Cameron Troilo, Inc. v. B. Blair Corp

CourtSuperior Court of Pennsylvania
DecidedAugust 25, 2020
Docket2785 EDA 2019
StatusUnpublished

This text of Cameron Troilo, Inc. v. B. Blair Corp (Cameron Troilo, Inc. v. B. Blair Corp) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cameron Troilo, Inc. v. B. Blair Corp, (Pa. Ct. App. 2020).

Opinion

J-S33017-20

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

CAMERON C. TROILO, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA : v. : : : B. BLAIR CORPORATION : : Appellant : No. 2785 EDA 2019

Appeal from the Order Entered August 28, 2019 In the Court of Common Pleas of Bucks County Civil Division at No(s): No. 2016-03212

BEFORE: DUBOW, J., MURRAY, J., and STEVENS, P.J.E.*

MEMORANDUM BY MURRAY, J.: Filed: August 25, 2020

B. Blair Corporation (Appellant) appeals from the order granting in part

and denying in part its motion to compel arbitration of the breach of

contract/warranty action brought against by Appellee, Cameron C. Troilo, Inc.

(Troilo). Upon review, we affirm.

The trial court summarized the history relevant to this appeal as follows:

This case involves a contract for site development work and paving. [Troilo] was the lead contractor on a development project called “Flowers Field.” Troilo began contract negotiations with [Appellant] to provide asphalt work on the project. Neither party would agree to the proposed terms of a written contract offered by the other [(hereinafter, “proposed contracts”)]. However, the parties entered into an oral agreement to start work. This oral agreement was based on the terms of a price sheet that had been

____________________________________________

* Former Justice specially assigned to the Superior Court. J-S33017-20

proposed by [Appellant (“Price Sheet”).1] Work began on the project under these terms, ratifying the oral contract. This agreement has been identified by the court and the parties as the “Basic Contract.”

As work was being performed under the Basic Contract, issues arose regarding the quality of the asphalt work. Troilo claims the asphalt “deviated from the prescribed PennDot Job Mix Formula (“JMF”) target gradation, because the asphalt did not have a sufficient amount of asphalt in it.” On May 23, 2016, Troilo filed a complaint against [Appellant] claiming breach of contract, breach of express warranty, and breach of implied warranty. On July 19, 2016, [Appellant] filed an answer and new matter.

Aside from the work performed under the Basic Contract, additional work was performed [by Appellant] at the Flowers Field project. To contract for this extra work, [Appellant and Troilo] entered [into] a series of [written] Additional Work Authorization agreements [(collectively, “AWAs”) over several months]. These were signed by the foreperson assigned to the site as [Appellant’s] representative[,] and Cameron Troilo, Jr., on behalf of Troilo. Each [AWA] included the following provision:

At [Appellant’s] election, and its sole discretion, any claim between [Appellant] and Troilo arising from a dispute under this Agreement shall be submitted to arbitration in accordance with the Construction Industry Rules of the American Arbitration Association [(“AAA”)]. Any award rendered by an arbitrator or arbitrators shall be final and judgment may be entered upon it. [(hereinafter, “the AWA arbitration provision”).]

On January 14, 2019, [Appellant] filed a Demand for Arbitration with the [AAA], pursuant to their contention that [under the AWA arbitration provision,] all disputes related to the Flowers Field project were subject to compulsory arbitration. On January 25, 2019, Troilo filed a Petition to Stay and Enjoin [the

1 The Price Sheet, which neither party signed, contained a provision stating that any disputes arising out of the parties’ agreement concerning the Flowers Field project would be resolved in the Bucks County Court of Common Pleas. Appellant’s Motion to Compel arbitration, 3/21/19, Exhibit 1 (Price Sheet).

-2- J-S33017-20

arbitration]. On March 21, 2019, [Appellant] filed a [Motion] to Compel.

On July 2, 2019, oral argument was held on Troilo’s Petition to Stay and Enjoin … and [Appellant’s Motion] to Compel arbitration. On August 28, 2019, the court issued an order granting in part and denying in part the Motion to Compel. The Motion was: “GRANTED only to the [AWAs] signed by both parties that contained the [AWA] arbitration provision. It is DENIED as to the “Basic Contract” which was never signed by the parties. [Order, 8/28/19, at 1 (emphasis added); see also id. at 1-2 (stating that the Basic Contract “was ratified by the performance of the work with the clear understanding by Troilo and [Appellant] that the arbitration [] provision was not agreed upon.”)]. The work performed under the [AWAs] was also subject to the lawsuit filed by Troilo, as the allegations relate to all of the asphalt work performed by [Appellant].

Trial Court Opinion, 1/17/20, at 1-3 (footnote citations and some capitalization

omitted, footnote and emphasis added).

Further, the “Terms and Conditions” section of the AWAs provides:

These Terms and Conditions shall supplement any prior written agreement between the Parties on the Project where the work is being performed and shall apply to the work described above [(hereinafter, the “supplement provision”)], but if no prior written agreement exists, these terms and conditions shall represent the entire Agreement between [Appellant] and [Troilo (hereinafter, the “completeness provision”).] …

Motion to Compel, 3/21/19, Exhibit 2 (AWAs).

Appellant timely filed a notice of appeal from the August 28, 2019

order,2 followed by a court-ordered Pa.R.A.P. 1925(b) concise statement of

errors complained of on appeal.

2 See 42 Pa.C.S.A. § 7320(a)(1) (providing that an “appeal may be taken from” a “court order denying an application to compel arbitration”).

-3- J-S33017-20

Appellant presents five issues for our review:

1. Should the court order the parties to arbitrate all disputes under both the Basic Contract and the AWAs based upon the supplement provision, which added the arbitration agreement to the Basic Contract as a supplemental term?

2. As a subset to question #1, should the court enforce all of the terms and conditions in the AWAs, including the term which states that the terms of the AWAs “shall supplement any prior written agreement,” as well as the supplemental terms themselves, including the arbitration agreement?

3. As a subset to question #1, should the court enforce all of the terms and conditions of the AWAs, which provide that “if no prior written agreement exists, these terms and conditions shall represent the entire agreement?”

4. As a subset to question #1, is enforcement of the arbitration agreement incompatible with the terms of the Basic Contract?

5. Should the Court stay all proceedings in the lower court pending the outcome of the required arbitration?

Appellant’s Brief at 5-6 (some capitalization omitted).

We address Appellant’s first four issues simultaneously, mindful of our

standard of review:

We review a trial court’s denial of a motion to compel arbitration for an abuse of discretion and to determine whether the trial court’s findings are supported by substantial evidence. In doing so, we employ a two-part test to determine whether the trial court should have compelled arbitration. The first determination is whether a valid agreement to arbitrate exists. The second determination is whether the dispute is within the scope of the agreement.

Whether a claim is within the scope of an arbitration provision is a matter of contract, and as with all questions of law, our review of the trial court’s conclusion is plenary. The scope of arbitration is determined by the intention of the parties as

-4- J-S33017-20

ascertained in accordance with the rules governing contracts generally. These are questions of law and our review is plenary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greene v. Oliver Realty, Inc.
526 A.2d 1192 (Supreme Court of Pennsylvania, 1987)
Maleski v. Mutual Fire, Marine & Inland Insurance
633 A.2d 1143 (Supreme Court of Pennsylvania, 1993)
Krebs v. United Refining Co. of Pennsylvania
893 A.2d 776 (Superior Court of Pennsylvania, 2006)
Elwyn v. DeLuca
48 A.3d 457 (Superior Court of Pennsylvania, 2012)
Setlock v. Pinebrook Personal Care & Retirement Center
56 A.3d 904 (Superior Court of Pennsylvania, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Cameron Troilo, Inc. v. B. Blair Corp, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cameron-troilo-inc-v-b-blair-corp-pasuperct-2020.