Musgrave v. SQUAW CREEK COAL CO.

964 N.E.2d 891, 2012 WL 952224, 2012 Ind. App. LEXIS 118
CourtIndiana Court of Appeals
DecidedMarch 21, 2012
Docket49A05-1104-MI-164
StatusPublished
Cited by9 cases

This text of 964 N.E.2d 891 (Musgrave v. SQUAW CREEK COAL CO.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Musgrave v. SQUAW CREEK COAL CO., 964 N.E.2d 891, 2012 WL 952224, 2012 Ind. App. LEXIS 118 (Ind. Ct. App. 2012).

Opinion

*894 OPINION

BAILEY, Judge.

Case Summary

Bil Musgrave (“Musgrave”), a former coal miner, appeals the trial court’s order in favor of Squaw Creek Coal Company (“SCCC”) and the Indiana Department of Natural Resources (“DNR”) on SCCC’s petition for judicial review. SCCC petitioned the trial court for judicial review of an order issued by an Indiana Natural Resources Commission (“Commission”) Administrative Law Judge (“ALJ”) vacating the DNR’s decision to release certain portions of SCCC’s reclamation bond on its surface mining permit, and the trial court reversed. The DNR cross-appeals the trial court’s order. We affirm.

Issues

The parties raise several issues for our review, which we consolidate and restate as the following three issues:

I. Whether the trial court erred by denying Musgrave’s motion to dismiss SCCC’s petition for judicial review for lack of jurisdiction because SCCC did not serve summonses upon the Commission, the DNR, and the Indiana Attorney General, and did not pay the Marion County Superior Court filing fee;
II. Whether Musgrave is collaterally estopped from challenging the DNR’s decision to release the reclamation bond at issue; and
III. Whether the trial court erred by reversing the ALJ’s order and remanding for entry of judgment in favor of SCCC and the DNR.

Facts and Procedural History

SCCC was formed in 1960 as a joint venture between Alcoa, Inc. and Peabody Coal Company to mine the coal from Squaw Creek Mine. The extracted coal was used to power Alcoa’s nearby aluminum production facility on the banks of the Ohio River. Musgrave is a former miner who worked at Squaw Creek Mine.

The Squaw Creek Mine was mined in segments using a method called “surface mining.” (App.636) Using this method, SCCC drilled and blasted the overburden 1 that covered the coal, removed the blasted and drilled pieces with draglines and shovels, and dumped the pieces to the side, making “structureless pile[s] of debris” (App.692) that ranged from twenty-five to eighty feet tall. The exposed coal was then extracted and transported to a processing area using “haul roads” that were approximately fifty feet wide and inclined because the mine floor was well below the original grade of the land. (App.636)

Between 1965 and 1979, Alcoa used abandoned haul roads in Squaw Creek Mine to dispose of waste generated at its aluminum production facility, such as chromium sludge, spent pot lining, and tarry wastewater and tars from tunnel kilns. Because the haul roads were lower than the surrounding spoil, the waste was dumped at relatively low levels. Alcoa dumped its wastes in coordination with the Indiana Department of Health, the predecessor to the Indiana Department of Environmental Management (IDEM), and the wastes were covered with native overburden. It is estimated that Alcoa dumped its waste at twelve locations in Squaw Creek Mine, but some former miners assert that waste was dumped in several additional locations.

*895 On March 28, 1984, SCCC obtained Permit S-008 to mine a certain area of Squaw Creek Mine’s North Field. The entire area covered by Permit S-008 is approximately 4,467 acres, 1,273.01 acres of which were actually mined. Successful reclamation of the land that was mined was secured with a bond.

All active mining at Squaw Creek Mine ended in 1987, and on October 26, 2007, SCCC applied for release of certain portions of the bond on Permit S-008. The DNR held a public hearing on the bond release petition on January 3, 2008 at which Musgrave and other concerned citizens testified, as did an Alcoa safety representative. Much of the hearing focused on Alcoa’s disposal of the waste, whether all disposal locations had been discovered, and the various health and environmental impacts that the waste disposal has allegedly had on Squaw Creek Mine. On January 4, 2008, the DNR conducted a field investigation of the area covered by the bond and approved SCCC’s bond release application on February 1, 2008. In approving the bond release, the DNR concluded that “[t]he actual or theoretical threat of pollution from industrial wastes is not the type of impact anticipated by the bond release requirements.” (App.96)

On February 15, 2008, Musgrave sought administrative review of the DNR’s decision from the Commission. After the parties filed several motions and participated in multiple conferences, Musgrave moved for summary judgment on April 3, 2009. SCCC and the DNR filed responses and cross motions for summary judgment on June 25, 2009 and June 26, 2009, respectively.

On December 28, 2009, the ALJ issued an order affirming the DNR’s decision to release parts of the bond on certain portions of SCCC’s reclamation bond, but vacating the DNR’s decision to affirm the release on others. 2 Although the ALJ concluded that none of the identified sites where Alcoa dumped waste were located within the bonded area, the ALJ vacated the DNR’s decision as to certain portions of land because she concluded that “the migration of waste or constituents of that waste from the disposal sites throughout [Squaw Creek Mine] and possibly beyond is facilitated by the permeable overburden layer created throughout [Squaw Creek Mine] by SCCC’s mining operations.” App. 69. The ALJ based this conclusion on evidence that the mining spoil was behaving as an “unconfined aquifer” (App. 748) where lateral migration of water occurs.

SCCC sought judicial review of the ALJ’s order by filing its Verified Motion for Judicial Review in Marion County Superior Court on January 22, 2010. That same day, SCCC sent a copy of its petition for judicial review to Musgrave, the Indiana Attorney General, the DNR, and the Commission. It also sent a summons with the petition sent to Musgrave. SCCC did not send summonses to the Attorney General, the DNR, or the Commission.

On January 27, 2010, Attorney April Lashbrook of the Indiana Attorney General’s Office entered an appearance on behalf of the DNR. On February 8, 2010, Attorney Peter Racher entered an appearance on behalf of Musgrave. Then, on March *896 17, 2010, Attorneys Peter Racher and Stephanie Eckerle filed an “Amended Limited Appearance by Attorneys in a Civil Case” (App.98) as well as a motion to dismiss SCCC’s petition for lack of subject matter jurisdiction, lack of personal jurisdiction, insufficiency of process, insufficiency of service of process, and failure to state a claim upon which relief may be granted. The trial court denied Musgrave’s motion to dismiss on May 26, 2010.

The parties briefed the issue of whether the ALJ properly reversed the DNR’s decision on phase III release of the bond, and the trial court held oral argument on December 16, 2010. On March 11, 2011, the trial court issued its “Order on Verified Petition for Judicial Review” reversing the ALJ’s order and remanding for entry of judgment in favor of SCCC and the DNR.

Musgrave now appeals. Additional facts will be supplied as necessary.

Discussion and Decision

The Trial Court’s Jurisdiction

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
964 N.E.2d 891, 2012 WL 952224, 2012 Ind. App. LEXIS 118, Counsel Stack Legal Research, https://law.counselstack.com/opinion/musgrave-v-squaw-creek-coal-co-indctapp-2012.