Elwyn v. DeLuca

48 A.3d 457, 2012 Pa. Super. 136, 2012 WL 2513461, 2012 Pa. Super. LEXIS 1064
CourtSuperior Court of Pennsylvania
DecidedJuly 2, 2012
StatusPublished
Cited by78 cases

This text of 48 A.3d 457 (Elwyn v. DeLuca) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elwyn v. DeLuca, 48 A.3d 457, 2012 Pa. Super. 136, 2012 WL 2513461, 2012 Pa. Super. LEXIS 1064 (Pa. Ct. App. 2012).

Opinion

OPINION BY FITZGERALD, J.:

Appellant, James J. DeLuca, appeals from the order entered in the Delaware County Court of Common Pleas overruling his preliminary objection to the complaint of Appellee, Elwyn. We are presented with the question: When an organization executes a contract with a second organization that is owned or led by one of its board members, and the first organization subsequently brings a breach of fiduciary duty suit against the board member relating to his duties as a board member and a separate breach of contract suit against the second organization, is the breach of fiduciary duty claim bound by a mandatory arbitration clause in the contract between the first and second organizations? We hold that it is not. Thus, we affirm the court’s order.

* Former Justice specially assigned to the Superior Court.

Appellee is a non-profit human services organization and is managed by a board of directors. Appellee’s Compl., 2/11/11, at ¶¶ 4-5. Appellant was a member of the board;1 he is also the co-owner, president, and CEO of J.J. DeLuca Company, Inc. (“JJDC”), a construction corporation. Appellee engaged JJDC to construct a residential building. On July 27, 2009,2 Appellee, as “Owner,” and JJDC, as “Construction Manager,” executed a contract, which was “an industry standard American Institute of Architects (AIA) form document modified by [the parties] for the Project, and consisted] of two principal parts: a Standard Form of Agreement between Owner and Construction Manager ... and the General Conditions of the Contract for Construction” (collectively, the “Contract”). Appellant’s Brief at 5. The trial court summarized:

Under the terms of the Contract, JJDC was to make the appropriate proportional payments to subcontractors for their completed work once payment was received from [Appellee. Appellee] claim[ed] that, although contracts were entered between JJDC and subcontractors for the building project and [Appel-lee] paid the invoices received from JJDC for the subcontractor’s work, JJDC failed to pay the subcontractors, thereby breaching the Contract with [Appellee],

Trial Ct. Op., 8/31/11, at 1-2.

On February 11, 2011, Appellee filed a complaint against Appellant, claiming [460]*460breach of fiduciary duty and, in the alternative, seeking common law indemnity. On the same day, Appellee also initiated a suit against JJDC, claiming breach of contract, unjust enrichment, fraudulent misrepresentation, negligent misrepresentation, and indemnification.3 In the instant matter, Appellee’s complaint asserted that Appellant, as a board member of Appellee, lobbied his fellow board members to select his company, JJDC, for the building project, and

willfully influenced the Board to award the contract to his company without disclosing all material facts and intentionally withholding facts, by acting in his overall self interest and not disclosing the extent of his profits from the building project, by failing to advise [Appel-lee] that the subcontractors were not being paid when it was within his knowledge, by misapplying funds received from [Appellee] in his capacity as President and CEO of JJDC, and by accepting payments on behalf of JJDC to which it was not entitled.

Id. at 2. Appellee’s alternative claim for common law indemnity

alleg[ed] that [Appellant] is primarily responsible for funds due to subcontractors for which the subcontractors have sought payment from [Appellee. Appel-lee] requested that the Court indemnify [it] from the costs owed to subeontrac-tors to whom JJDC never made payment.

Id.

On March 25, 2011, Appellant filed preliminary objections, arguing, inter alia, “that the claims set forth in [Appellee’s] Complaint were subject to an agreement for alternative dispute resolution which mandated mediation and binding arbitration of all disputes between the parties.” Id. at 2. On June 3rd, the court overruled the preliminary objections and directed Appellant to file an answer to Appellee’s complaint. Appellant instead took this timely appeal, presenting three issues for our review, which we address together.4

Appellant first avers that the Contract between Appellee and JJDC includes an enforceable agreement to arbitrate, and that he “is only seeking to hold [Appellee] to the contractual terms to which it has bound itself.” Appellant’s Brief at 15. Appellant contends that although he was not a signatory to the contract, he has standing to enforce the agreement in this suit. He cites to Dodds v. Pulte Home Corp., 909 A.2d 348 (Pa.Super.2006), in arguing Appellee’s claim against him “is closely intertwined with the contractual claims, stems from the same facts and implicates the same legal [principles and thus] also subject to arbitration.” Appellant’s Brief at 12-13. Appellant also asserts that while the trial court concluded Appellee’s breach of fiduciary claim [461]*461against him was separate from its breach of contract claim against JJDC, the court failed to look beyond “the labels applied to the claims” in Appellee’s complaint and address the inclusion of the breach of contract claims. Id. at 18-14. Instead, Appellant reasons, the gist of Appellee’s actions against him “arise from the Contract and are inextricably entwined with its claims against” JJDC. Id. at 16. Appellant emphasizes that the primary factual basis in Appellee’s complaint is “the allegations of (i) a failure to make required payments to subcontractors ... and (ii) the seeking of the receipt of payments not authorized by the Contract.” Id. We find no relief is due.

We note the relevant standard of review:

We review a trial court’s denial of a motion to compel arbitration for an abuse of discretion and to determine whether the trial court’s findings are supported by substantial evidence. In doing so, we employ a two-part test to determine whether the trial court should have compelled arbitration. The first determination is whether a valid agreement to arbitrate exists. The second determination is whether the dispute is within the scope of the agreement.

Smay v. E.R. Stuebner, Inc., 864 A.2d 1266, 1270 (Pa.Super.2004) (citations omitted).

Whether a claim is within the scope of an arbitration provision is a matter of contract, and as with all questions of law, our review of the trial court’s conclusion is plenary. “The scope of arbitration is determined by the intention of the parties as ascertained in accordance with the rules governing contracts generally.” “These are questions of law and our review is plenary.”

Id. at 1272-73 (citations omitted).

Arbitration is a matter of contract, and parties to a contract cannot be compelled to arbitrate a given issue absent an agreement between them to arbitrate that issue. Even though it is now the policy of the law to favor settlement of disputes by arbitration and to promote the swift and orderly disposition of claims, arbitration agreements are to be strictly construed and such agreements should not be extended by implication.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shultz, A. v. Sky Zone, LLC, Aplt.
Supreme Court of Pennsylvania, 2025
Santiago v. Philly Trampoline Park, Aplts.
Supreme Court of Pennsylvania, 2025
Golden Eagle Resources v. EQT Production
Superior Court of Pennsylvania, 2025
Clay, B. v. First National Bank
Superior Court of Pennsylvania, 2025
Pennenergy Resources v. MDS Energy
2024 Pa. Super. 219 (Superior Court of Pennsylvania, 2024)
Complete Business Solutions v. Redmond, A.
Superior Court of Pennsylvania, 2024
Yurkanin & Zabriski PC v. Yurkanin, G.
Superior Court of Pennsylvania, 2024
McCrossin, J. v. Comcast Spectacor
2024 Pa. Super. 18 (Superior Court of Pennsylvania, 2024)
Kriebel Minerals v. EQT Corporation
Superior Court of Pennsylvania, 2024
Doe, J. v. The Cheesecake Factory
2023 Pa. Super. 153 (Superior Court of Pennsylvania, 2023)
PennEnergy v. Winfield Resources
2023 Pa. Super. 130 (Superior Court of Pennsylvania, 2023)
Pennenergy Resources, LLC v. Winfield Resources
2023 Pa. Super. 75 (Superior Court of Pennsylvania, 2023)
MURPHY v. EPIQ SYSTEMS
W.D. Pennsylvania, 2022
MBC Development, LP v. Miller, J.
2022 Pa. Super. 141 (Superior Court of Pennsylvania, 2022)
Humphrey, P. v. GlaxoSmithKline PLC
2021 Pa. Super. 180 (Superior Court of Pennsylvania, 2021)
Dakota Oil Processing v. Hayes, C.
Superior Court of Pennsylvania, 2021
Paul O'Hanlon v. Uber Technologies Inc
990 F.3d 757 (Third Circuit, 2021)
Davis, H. v. 2507 Chestnut St. Operations
Superior Court of Pennsylvania, 2019
Gallagher, M. v. Hearthside Realty, Inc.
Superior Court of Pennsylvania, 2019

Cite This Page — Counsel Stack

Bluebook (online)
48 A.3d 457, 2012 Pa. Super. 136, 2012 WL 2513461, 2012 Pa. Super. LEXIS 1064, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elwyn-v-deluca-pasuperct-2012.