Industrial General Corp. v. Sequoia Pacific Systems Corp.

44 F.3d 40, 1995 U.S. App. LEXIS 397, 1995 WL 3851
CourtCourt of Appeals for the First Circuit
DecidedJanuary 11, 1995
Docket94-1617
StatusPublished
Cited by55 cases

This text of 44 F.3d 40 (Industrial General Corp. v. Sequoia Pacific Systems Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial General Corp. v. Sequoia Pacific Systems Corp., 44 F.3d 40, 1995 U.S. App. LEXIS 397, 1995 WL 3851 (1st Cir. 1995).

Opinion

STAHL, Circuit Judge.

Industrial General Corporation’s (“IGC”) subsidiary, Plastek Corporation (“Plastek”), supplied molded plastic parts to Moog Electronics (“Moog”) for use in electronic voting machines Moog was assembling for Sequoia Pacific Systems Corporation (“Sequoia”). After Moog faded to pay Plastek $80,100 for supplied parts, Plastek sued Sequoia alleging breach of contract and violation of Mass. Gen.L. eh. 93A, § 11. Following a seven-day trial, the jury returned a verdict for Sequoia on the breach of contract claim. In an advisory verdict on the 93A claim, it found that Sequoia had acted “unfairly.” The district court eventually agreed with the advisory finding and further held that Sequoia had breached a fiduciary duty it owed to Plastek and entered judgment for Plastek on the 93A claim. Because we find that no fiduciary relationship existed between Plastek and Sequoia, we reverse the court’s chapter 93A judgment. 1

I.

FACTUAL BACKGROUND AND PRIOR PROCEEDINGS

In 1984, Sequoia began to design and develop computerized electronic voting machines which it hoped to sell to local election boards. During that same year, Sequoia Associates, a partnership and one of Sequoia’s stockholders, had explored the possibility of acquiring IGC’s predecessor-in-interest, Wal-co National, Inc. (“Walco”). Though the Sequoia Associates-Walco deal ultimately failed, because of the acquisition negotiations, Sequoia Associates had become familiar with Walco’s Plastek division, which produced molded plastic parts. Recognizing that the voting machines would use plastic parts, Sequoia Associates advised Sequoia of Plastek’s molding abilities. The introduction was fortuitous, as Sequoia was under time constraints to complete the project and had been unable to locate a suitable supplier for the needed plastic parts.

*42 Commencing in mid-1985, Sequoia and Plastek entered into a series of contracts providing that Plastek would develop prototype molds and, later, produce prototype parts for use in the voting machines project. Meanwhile, Sequoia and Moog entered into agreements for Moog to assemble a number of prototype voting machines. In connection with these agreements, Sequoia instructed Plastek to ship some prototype parts to Moog. Sequoia paid Plastek in full for the prototype molds and prototype parts and these transactions are not in dispute. Later, Plastek produced production molds, for which Sequoia also paid in full.

In the latter part of 1985, Sequoia decided to contract with a manufacturer to assemble the Sequoia-designed voting machines. Sequoia would then purchase the machines on a “turn-key” basis, 2 thus relieving it of both the burden of carrying the inventory of parts required for assembly and the burden of assembly itself. Sequoia awarded the initial manufacturing contract to Momentum Technologies, Inc. (“Momentum”). Moog sued Sequoia, claiming that one of their earlier prototype-assembly contracts contained a promise to award Moog a contract for an actual production run of at least 5,000 machines. In settlement, Sequoia agreed to award Moog a contract to manufacture 500 machines with Momentum manufacturing the balance of Sequoia’s requirements.

Moog’s finances during this period were shaky, though the extent of Sequoia’s knowledge of Moog’s condition was disputed at trial. The district court credited the testimony of Edmund Lonergan, Sequoia’s former technical director, who at trial testified by deposition that he developed a “gut feeling” that Moog was not “financially strong enough to manufacture all the units per our [settlement] agreement with them.” Lonergan alerted his superiors at Sequoia. James Lar-kin, Sequoia’s chief financial officer, testified that he knew Moog had a cash-flow problem and that he agreed to a billing arrangement designed to improve Moog’s cash situation.

Sequoia informed Plastek that the machines would be assembled by contractors and that Plastek’s agreement for production parts were to be made directly with those assemblers. Complying with this directive, both Moog and Momentum contracted directly with Plastek and other suppliers for the voting machine parts.

In June and July 1986, Moog issued to Plastek purchase orders for production parts. 3 Plastek sent acknowledgement of the orders to Moog. Plastek manufactured the parts and shipped them to Moog on a net 30 day basis. Plastek invoiced Moog directly and the invoices stated, “Sold to Moog.” The shipments were carried on Plastek’s books as Moog account receivables. Plastek never conducted a credit check on Moog, nor did any Plastek official inquire of Sequoia about Moog’s financial situation or creditworthiness.

After the Moog-Sequoia settlement was in place, things began to deteriorate at Moog. Moog quickly fell behind on its production schedule. Eventually, Sequoia determined that Moog would be unable to timely perform its contract and, in September 1986, requested Moog to transfer all work-in-progress to Momentum. Sequoia paid Moog in full for its work-in-progress, including the amount Moog owed Plastek for the production parts.

Moog, however, never paid Plastek. Plas-tek sought to collect its unpaid balance from Moog with no success. - In November 1986, well after the work-in-progress transfer had taken place, Plastek alerted Sequoia of its problems with Moog. By early 1987, Moog was insolvent. In February 1987, Plastek notified Sequoia that it was holding Sequoia responsible for the unpaid Moog balance. Five months had passed since Plastek had shipped and invoiced its parts to Moog.

In 1989, Plastek, through its parent, IGC, brought the present action in Massachusetts Superior Court seeking recovery for breach of contract and for violation of Mass.Gen.L. eh. 93A, § 11. Sequoia removed the case to *43 federal district court with jurisdiction grounded in diversity of citizenship. After discovery, the district court denied Sequoia’s motion for summary judgment. The district court held a seven-day jury trial in February 1994. The district court instructed the jury to answer questions on a special verdict.

The jury returned a verdict in Sequoia’s favor on the breach of contract claim. With regard to the chapter 93A claim, the jury found that Sequoia acted “unfairly” in “failing to disclose what it knew about Moog’s financial stability.” However, the jury did not find that Sequoia’s acts were deceptive or that its actions were knowing and willful. The district court, essentially agreeing with the jury, found that Plastek was in a position of “trust and dependence” relative to Sequoia and that Sequoia had acted “unfairly in failing to disclose the fact that Moog was an unreliable customer.” Industrial Gen. Corp. v. Sequoia Pac. Sys. Corp., 849 F.Supp. 820, 824 (D.Mass.1994). The district court entered judgment in favor of IGC for $80,100.69 plus costs. This appeal followed.

II.

DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SEC v. Sanchez Diaz Monge
88 F.4th 81 (First Circuit, 2023)
Katz v. Belveron Real Estate Partners
28 F.4th 300 (First Circuit, 2022)
Pearson v. Hodgson
D. Massachusetts, 2018
Pearson v. Hodgson
363 F. Supp. 3d 197 (District of Columbia, 2018)
Becker v. Independence Bank
305 F. Supp. 3d 351 (D. Rhode Island, 2018)
NexTT Solutions, LLC v. XOS Technologies, Inc.
113 F. Supp. 3d 450 (D. Massachusetts, 2015)
Bamberg v. Goldman, Sachs & Co.
771 F.3d 37 (First Circuit, 2014)
Scott v. Mage, LLC
32 Mass. L. Rptr. 61 (Massachusetts Superior Court, 2014)
Smith v. Dorchester Real Estate, Inc.
732 F.3d 51 (First Circuit, 2013)
Patrocinio v. A.M.R. Realty, LLC
28 Mass. L. Rptr. 211 (Massachusetts Superior Court, 2011)
Gemini Investors, Inc. v. Ches-Mont Disposal, LLC
629 F. Supp. 2d 163 (D. Massachusetts, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
44 F.3d 40, 1995 U.S. App. LEXIS 397, 1995 WL 3851, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-general-corp-v-sequoia-pacific-systems-corp-ca1-1995.