Interceramic, Inc. v. South Orient RR Co., Ltd.

999 S.W.2d 920, 1999 WL 722643
CourtCourt of Appeals of Texas
DecidedOctober 13, 1999
Docket06-98-00158-CV
StatusPublished
Cited by22 cases

This text of 999 S.W.2d 920 (Interceramic, Inc. v. South Orient RR Co., Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Interceramic, Inc. v. South Orient RR Co., Ltd., 999 S.W.2d 920, 1999 WL 722643 (Tex. Ct. App. 1999).

Opinion

OPINION

WILLIAM J. CORNELIUS, Chief Justice.

Interceramic, Inc. appeals from an adverse judgment in a breach of contract suit tried to the court. South Orient Railroad Company sued Interceramic for breach of contract because Interceramic failed to ship an agreed volume of ceramic tile from Chihuahua, Mexico to Garland, Texas, via the railroad. Interceramic filed a counterclaim alleging that the Railroad failed to timely deliver the tiles that had been shipped according to the contract. The trial court found in favor of the Railroad on all issues and rendered judgment for the Railroad for $564,052.32 in damages, plus interest and attorney’s fees. The court made extensive findings of fact and conclusions of law in support of its judgment.

The Railroad and Interceramic entered into a one-year contract on August 18, 1995, in which the Railroad agreed to transport tiles to and from Interceramic’s Chihuahua plants to warehouses in Garland. The Railroad also agreed to move the tiles by truck, called drayage, from the train station to Interceramic’s warehouses. The Railroad agreed to provide service at least three times per week. Interceramic guaranteed that it would ship a minimum of ten loads per train from Chihuahua to Garland, or thirty loads or loaded vans per week. Invoicing and payment was to be made twice a month.

It is undisputed that Interceramic never met the volume requirements of the con *924 tract. During the entire contract term, it shipped only 234 vans by rail. Before the end of the one-year term of the contract, at the end of June 1996, the Railroad stopped service. The trial court found that the Railroad stopped service in order to mitigate its losses after Intereeramic failed to ship the required number of loads, and the court reduced damages accordingly.

On appeal, Intereeramic contends that the judgment is erroneous because its failure to ship the required quantities was excused by a prior breach by the Railroad; the Railroad waived its right to enforce the volume provision of the contract by waiting until the expiration of the contract to seek enforcement; the calculation of damages is defective; and the trial court abused its discretion by admitting expert witness testimony that was provided by supplementation only eight days before trial.

Intereeramic contends that the Railroad breached the contract because the contract required the Railroad to provide timely drayage for the tiles from the railroad station to the Intereeramic warehouses. Intereeramic contends that this failure to provide timely drayage was the first breach of the contract, and that it excused its own failure to ship the agreed loads of tiles.

Whether a party has breached a contract is a question of law, not a question of fact. Lafarge Corp. v. Wolff, Inc., 977 S.W.2d 181, 186 (Tex.App.—Austin 1998, pet. denied); Garza v. Southland Corp., 836 S.W.2d 214, 219 (TexApp.—Houston [14th Dist.] 1992, no writ). In this case, the court also acted as the fact finder, so it was responsible for determining the disputed facts as well as applying the law to those facts.

When a party materially breaches a contract, the other party may treat the contract as ended and cease performance. Thus, a party who fails to perform his obligation may not thereafter enforce the remaining terms of the contract against the other party. Hernandez v. Gulf Group Lloyds, 875 S.W.2d 691, 692 (Tex. 1994); Graco Robotics, Inc. v. Oaklawn Bank, 914 S.W.2d 633, 641 (Tex.App.— Texarkana 1995, writ dism’d); Morgan v. Singley, 560 S.W.2d 746, 748 (Tex.Civ. App.—Texarkana 1977, no writ).

The first issue is whether the trial court erred by finding and concluding that the Railroad did not breach the contract.

Intereeramic argues that the contract requires the Railroad to provide timely drayage of the loads between the railroad station and its warehouses, and that the Railroad did not meet that requirement. Thus, it argues that the trial court erred by concluding that the Railroad did not breach the contract. The initial question is whether the contract requires such performance. It does not. The contract states only that the service will include “all drayage, ramping and de-ramping, etc.” It does not give any specifications whatsoever for the drayage. There is no requirement that transport be completed within any particular length of time.

Where a contract calls for certain performance, but expresses no time for that performance, the law implies that a reasonable time was contemplated. Intercer-amic, however, never raised the issue of reasonable time with the trial court, and it does not contend on appeal that the rule of reasonableness should be applied.

The trial court found that the contract does not specify a delivery schedule, that Intereeramic unilaterally implemented specific appointment times for the drayage after the contract was signed, and that Interceramic’s signatory to the contract, Dave Corey, misled the Railroad regarding those appointments. These findings, which are supported by evidence, are sufficient to support the trial court’s conclusion *925 that the Railroad did not breach the contract in its performance of the drayage.

Interceramic apparently contends that the signed contract is not the sole document comprising the contract, and that a letter it wrote to the Railroad a week after the contract was signed should be considered as a component of the contract, or at least should have been considered by the trial court in construing the contract. The trial court clearly considered only the signed contract, as is reflected by the language used in its findings of fact. There is no finding of fact addressing the letter, and there is no complaint on appeal that the trial court erred by failing to consider the two documents as a single contractual entity. Accordingly, we will restrict our review to Interceramic’s contention on appeal, i.e., that the letter provides evidence from which we should conclude that the court erroneously interpreted the terms of the contract.

Interceramic bears a difficult burden. In a bench trial in which the sufficiency of the evidence is challenged, the trial court’s findings are reviewed for legal and factual sufficiency using the same standards as used in reviewing jury findings. Okon v. Levy, 612 S.W.2d 938, 941 (Tex.Civ.App.—Dallas 1981, writ ref'd n.r.e.). The trial court has the right to believe or disbelieve evidence as it sees fit and to resolve conflicts in the evidence.

The only portion of the contract itself that is relevant to this issue is quoted above, and it contains no specifics about the time or manner of the drayage. The letter on which Interceramic relies contains language first confirming the volume of freight and then stating:

However, if your drayage company is not able to pickup [sic] these orders, then we will have to move these orders by normal truck service so we can meet our delivery dates. In addition, it is very important that the Dallas/Ft.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wallace v. Perry (In Re Perry)
423 B.R. 215 (S.D. Texas, 2010)
South Plains Switching, Ltd. v. BNSF Railway Co.
255 S.W.3d 690 (Court of Appeals of Texas, 2008)
Nikisha Shonte Neal v. State
Court of Appeals of Texas, 2005
Willis v. Donnelly
118 S.W.3d 10 (Court of Appeals of Texas, 2003)
Teitel v. University of Houston Board of Regents
285 F. Supp. 2d 865 (S.D. Texas, 2002)
Taub v. Houston Pipeline Co.
75 S.W.3d 606 (Court of Appeals of Texas, 2002)
Two Thirty Nine Joint Venture v. Joe
60 S.W.3d 896 (Court of Appeals of Texas, 2001)
Vingcard A.S. v. Merrimac Hospitality Systems, Inc.
59 S.W.3d 847 (Court of Appeals of Texas, 2001)
Abraxas Petroleum Corp. v. Hornburg
20 S.W.3d 741 (Court of Appeals of Texas, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
999 S.W.2d 920, 1999 WL 722643, Counsel Stack Legal Research, https://law.counselstack.com/opinion/interceramic-inc-v-south-orient-rr-co-ltd-texapp-1999.