014

Appeal from the Order Entered December 13, 2013, In the Court of Common Pleas of Allegheny County, Civil Division, at No. GD-11-21284.

BEFORE: FORD ELLIOTT, P.J.E., SHOGAN and MUSMANNO, JJ.

MEMORANDUM BY SHOGAN, J.: FILED DECEMBER 15, 2014

Repal Construction Company, Inc. (“Repal” or “contractor”) appeals

from the December 13, 2013 order from the Court of Common Pleas of

Allegheny County, overruling Repal’s preliminary objections. Specific to this

appeal, Repal had alleged that claims in the complaint filed against it by

Interstate Fire Protection Company, Inc. (“Interstate” or “subcontractor”),

were subject to an arbitration agreement. For the reasons that follow, we

affirm.

Interstate is a fire protection subcontractor that performed work on

construction projects for Repal. On October 14, 2011, Interstate filed a

three-count complaint against Repal seeking recovery for work it performed J-A27029-14

on nine different projects governed by nine separate subcontracts. All of the

subcontracts contained alternative dispute resolution provisions. The

dispute resolution provisions in the nine contracts fall basically into two

groups. The relevant clause in the WalMart,1 Panera Bread, and Back Stage

Pass agreements is found at Paragraph 4 of Exhibit A (“Exhibit A”) attached

to the subcontracts and reads:

In case of any disputes between the Subcontractor and Contractor, the Subcontractor agrees that the form of dispute resolution between it and the contractor shall be governed by the terms of the Contract Documents to the same manner of dispute resolution as is provided for between the Owner and Contractor and by any and all decisions or determinations whether by court, arbitrator(s) or architect made with respect thereto. This provision is to be defined as requiring the Subcontractor to be governed by arbitration, mediation or legal or equitable action if the contractor is required to use those means of resolving contract disputes on the project with the Owner. However, notwithstanding anything to the contrary herein, the Contractor may elect that any dispute between it and the Subcontractor shall be governed by action in a court of law or equity. This election shall be made within 60 days after Subcontractor notifies Contractor of its intent to seek dispute resolution and specifically refers to this provision.

The pertinent clauses in the Union Aid Society, Tenant Fit-Out, Bryant

Street Project, Third East Hills, and World Vision agreements include the

1 The WalMart subcontract also included a provision requiring the parties to submit their claims to non-binding mediation as a condition precedent to filing suit. Addendum to the Repal Subcontract for the WalMart Project, Exhibit “C”, ¶ 4. Although Repal referenced Interstate’s failure to comply with this provision in its preliminary objections, the trial court did not address the unique clause included in the WalMart agreement. Repal does not challenge the trial court’s omission in this regard on appeal.

-2- J-A27029-14

above-recited provision, also attached as Exhibit A to each of those

subcontracts, and an additional provision included in the body of the

agreements:

§ 6.1.2. Claims not involving the Owner.

Contractor and Subcontractor agree that claims and disputes, between themselves, and/or the Contractor's surety, shall be resolved either by arbitration to be conducted by the Construction Dispute Resolution Group of the Allegheny County Bar Association (“CDRG”) . . . or litigation before the Court of Common Pleas of Allegheny County, Pennsylvania or in the Federal District Court for the Western District of Pennsylvania, without a jury, or before a jury, all as the Contractor or Contractor's surety, if any, should in their sole discretion elect . . . . This shall be acknowledged as Subcontractor's consent to arbitration, notwithstanding that the decision to arbitrate disputes shall be in the sole discretion of Contractor.

The North Allegheny agreement includes the above-recited § 6.1.2.

clause (“Paragraph 6”) concerning claims not involving the owner; however,

Exhibit A attached to the North Allegheny subcontract is an “open shop

performance clause.” The North Allegheny subcontract does not include the

Exhibit A notice provision that is incorporated into the other eight

agreements.

Repal filed preliminary objections to the complaint on December 12,

2011, alleging, inter alia, that the complaint must be dismissed based on

Repal’s reading of the language in the subcontracts that compels the parties

to submit their claims to arbitration, if Repal so elects. On February 20,

2012, pursuant to Allegheny County Court Local Rule 1028(C)(1)(c)(ii),

-3- J-A27029-14

Repal filed evidence in connection with its preliminary objections, to wit,

letters dated February 17, 2012, informing Interstate of Repal’s election to

submit seven of the nine disputes to arbitration.2 Repal also attached copies

of contracts between it and the owners of four of the projects where

Interstate performed subcontractor work.

Argument on Repal’s preliminary objections was scheduled for March

12, 2012, but the parties agreed to a continuance so that they could attempt

to reach an amicable resolution. However, there was minimal

communication between the parties and, it was not until twenty months later

on November 1, 2013, that Interstate filed an Answer to Repal’s Preliminary

Objections. Interstate argued that the matter could not be referred to

arbitration because the arbitration entity, CDRG, no longer existed and

because the request for arbitration was untimely.

After oral argument, the trial court overruled Repal’s arbitration-based

preliminary objection, reasoning:

The Arbitration language is cast in the disjunctive and the Arbitration entity does not exist . . . . I do not believe the language of the contracts can permit me to impose some other Arbitration entity upon Plaintiff especially because of the word “or.”

Trial Court Order, 12/13/13, at 2 (emphasis in original).

The trial court then overruled the remaining preliminary objections and

2 Repal did not submit arbitration-election letters in regard to the WalMart and Back Stage Pass disputes.

-4- J-A27029-14

ordered Repal to file an answer. Id.

On January 3, 2014, Repal filed an appeal.3 On January 22, 2014, the

trial court issued an opinion, concluding that the invocation of arbitration

was outside the time limitation agreed upon, and further, that even if the

invocation was timely, the entity for arbitration was now defunct.

Appellant raises the following issues for review:4

1. DID THE TRIAL COURT ERR IN FINDING THAT THE PARTIES DID NOT HAVE A VALID AGREEMENT TO ARBITRATE?

2. DID THE TRIAL COURT ABUSE ITS DISCRETION WHEN IT DETERMINED THAT APPELLANT’S INVOCATION OF DISPUTE RESOLUTION WAS OUTSIDE THE TIME LIMITATION IMPOSED AND AGREED UPON BY THE PARTIES, WHERE THE APPELLANT TIMELY NOTIFIED APPELLEE OF ITS ELECTION TO ARBITRATE?

3. DID THE TRIAL COURT ABUSE ITS DISCRETION WHEN IT DETERMINED THAT THE AGREEMENT TO ARBITRATE COULD NOT BE ENFORCED BECAUSE THE ARBITRATION ENTITY NO LONGER EXISTS?

Appellant’s Brief at 3.

When reviewing a trial court’s denial of a motion to compel arbitration,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Toy v. Metropolitan Life Insurance
863 A.2d 1 (Superior Court of Pennsylvania, 2004)
Shadduck v. Christopher J. Kaclik, Inc.
713 A.2d 635 (Superior Court of Pennsylvania, 1998)
Midomo Co. v. Presbyterian Housing Development Co.
739 A.2d 180 (Superior Court of Pennsylvania, 1999)
Marks v. Nationwide Insurance Co.
762 A.2d 1098 (Superior Court of Pennsylvania, 2000)
Smith v. Cumberland Group, Ltd.
687 A.2d 1167 (Superior Court of Pennsylvania, 1997)
Boyer v. Walker
714 A.2d 458 (Superior Court of Pennsylvania, 1998)
Stewart v. GGNSC-Canonsburg, L.P.
9 A.3d 215 (Superior Court of Pennsylvania, 2010)
Reddam v. KPMG LLP
457 F.3d 1054 (Ninth Circuit, 2006)
Smay v. E.R. Stuebner, Inc.
864 A.2d 1266 (Superior Court of Pennsylvania, 2004)
Elwyn v. DeLuca
48 A.3d 457 (Superior Court of Pennsylvania, 2012)
Pisano v. Extendicare Homes, Inc.
77 A.3d 651 (Superior Court of Pennsylvania, 2013)
Wert v. ManorCare of Carlisle PA, LLC
95 A.3d 268 (Supreme Court of Pennsylvania, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Interstate Fire Protection v. Repal Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/interstate-fire-protection-v-repal-construction-pasuperct-2014.