Industrial Development Board v. Fuqua Industries, Inc.

523 F.2d 1226
CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 24, 1975
DocketNo. 74-2336
StatusPublished
Cited by10 cases

This text of 523 F.2d 1226 (Industrial Development Board v. Fuqua Industries, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial Development Board v. Fuqua Industries, Inc., 523 F.2d 1226 (5th Cir. 1975).

Opinion

WISDOM, Circuit Judge:

In this diversity action the district court directed verdicts against two plaintiffs, The Industrial Development Boards of the Town of Section, Alabama, and the City of Fort Payne, Alabama (Boards), on four counts of a multi-count complaint and directed a verdict against one plaintiff, Phillips-Van Heusen Corporation (Van Heusen), on two counts of its complaint. One of Van Heusen’s counts was submitted to the jury, which found for the defendant, Fuqua Industries, Inc. (Fuqua). We affirm the directed verdicts entered against the Boards, but we remand for a new trial most of Van Heusen’s claims.

THE FACTS

Vareo Steel, Inc. (Vareo) agreed to construct for each Board a prefabricated factory building on land owned by the Boards. Each Board had leased the premises to Van Heusen at a rental calculated to liquidate the Board’s debt on bond issues that raised the funds necessary for the construction projects. The alleged failure of Vareo to construct these buildings in accordance with the contract plans and specifications generated the plaintiffs’ suits.

In the late 1950’s Van Heusen decided to change from the bar-joist structures it had been using for shirt factories to preengineered factories. Van Heusen chose Vareo to construct the new type of building. Van Heusen was satisfied with the work on this plant and engaged Vareo to build two others of the same type. The Van Heusen production schedule was then growing at a pace requiring a new plant to be constructed every year. As a consequence, in 1964 Van Heusen began negotiations with Vareo for the construction of the two factories involved in this case. On March 9, 1965, Van Heusen and the Vareo group (Vareo and its subcontractors) reached a tentative agreement on the price of the two factories.1

The Boards had already signed lease agreements with Van Heusen. On March 29, 1965, the Boards and Vareo entered into a contract for the construction of the preengineered buildings. The contract price was $450,386 for the Fort Payne structure and $248,889 for the Section structure. Fuqua, who became the successor to Varco’s contractual obligations through various mergers, admits in its brief, and there was testimony supporting this admission, that the Boards “did not have a nickel in the buildings” and that “Van Heusen’s only reason for using the [Bjoards was the cheaper borrowing costs”. When the construction of [1230]*1230the Fort Payne building was more than one-half completed, Golden, an executive of Van Heusen, noticed that steel purlins2 in the structure appeared to be twisted. Concerned for the safety of the building, Golden and Howard, Chairman of the Fort Payne Board, sought assurances from Vareo and its subcontractors that the steel was satisfactory for the purposes for which it was intended. Vareo officials then wrote two letters (“certifications”, Van Heusen characterizes them) assuring Van Heusen that the steel work in both factories was in good condition in all respects. Toward the end of 1965 the buildings were completed and accepted by the respective Boards, Van Heusen, and Van Heusen’s architect, Holman.

In 1970, Van Heusen employed a new architect, Morgan, to inspect the two factories. Because of the twisted condition of the purlins and various other alleged defects, Morgan requested Vareo to furnish the calculations of the engineers showing the load bearing capacity of the steel structures in the two factories. Morgan’s dissatisfaction with these calculations caused Van Heusen to engage other contractors to repair the buildings at a total cost of $513,191.86. To recover this sum, Van Heusen and the Boards sued Fuqua, two subcontractors (Rock Steel Building Co. & DeWitt Newton,- Inc.), and the surety on Varco’s contract (St. Paul Fire & Marine Insurance Company).

Neither of the Boards had expended any money for the repair of the factories. Indeed, Van Heusen signed an agreement with each of the Boards in which Van Heusen agreed to make the repairs it felt were necessary, and to indemnify the Boards for any costs resulting from the repairs or any legal action Van Heusen intended to prosecute against the contracting parties.

In this appeal we concern ourselves with four counts. (1) Count II was based directly on the March 29, 1965, contract. (2) Count III was based on the surety’s contract. (3) Count IV was based on the two letters (“certifications”) that Van Heusen received from Vareo. This count rests on the theory that these certifications constitute warranties, which relieve Van Heusen’s original architect of the responsibility for designing the steel. (4) Count V sounds in fraud and deceit. The plaintiff contends that at the time Vareo entered into the contract with the Boards it had no intention of complying with the contract specifications.

The directed verdict against the Boards on Counts II and III were entered because the Boards had failed to adduce any evidence showing that they had been damaged by the alleged failure of the defendants to complete the contract according to specifications.

The directed verdict against the Boards and Van Heusen on Count IV was entered apparently because the district court felt that there was no evidence that the certifications had been given for any consideration and because it did not appear to the district court that the certifications gave the plaintiffs any rights which they did not have under the main contract. The directed verdicts against the Boards and Van Heusen on Count V were entered because the district court found no evidence of any fraudulent intention on the part of the defendants and because the claims had expired under the statute of limitations.

The only issue that went to the jury with which this appeal is concerned3 was whether Van Heusen, as a third-party beneficiary to the March 29 contract between the Boards and Vareo, had suffered any damages as a result of the failure of the defendants to comply with [1231]*1231contract provisions. On this appeal, Van Heusen contends that the trial court erred in requiring, as a condition to recovery, that the jury find that Van Heusen was a third-party beneficiary under the March 29 contract. Van Heusen argues that, by virtue of its agreements indemnifying the Boards for any expenses related to this matter and for its payment of the full cost of repair, it was subrogated to the Board’s position with respect to the defendants. In the alternative, Van Heusen contends that it has standing to sue on the ground that it is the assignee of the Board’s causes of action against the defendants, and that simply as the lessee of the factories it has standing to sue. The appellants further contend that even if no damages were proved by the Boards, their right to proceed for nominal damages was erroneously limited by the directed verdicts against them on Counts II and III. Van Heusen asserts that its position was jeopardized when the Boards were removed from the ease. The Boards and Van Heusen contend that the directed verdicts on Count IV were erroneous, because consideration is unnecessary under the relevant law and because the certificates indicate that Vareo was assuming or had assumed responsibilities with respect to the design of the factories that, according to the original contract, were to be fulfilled by Van Heusen’s architect, Holman. Finally, the Boards and Van Heusen argue that there was sufficient evidence of fraudulent intention and of concealment of the fraud to send Count V to the jury.

THE BOARDS

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
523 F.2d 1226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-development-board-v-fuqua-industries-inc-ca5-1975.