Indiana Department of Natural Resources v. Peabody Coal Co.

740 N.E.2d 129, 149 Oil & Gas Rep. 231, 2000 Ind. App. LEXIS 1894, 2000 WL 1716256
CourtIndiana Court of Appeals
DecidedNovember 16, 2000
Docket77A04-9909-CV-429
StatusPublished
Cited by5 cases

This text of 740 N.E.2d 129 (Indiana Department of Natural Resources v. Peabody Coal Co.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Indiana Department of Natural Resources v. Peabody Coal Co., 740 N.E.2d 129, 149 Oil & Gas Rep. 231, 2000 Ind. App. LEXIS 1894, 2000 WL 1716256 (Ind. Ct. App. 2000).

Opinion

OPINION

SHARPNACK, Chief Judge

The Indiana Department of Natural Resources ("DNR") appeals the judgment of the trial court affirming a decision of the administrative law judge ("ALJ") in favor of Peabody Coal Company ("Peabody"). The DNR raises four issues, which we consolidate and restate as:

(1) whether the trial court erred in affirming the ALJ's decision that the DNR had applied an incorrect legal standard in requiring Peabody to replace more than topsoil for land reclamation; and
(2) whether the trial court erred in affirming the ALJ's decision that the DNR made inadequate findingé to support its determination that Peabody was required to remove eighteen inches of soil, including both topsoil and subsoil, for land reclaimation.

We affirm.

The relevant facts follow. The DNR is a state administrative agency with responsibility for the administration and enforcement of the Indiana Surface Mining Control and Reclamation Act ("SMCRA"), 1 a program for the regulation of surface coal mining. Peabody is a corporation that operates surface coal mining operations under SMCRA permits issued by the DNR. This case arises out of the refusal of the DNR to allow a revision to four of Peabody's surface mining permits so as to allow Peabody to remove and store for replacement eight to twelve inches of topsoil rather than eighteen inches of combined topsoil and subsoil as the permit required.

In 1990, it was the DNR's policy to require surface land miners to replace and redistribute a minimum of eighteen inches of soil, which could include both topsoil and subsoil, after mining on all non-prime farmland areas used as cropland. On October 12, 1990, Peabody filed a request for administrative review, under $10 Ind.Administrative Code 0.6-1-15, seeking to set aside the DNR's policy. 2 The ALJ determined that the most reasonable interpretation of 310 Ind.Administrative Code 12-5-12.1, the section of the SMCRA that bears most directly on topsoil and subsoil replacement for surface coal mining activities, was that subsoil is not generally required to be salvaged and replaced. However, under subsection (£), which acts as an exeeption to the general principle, the DNR could require subsoil to be salvaged and replaced only if the director found subsoil replacement to be necessary in a particular case. The ALJ concluded that without having formally promulgated a rule in accordance with Ind.Code § 4-22-2, the DNR could not uniformly require all miners to replace a minimum of eighteen inches of soil after mining regardless of whether eighteen inches of topsoil existed before mining.

While that case was pending review by the trial court, the DNR and Peabody agreed as to the permits at issue here to a condition requiring a soil replacement *132 depth of eighteen inches, subject to judicial review by the trial court. Pursuant to the agreement, Peabody thereafter submitted permit revisions incorporating the eighteen inch minimum soil replacement depth with a reservation that if the eighteen inch policy was determined to be invalid by the trial court, it would submit another revision to seek removal of the language.

When the trial court affirmed the decision of the ALJ that the DNR could not impose a general minimum soil replacement depth of eighteen inches for all cropland without having formally promulgated such a rule, 3 Peabody sought a revision to the permits at issue 'here to reduce the amount of soil it had to replace after mining. In essence, Peabody sought to remove and replace only the topsoil, which varied from eight to twelve inches, not the subsoil. After reviewing Peabody's revision applications, the DNR denied the applications in four separate, but virtually identical letters. In each of the four letters, the DNR wrote:

The applicant proposes to restore an average of 8 to 12 inches of topsoil on graded cast overburden for all non-prime farmland areas. Based upon the information available to the Director, the Director finds in this specific case, a soil replacement of 8 to 12 inches is inadequate to comply with the land capability restoration and revegetation requirements of 310 IAC 12-5. Therefore, the Director has made a special finding that it is appropriate with respect to this particular case to require a portion of the subsoil be removed and segregated, and redistributed in accordance with 310 IAC 12-5-12.1 since he finds such subsoil layers are necessary to comply with the land capability restoration and re-vegetation requirements of 310 IAC 12-5.

Record, pp. 903, 905, 913, 917.

Peabody petitioned for administrative review of the DNR's denial of its requests to reduce soil replacement depths. On April 14, 1998, the ALJ made the following findings, in pertinent part:

(15) As specified in IC 14-84-10-2(b)(8), one of the duties of an operator is to '[rlestore the land affected to a condition capable of supporting the uses that the land was capable of supporting before mining or higher or better uses."
(16) The clear statutory purpose of Indiana SMCRA is to require an operator to reclaim land to as 'good or better shape as it was prior to mining." JH & L Coal Company, d/b/a Miller Mining v. Department of Natural Resources, 7 Caddnar 28 (1994). To that end, unless a site is restored to the same use as existed prior to mining, the site must be restored to a higher and better use. A corollary is that the approved postmin-ing land use for a particular site is either the same as, or better than, the premining land use.
(17) The 'special finding' made by the DNR for the subject permits requires a two-prong standard be met in order for an operator not to provide 18 inches as a standard soil replacement. Reference is made both to 'land capability restoration' and to 'revegetation' requirements. (18) ... compliance with the revegetation requirements for the approved post-mining land use is a cornerstone of Indiana SMCRA. Since the approved postmining land use is either the same as or better than the premining land use, compliance with the revegetation requirements assures an operator must reclaim the land to as good as or a better condition than existed prior to mining.
(19) In the Peabody cases, the approved postmining land use is cropland. Re-vegetation requirements must be measured within the context of cropland.... (20) No general 'land capability' standard is set forth in 310 IAC 12-5-12.1(F), however, apart from the revegetation *133 requirements in 310 IAC 12-5-59, 61, 62, 63, and 64.1. Soil replacement, land use, and revegetation are inextricable. Attainment of the approved postmining land use, as demonstrated by compliance with the revegetation requirements for that land use, insure that the land will be restored to a condition capable of supporting that use.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Musgrave v. SQUAW CREEK COAL CO.
964 N.E.2d 891 (Indiana Court of Appeals, 2012)
State v. Molnar
803 N.E.2d 261 (Indiana Court of Appeals, 2004)
Indiana Bell Telephone Co. v. Time Warner Communications of Indiana, L.P.
2 A.L.R. Fed. 2d 617 (Indiana Court of Appeals, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
740 N.E.2d 129, 149 Oil & Gas Rep. 231, 2000 Ind. App. LEXIS 1894, 2000 WL 1716256, Counsel Stack Legal Research, https://law.counselstack.com/opinion/indiana-department-of-natural-resources-v-peabody-coal-co-indctapp-2000.