Insight Investments v. North American Specialty Insurance Company

Court of Appeals for the Tenth Circuit·Decided September 25, 2025·No. 24-6068·Unpublished

Opinion

FILED

United States Court of Appeals UNITED STATES COURT OF APPEALS Tenth Circuit

FOR THE TENTH CIRCUIT September 25, 2025

Christopher M. Wolpert

Clerk of Court

INSIGHT INVESTMENTS, LLC,

Plaintiff - Appellant/Cross-

Appellee,

v. Nos. 24-6068 & 24-6076 (D.C. No. 5:20-CV-00788-G)

NORTH AMERICAN SPECIALTY (W.D. Okla.) INSURANCE COMPANY,

Defendant Third-Party Plaintiff -

Appellee/Cross-Appellant,

and SASHA M. BELL,

Third-Party Defendant. 1

ORDER AND JUDGMENT *

Before HARTZ, TYMKOVICH, and EID, Circuit Judges.

A subcontractor’s labor-and-material payment bond guarantees that all the subcontractor’s bills for labor and materials will be paid by a surety if it defaults. In this case, a subcontractor, Icon Construction, Inc. (Sub), prepared a modular building

1 Third-Party Defendant Sasha M. Bell is not a party to this appeal.

*

This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. It may be cited, however, for its persuasive value consistent with Fed. R. App. P. 32.1 and 10th Cir. R. 32.1.

to be used on an Air Force base during renovation of the permanent clinic. It procured a labor-and-material payment bond from North American Specialty Insurance Company (Surety).

While the construction project was underway, Sub entered into a contract with Insight Investments, LLC (Insight) stating that Sub sold the modular building to Insight and Insight then leased it back to Sub. Undisputed facts, however, establish that the true nature of the transaction was that Insight simply financed Sub’s performance under its subcontract with the prime contractor. When Sub failed to pay what it owed Insight, Insight made a claim on the bond from Surety. Surety refused to pay, and Insight filed this lawsuit.

There are three issues on appeal: (1) Does the payment bond protect Insight if it was merely financing Sub? (2) For purposes of determining bond coverage, does the parol-evidence rule require the court to adopt the description of the relationship between Sub and Insight in their separate contract, or may the court consider extrinsic evidence? And (3) if the court denies a claim under the bond, is Surety entitled to recover prevailing-party attorney fees under the applicable Oklahoma statute?

On the first question, we hold that Insight is not covered under the bond because it did not provide labor or material, but only money. Next, we hold that the parol-evidence rule governs only the parties to a contract, so Surety was allowed to introduce evidence regarding Sub’s actual relationship with Insight. Finally, we hold that Surety is entitled to prevailing-party attorney fees under Okla. Stat. Ann. tit. 12,

§ 936 (2025), because the statute requires only that there be an action to recover for unpaid labor or services, not that the action be valid.

I. BACKGROUND A. The Construction Project In September 2016 United Excel Corporation (Prime) entered into a contract with the U.S. Army Corps of Engineers, agreeing to serve as the prime contractor on a project to renovate a medical clinic on Vance Air Force Base in Oklahoma. In April 2017 Prime subcontracted with Sub, whose task was to design, manufacture, and install a modular building (the Module) to serve as a temporary medical clinic while renovation of the existing clinic was underway. Prime was to pay Sub $807,766, including 20 monthly lease payments of $19,000 after installation. If the Module was used beyond the 20-month term, the monthly rate would decrease to $17,250.

Sub began manufacturing the Module at its own facility in late August 2017.

The following month, Sub purchased from Surety a “Subcontract Labor and Material Payment Bond” (the Bond). Joint App. at 69. The Bond provided “[t]hat if [Sub] shall promptly make payment to all claimants as hereinafter defined, for all labor and material used or reasonably required for use in the performance of the subcontract, then this obligation shall be void; otherwise it shall remain in full force and effect[.]” Id. In other words, if Sub promptly paid all claimants, there would be nothing for the surety to cover.

The Bond defines a claimant as:

[O]ne having a direct contract with [Sub] for labor, material, or both, used or reasonably required for use in the performance of the contract, labor and material being construed to include that part of water, gas, power, light, heat, oil, gasoline, telephone service, or rental of equipment directly applicable to the subcontract.

Id. The Bond permits any claimant to sue if it “has not been paid in full before the expiration of a period of ninety (90) days after the date on which the last of [its] work or labor was done or performed, or materials were furnished . . . .” Id.

From late August through December 2017, Sub manufactured the Module, delivered it to the site, and substantially completed its installation. Prime was then to begin paying Sub monthly rent.

B. The Sub-Insight Transaction In May 2016, more than a year before Sub began working on the project, Insight salesman Reid Lukes sent an email advertising Insight’s “financing programs” for modular buildings. Id. at 460. In a follow-up email, he said Insight was “just a finance company” that “funds all of [its] modular partners [presumably, those making modular buildings who are financed by Insight] 100% of the project without recourse.” Id. at 458 In October 2016 Sub contacted Insight to discuss financing for the Module.

Ten months later, Lukes requested more details, sending an email asking, “How much were you looking for us to fund?” Id. at 466. Eric Salomone, Sub’s Vice President, responded, “We were looking for you to fund $511,433 for the building.” Id. Lukes replied that Insight typically invested a lower percentage of equity, and proposed funding $466,501 instead.

These negotiations culminated in late December 2017, when Salomone sent Lukes an email with the final terms:

[Sub] accepts the revised up-front funding of the building at $410,000.00 (from the original $466,501.00). As discussed on the phone, we would like to receive the funding as early as possible. Also, should the lease not get extended beyond the initial 20 month term long enough for [Sub] to recover the remaining $56,501.00 from the original building price via a 50% split of the extension lease payments, [Sub] would share in the future sale or lease of the building until we recover at least said remaining $56,501.00.

Id. at 478 (emphasis added). After several emails concerning documentation, Lukes replied, “Once we receive our return on equity, Insight will share all future rents and/or sale of the building 50/50.” Id. at 477.

This transaction was memorialized in three documents: a Master Lease Agreement, an amendment to that agreement providing that Sub would direct Prime to send its rent payments directly to Insight’s bank, and a Remarketing Agreement (collectively the Sub-Insight Agreement). The Sub-Insight Agreement terms the parties’ arrangement as a “lease,” characterizing the transaction as a purchase by Insight of the completed Module, followed by a lease back to Sub. Id. at 671. In sum, Insight provided cash funding in exchange for monthly rent payments and an ownership interest in the Module. Insight stipulated that it “did not manufacture, deliver, or install” the building. Id. at 368 (joint stipulation). Surety was not made aware of this agreement.

In late December 2017, Sub sent Insight an invoice for $410,000. Although Insight advanced the money, Sub did not repay Insight, apparently because Prime did not pay Sub.

In July 2018 Insight submitted a claim against Surety under the Bond. Surety denied Insight’s claim, stating that Insight was not a proper claimant because it had not provided labor or material to Sub—rather, it had “provide[d] funding.” Id. at 95.

C. Court Proceedings

Free access — add to your briefcase to read the full text and ask questions with AI

Insight Investments v. North American Specialty Insurance Company, (10th Cir. 2025).

Insight Investments v. North American Specialty Insurance Company (Insight Investments v. North American Specialty Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Combs v. Shelter Mutual Insurance
551 F.3d 991 (Tenth Circuit, 2008)
Boren v. Thompson & Associates
2000 OK 3 (Supreme Court of Oklahoma, 2000)
Barbero v. Equitable General Insurance Co.
1980 OK 23 (Supreme Court of Oklahoma, 1980)
Burrows Construction Co. v. Independent School District No. 2
1985 OK 57 (Supreme Court of Oklahoma, 1985)
ABC Coating Co. v. J. Harris & Sons Ltd.
1987 OK 125 (Supreme Court of Oklahoma, 1987)
Russell v. Flanagan
1975 OK 173 (Supreme Court of Oklahoma, 1975)
Kay v. Venezuelan Sun Oil Co.
1991 OK 16 (Supreme Court of Oklahoma, 1991)
Maxxum Construction, Inc. v. First Commercial Bank
2011 OK CIV APP 84 (Court of Civil Appeals of Oklahoma, 2011)
First National Bank in Durant v. Honey Creek Entertainment Corp.
2002 OK 11 (Supreme Court of Oklahoma, 2002)
Colony Insurance Co. v. Burke
698 F.3d 1222 (Tenth Circuit, 2012)
First National Bank of Chisholm v. O'Neil
223 N.W. 298 (Supreme Court of Minnesota, 1929)
Linde Air Products Co. v. American Surety Co.
152 So. 292 (Mississippi Supreme Court, 1934)
Rockwell Bros. & Co. v. Keatley
1915 OK 830 (Supreme Court of Oklahoma, 1915)
First Nat. Bank of Eufaula v. Southern Surety Co.
1916 OK 986 (Supreme Court of Oklahoma, 1916)
In Re Assessment of Alleged Omitted Property of Kennedy
1936 OK 383 (Supreme Court of Oklahoma, 1936)
Whale v. Rice
1935 OK 838 (Supreme Court of Oklahoma, 1935)
Harper v. Tri-State Motors, Inc.
58 P.2d 18 (Utah Supreme Court, 1936)