In Re Upstream Addicks and Barker (Texas) Flood-Control Reservoirs v. United States

United States Court of Federal Claims·Decided December 15, 2021·No. 17-9001·Published

Opinion

In the United States Court of Federal Claims Sub-Master Docket No. 17-9001L

(Filed: December 15, 2021)

IN RE UPSTREAM ADDICKS AND Motion to certify class; timeliness; Rule 23 BARKER (TEXAS) FLOOD- criteria CONTROL RESERVOIRS

THIS DOCUMENT APPLIES TO:

ALL UPSTREAM CASES

Daniel H. Charest and E. Lawrence Vincent, Burns Charest LLP, Dallas, Texas, Charles Irvine, Irvine & Conner PLLC, Houston, Texas, and Edwin Armistead Easterby, Williams Hart Boundas Easterby, LLP, Houston, Texas, Co-Lead Counsel for Upstream Plaintiffs.

Kristine S. Tardiff, Trial Attorney, Environment & Natural Resources Division, United States Department of Justice, Washington, D.C., for defendant. With her on the briefs were Todd Kim, Assistant Attorney General, and Laura W. Duncan, Frances B. Morris, and Gregory M. Cumming, Trial Attorneys, Environment & Natural Resources Division, United States Department of Justice, Washington, D.C.

Vuk S. Vujasinovic, VB Attorneys, PLLC, Houston, Texas, filed a brief for the Banker plaintiffs. With him on the brief were Brian Beckom and Job Tennant, VB Attorneys, PLLC, Houston, Texas.

Zheng Luo, Katy, Texas, filed a brief pro se.

Ligang Lei, Katy, Texas, filed a brief pro se.

OPINION AND ORDER

LETTOW, Senior Judge.

Before the court is plaintiffs’ motion to certify a class limited to liability issues pursuant to Rule 23 of the Rules of the Court of Federal Claims (“RCFC”) in this Fifth Amendment taking case. Plaintiffs—property owners upstream of the Addicks and Barker Dams in the Houston, Texas area that experienced flooding during Tropical Storm Harvey—argue that the bellwether approach to case management employed throughout the past years of litigation is inferior to class certification. This motion arises after the conclusion of the liability phase of the trial of bellwether plaintiffs using the bellwether test-case approach. See generally Pls.’ Mot. for Class Certification (“Pls.’ Mot.”), ECF No. 397; Pls.’ Suppl. Br. (“Pls.’ Suppl.”), ECF No. 404; and Pls.’ Reply, ECF No. 408. The government counters that the motion for class certification comes too late and that plaintiffs should otherwise be denied certification on the merits. See Def.’s Opp’n to Pls.’ Mot. for Class Certification (“Def.’s Opp’n”), ECF No. 405. Plaintiffs’ motion is DENIED both because of the timing of their request and their failure to satisfy the criteria of RCFC 23.

BACKGROUND

These cases arise from a flooding event:

After making landfall in August 2017, Tropical Storm Harvey (“Harvey”) doused Houston with an average of 33.7 inches of rain over a four-day period. Many properties, including over 150,000 homes, flooded during the storm. Those affected included private property owners within the Addicks and Barker Reservoirs, west of Houston, upstream of the federally designed, built, and maintained Addicks and Barker Dams. During Harvey, the Addicks and Barker Dams collected storm water in their respective reservoirs [extending beyond government-owned land,] causing [private] properties [upstream but] within the reservoir to flood from the impounded water.

In re Upstream Addicks & Barker (Texas) Flood-Control Reservoirs, 146 Fed. Cl. 219, 227 (2019).

“The first complaint relating to Harvey and the Addicks and Barker Dams was filed on September 5, 2017. Hundreds of such cases followed.” In re Upstream Addicks & Barker, 146 Fed. Cl. at 228 (internal citation omitted). Initially, Chief Judge Braden of the court ordered those plaintiffs who sought class certification to move for certification by November 9, 2017. See Y and J Properties, Ltd. v. United States, 134 Fed. Cl. 465 (2017). On November 20, 2017, however, the Chief Judge relieved plaintiffs of the class certification deadline. See Order of Nov. 20, 2017 at 2, No. 17-3000, ECF No. 68. Instead, after soliciting case management suggestions from plaintiffs and defendant, “the Chief Judge . . . issued Management Order No. 1, consolidating these cases, and all related later-filed cases, within one master docket. The Chief Judge then bifurcated the issues of liability and damages, initially setting a schedule to deal with liability. Subsequently, [on December 5, 2017,] the Chief Judge divided the Master Docket into two sub-master dockets—one for downstream properties and, pertinent here, one for upstream properties.” In re Upstream Addicks & Barker, 146 Fed. Cl. at 228 (internal citations omitted).

In the upstream cases, the court applied the principles of multi-district litigation under 28 U.S.C. § 1407 and conducted pretrial proceedings under the guidance of 28 U.S.C. § 1407(b). “In the spring of 2018, thirteen plaintiff properties were designated to serve as bellwethers for the [upstream] cases.” In re Upstream Addicks & Barker, 146 Fed. Cl. at 228. “A ten-day trial was held in Houston, Texas, commencing on May 6, 2019, regarding the liability of the United States for the thirteen test properties.” Id. In December 2019, “the court [found] the government to be liable for a taking of a flowage easement on the [bellwether] properties.” Id.

2 Nearly two years later, as the parties engaged in discovery in preparation for the just compensation phase of the trial of the claims of bellwether plaintiffs, plaintiffs moved for class certification on September 24, 2021. See Pls.’ Mot. Following a supplemental briefing order, the matter is fully briefed. The court received additional briefs from one of the bellwether property owners raising questions about, but otherwise consistent with, certification, ECF No. 406, and from a pro se plaintiff, Zheng Luo, opposing certification on adequacy of counsel grounds, ECF No. 412. See also Pls.’ Reply to Pro Se Opp’n, ECF No. 413; Def.s’ Reply to Pro Se Opp’n, ECF No. 414. Another pro se plaintiff, Ligang Lei, filed a brief supporting certification, ECF No. 416. A hearing was held on November 29, 2021.

STANDARD FOR DECISION

Class actions are governed by RCFC 23. 1 To merit class certification,

a putative class representative must demonstrate: (i) numerosity—that the proposed class is so large that joinder is impracticable; (ii) commonality—that there are common questions of law or fact that predominate over questions affecting individual prospective class members and that the government has treated the prospective class members similarly; (iii) typicality—that his or her claims are typical of the proposed class; (iv) adequacy—that he or she will fairly represent the proposed class; and (v) superiority—that a class action is the fairest and most efficient method of resolving the suit.

1 Rule 23(a) and (b), in whole, require the following:

(a) Prerequisites. One or more members of a class may sue as representative parties on behalf of all members only if: (1) the class is so numerous that joinder of all members is impracticable; (2) there are questions of law or fact common to the class; (3) the claims or defenses of the representative parties are typical of the claims or defenses of the class; and (4) the representative parties will fairly and adequately protect the interests of the class.

(b) Class Actions Maintainable. A class action may be maintained if RCFC 23(a) is satisfied and if: (1) [not used]; (2) the United States has acted or refused to act on grounds generally applicable to the class; and (3) the court finds that the questions of law or fact common to class members predominate over any questions affecting only individual members, and that a class action is superior to other available methods for fairly and efficiently adjudicating the controversy.

Free access — add to your briefcase to read the full text and ask questions with AI

In Re Upstream Addicks and Barker (Texas) Flood-Control Reservoirs v. United States, (uscfc 2021).

In Re Upstream Addicks and Barker (Texas) Flood-Control Reservoirs v. United States (In Re Upstream Addicks and Barker (Texas) Flood-Control Reservoirs v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. General Motors Corp.
323 U.S. 373 (Supreme Court, 1945)
American Pipe & Construction Co. v. Utah
414 U.S. 538 (Supreme Court, 1974)
Eisen v. Carlisle & Jacquelin
417 U.S. 156 (Supreme Court, 1974)
East Texas Motor Freight System, Inc. v. Rodriguez
431 U.S. 395 (Supreme Court, 1977)
General Telephone Co. of Southwest v. Falcon
457 U.S. 147 (Supreme Court, 1982)
United States v. Mendoza
464 U.S. 154 (Supreme Court, 1984)
Amchem Products, Inc. v. Windsor
521 U.S. 591 (Supreme Court, 1997)
Wal-Mart Stores, Inc. v. Dukes
131 S. Ct. 2541 (Supreme Court, 2011)
Jimenez v. Weinberger
523 F.2d 689 (Seventh Circuit, 1975)
Robidoux v. Celani
987 F.2d 931 (Second Circuit, 1993)
Messner v. Northshore University HealthSystem
669 F.3d 802 (Seventh Circuit, 2012)
Trevizo v. Adams
455 F.3d 1155 (Tenth Circuit, 2006)
Turner v. United States
115 Fed. Cl. 614 (Federal Claims, 2014)
Two Shields v. United States
820 F.3d 1324 (Federal Circuit, 2016)
Charleston Area Medical Ctr. v. United States
940 F.3d 1362 (Federal Circuit, 2019)
Barnes v. United States
68 Fed. Cl. 492 (Federal Claims, 2005)