Peabody Coal Co. v. Indiana Department of Natural Resources

629 N.E.2d 925, 1994 Ind. App. LEXIS 190, 1994 WL 59337
CourtIndiana Court of Appeals
DecidedMarch 2, 1994
Docket77A01-9307-CV-233
StatusPublished
Cited by19 cases

This text of 629 N.E.2d 925 (Peabody Coal Co. v. Indiana Department of Natural Resources) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peabody Coal Co. v. Indiana Department of Natural Resources, 629 N.E.2d 925, 1994 Ind. App. LEXIS 190, 1994 WL 59337 (Ind. Ct. App. 1994).

Opinion

ROBERTSON, Judge.

The Peabody Coal Company appeals the trial court’s decision to grant relief on the petition of the Indiana Department of Natural Resources [DNR] for judicial review of the decision of the Administrative Law Judge [ALJ] of the Natural Resources Commission [NRC] to vacate the DNR’s Notice of Violation [NOV] against Peabody. The DNR had issued the NOV against Peabody because an inspection revealed that its Hawthorn strip coal mine was in violation of certain regulations regarding the drainage of surface water off the mining site. Peabody raises two issues, which we restate as three, none of which constitute reversible error.

FACTS

The pertinent facts are not disputed: the case was submitted to the ALJ below on stipulated facts. The parties filed cross-motions for summary judgment. On July 10, 1989, a DNR mine inspector inspected Peabody’s Hawthorn Mine in Sullivan County, Indiana, which is operated under a surface coal mining and reclamation operation permit issued by the DNR under the Indiana Surface Mining Act [ISMCRA]. The inspection report reads in pertinent part as follows:

[As] was mentioned in last months [sic] inspection report, additional drainage control measures are needed ... to [e]nsure that this affected area drainage is passed thru [sic] a basin before discharging off the permit. Previously, this area was upgraded and drainage was controlled along this perimeter by the pit and by [bails of straw] at drainage focal points. Recent final grading along this perimeter however has redirected drainage so that drainage is now uncontrolled and will flow across the undisturbed area and off the permitted area without passing thru [sic] a basin. This perimeter is now characterized by an unvegetated and graded spoil slope approximately 500 ft. in length which slopes towards the wooded East perimeter. No diversion exist[s] along this perimeter and drainage can now flow Eastward off the permitted area into the ditch along side Highway 159. Evidence of off site drainage flow exist[s] along this wooded perimeter where a spoil derived sediment is deposited throughout this narrow (100 ft.) wooded strip up to and into the State Road ditch. [This NOV] is hereby issued for failure to pass all disturbed area drainage through a siltation structure before leaving the permit area and to retain all sediment within the disturbed area. The action required will call for this affected area drainage to be passed thru [sic] a sediment basin before discharging off the permit. The compliance time will be set for August 14, 1989 @ 8:00 AM.

The NOV cited Peabody with the violation of three regulations, 310 IAC 12-5-17(a)(l), 310 IAC 12 — 5—20(b)(3), and 310 IAC 12-3-4; and also charged a violation of the terms of the Hawthorn Mine operating permit. 1

*928 Peabody requested administrative review of the NOV. The parties agreed that the case could be resolved by summary judgment and stipulated the NOV itself and its accompanying inspection report into the record. The gravamen of Peabody’s motion was that, even assuming the facts in the inspection report were true, there was insufficient evidence to support a violation because no evidence had been presented that any regulation regarding effluent limitations had been violated, nor had any evidence been presented of a disturbance in the hydrologic balance. The gravamen of the DNR’s motion was that the earlier administrative rulings were erroneous and should be overruled. The ALJ, relying on the earlier administrative decisions, vacated the NOV. 2

DNR sought judicial review in the trial court. The trial court determined that the earlier administrative rulings were erroneous and that the ALJ’s decision in the present case was arbitrary, capricious, and contrary to law. This appeal ensued.

DECISION

This case is:

governed by the [Indiana Administrative Orders and Procedures Act, the AOPA], IND.CODE 4-21.5-3-1 et seq. The function of the trial court on the judicial review of administrative determinations is limited to a determination of whether the agency possessed jurisdiction over the matter and whether the order was made in accordance with the proper legal procedure, was based upon substantial evidence, and did not violate any constitutional, statutory, or legal principle. The scope of judicial review of administrative determinations is limited to the consideration of whether there was substantial evidence to support the finding or order of the administrative body and whether or not the action constitutes an abuse of discretion or is arbitrary and capricious as revealed by uncontradieted facts. The burden of proving an administrative action was an abuse of discretion or arbitrary and capricious falls upon the party attempting to upset the administrative order. The Court of Appeals will not substitute its opinion for that of an agency concerning matters within the scope of that agency’s discretion and authority.
Courts that review administrative determinations, at both the trial and appellate level, are prohibited from reweighing the evidence or judging the credibility of witnesses and must accept the facts as found by the administrative body. However, we need not accord the same degree of deference to an agency’s conclusion on a question of law. Law is the province of the judiciary. Our constitutional system empowers the courts to draw legal conclusions and accordingly the court in its function of judicial review of an administrative action may set aside an agency determination that is not in accordance with law.
An interpretation given a statute by an administrative agency charged with the duty of enforcing the statute is entitled to great weight; however, an agency’s interpretation of a statute which is incorrect is entitled to no weight. While evidence before an administrative agency will not be reweighed by the reviewing court, where the agency’s finding is contrary to law, it shall be reversed. If an agency misconstrues a statute, there is no reasonable basis for the agency’s ultimate action and the trial court is required to reverse the agency’s action as being arbitrary and capricious.

State Prison & State Employees’ Appeals Commission v. Van Ulzen (1991), Ind.App., 567 N.E.2d 1164, 1166-67 (Citations omitted), vacated on other grounds, 582 N.E.2d 789.

*929 I.

Whether the earlier administrative decisions bar the DNR from seeking judicial review of the present decision?

Peabody argues that the earlier administrative decisions, Dugger and Universal, invoke administrative res judicata (or perhaps a collateral estoppel) upon the DNR barring it from seeking judicial review of the present order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Indiana Department of Natural Resources v. Peabody Coal Co.
740 N.E.2d 129 (Indiana Court of Appeals, 2000)
Partlow v. Indiana Family & Social Services Administration
717 N.E.2d 1212 (Indiana Court of Appeals, 1999)
Indiana Payphone Ass'n v. Indiana Bell Telephone Co.
690 N.E.2d 1195 (Indiana Court of Appeals, 1997)
Indiana Department of Natural Resources v. United Minerals, Inc.
686 N.E.2d 851 (Indiana Court of Appeals, 1997)
Miller Brewing Co. v. Bartholemew County Beverage Co.
674 N.E.2d 193 (Indiana Court of Appeals, 1996)
Union Tank Car, Fleet Operations v. Commissioner of Labor
671 N.E.2d 885 (Indiana Court of Appeals, 1996)
Scott v. Scott
668 N.E.2d 691 (Indiana Court of Appeals, 1996)
Peabody Coal Co. v. Indiana Department of Natural Resources
664 N.E.2d 1171 (Indiana Supreme Court, 1996)
Ripley County Board of Zoning Appeals v. Rumpke of Indiana, Inc.
663 N.E.2d 198 (Indiana Court of Appeals, 1996)
Sullivan v. Day
661 N.E.2d 848 (Indiana Court of Appeals, 1996)
Natural Resources Commission v. Sugar Creek Mobile Estates
646 N.E.2d 61 (Indiana Court of Appeals, 1995)
Marion Teachers Ass'n v. Board of School Trustees
643 N.E.2d 370 (Indiana Court of Appeals, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
629 N.E.2d 925, 1994 Ind. App. LEXIS 190, 1994 WL 59337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peabody-coal-co-v-indiana-department-of-natural-resources-indctapp-1994.