In re Tyco (Kozlowski 03-1343) MD-02-1335-B 03/16/04
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
In re Tyco International, Ltd. Multidistrict Litigation (MDL 1335) MDL DOCKET NO. 02-1335-B TYCO-PLAINTIFF ACTIONS Case N o . 03-1343-B
Opinion N o . 2004 DNH 048
MEMORANDUM AND ORDER
Tyco International, Ltd. has sued its former Chief Executive
Officer L . Dennis Kozlowski for fraud and breach of fiduciary
duty. One of the complaint’s several counts seeks a declaratory
judgment that Kozlowski fraudulently induced Tyco to enter into a
“Retention Agreement” that guaranteed Kozlowski substantial
benefits if he was terminated. The Retention Agreement contains
an arbitration clause which provides that “[a]ny dispute or
controversy under this Agreement shall be settled exclusively by
arbitration in accordance with the rules of the American
Arbitration Association then in effect.” Kozlowski moves to
compel arbitration based on his assertion that all of Tyco’s claims are subject to the arbitration clause. In the
alternative, Kozlowski moves to dismiss the eighth cause of
action, a breach of contract claim, and the twelfth cause of
action, a contribution claim.
I.
Kozlowski first argues that I cannot determine which, if
any, of Tyco’s claims are arbitrable because the Retention
Agreement reserves such questions for the arbitrator. Because
Kozlowski’s argument runs counter to the presumption that the
court should resolve arbitrability issues, I will accept his
argument only if the Retention Agreement “clearly and
unmistakably” provides that arbitrability issues should be
resolved by an arbitrator rather than the court. Howsam v . Dean
Witter Reynolds, Inc., 537 U.S. 7 9 , 83 (2002)(quoting AT & T
Techs., Inc. v . Communications Workers, 475 U.S. 643, 649 (1986).
Kozlowski bases his argument on the Retention Agreement’s
arbitration clause, which states that “[a]ny dispute or
controversy under this Agreement shall be settled exclusively by
2 arbitration in accordance with the rules of the American
Arbitration Association then in effect.” (Mot. of Def. to
Dismiss or Stay & Compel Arb. Ex. A ¶ 18.) He then cites Rule 8
of the applicable American Arbitration Association (“AAA”) rules,
which provides that “the arbitrator shall conduct an Arbitration
Management Conference with the parties . . . to explore and
resolve matters that will expedite the arbitration proceedings.
The specific matters to be addressed include: (i) the issues to
be arbitrated . . . .” (Mot. of Def. to Dismiss or Stay & Compel
Arb. Ex. B ¶ 8.) Because the Retention Agreement incorporates an
AAA rule that requires the arbitrator to discuss the “issues to
be arbitrated” at an Arbitration Management Conference, Kozlowski
claims that the Retention Agreement clearly and unmistakably
requires arbitrability questions to be resolved by the
arbitrator. I disagree.
Rule 8 requires the arbitrator to convene an Arbitration
Management Conference “[a]s soon as possible” after the
arbitrator is appointed. The stated purpose of the conference is
“to explore and resolve matters that will expedite the
3 arbitration proceedings.” The rule then lists 12 specific
matters to be discussed at the conference, including “the issues
to be arbitrated.”1 Kozlowski views Rule 8 as a grant of
authority to the arbitrator to resolve all arbitrability
questions as well as to control the other matters identified in
the rule. A review of the rule in context, however, reveals that
it merely identifies issues that must be discussed at the
conference without granting the arbitrator any additional power
that she does not otherwise have under the Retention Agreement
itself or other AAA rules.
Although Rule 8 lists items to be discussed at the
Arbitration Management Conference, the arbitrator’s authority
over each of the identified items is established by a counterpart
elsewhere in the rules. Two examples illustrate the point. Rule
1 The 12 matters to be discussed include (i) the issues to be arbitrated; (ii) the date, time, place, and duration of the hearings; (iii) the resolution of outstanding discovery issues; (iv) the applicable rules of evidence and burdens of proof; (v)the exchange of stipulations; (vi) witness names and scope of their testimony; (vii) bifurcation of the proceedings into liability and damages phases; (viii) the need for a stenographic record; (ix) the need for oral argument; (x) the form of the award; (xi) any other issues relating to the subject or conduct of the arbitration; and (xii) the allocation of attorney’s fees.
4 8 requires the arbitrator to discuss outstanding discovery issues
at the conference but the arbitrator’s power to control discovery
is found in Rule 7 , which provides in pertinent part that
“[t]he arbitrator shall have the authority to order such
discovery . . . as the arbitrator considers necessary . . . .”
Similarly, Rule 8 requires the arbitrator to discuss “the date,
time, place and estimated duration of the hearing” but the
arbitrator’s power to determine disputes concerning these matters
is found in Rule 10 which provides that “[t]he arbitrator shall
have the authority to set the date and time of the hearing in
consultation with the parties.” Each of the other items listed
in Rule 8 has a similar counterpart elsewhere in the rules that
explicitly defines the arbitrator’s authority with respect to that item.2
2 The authority to allow a new or different claim or counterclaim after the appointment of the arbitrator is set out in Rule 5 ; to determine the date, time, and place of the hearing is in Rule 9 and 1 0 ; to resolve discovery issues is in Rule 7 ; to determine the standards of proof, applicable law, witness names and scope of their testimony, and to exercise authority over the presentation of evidence is in Rule 2 2 ; to determine to bifurcate the proceedings is in Rule 2 4 ; to set oral argument is in rule 3 0 ; to determine the form of the award is in Rule 34(d); to set the rules of conduct for the proceedings is in Rule 2 2 ; and to award attorney’s fees is in Rule 34(e).
5 Rule 5 is the counterpart to Rule 8’s listing of “the issues
to be arbitrated” as an issue to be discussed at the Arbitration
Management Conference. It describes the procedures that the
parties must follow when amending arbitration claims and gives
the arbitrator the power to reject new or different claims that
are filed after the arbitrator is appointed. Nowhere do the
rules grant the arbitrator the exclusive power to resolve other
arbitrability disputes. Thus, while Rule 8 requires the
arbitrator to discuss the issues to be arbitrated at the
conference, the power to resolve arbitrability questions, apart
from the power to reject claims that are filed after the
arbitrator is appointed, must be found in the parties’ agreement
to arbitrate. Because the Retention Agreement does not clearly
and unmistakably give such power to the arbitrator, I reject
Kozlowski’s claim that the arbitrator must resolve the
arbitrability issues that his motion to compel presents.
II.
Kozlowski alternatively argues that I should determine that
all of Tyco’s claims are subject to arbitration. I have
Free access — add to your briefcase to read the full text and ask questions with AI
In re Tyco (Kozlowski 03-1343) MD-02-1335-B 03/16/04
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
In re Tyco International, Ltd. Multidistrict Litigation (MDL 1335) MDL DOCKET NO. 02-1335-B TYCO-PLAINTIFF ACTIONS Case N o . 03-1343-B
Opinion N o . 2004 DNH 048
MEMORANDUM AND ORDER
Tyco International, Ltd. has sued its former Chief Executive
Officer L . Dennis Kozlowski for fraud and breach of fiduciary
duty. One of the complaint’s several counts seeks a declaratory
judgment that Kozlowski fraudulently induced Tyco to enter into a
“Retention Agreement” that guaranteed Kozlowski substantial
benefits if he was terminated. The Retention Agreement contains
an arbitration clause which provides that “[a]ny dispute or
controversy under this Agreement shall be settled exclusively by
arbitration in accordance with the rules of the American
Arbitration Association then in effect.” Kozlowski moves to
compel arbitration based on his assertion that all of Tyco’s claims are subject to the arbitration clause. In the
alternative, Kozlowski moves to dismiss the eighth cause of
action, a breach of contract claim, and the twelfth cause of
action, a contribution claim.
I.
Kozlowski first argues that I cannot determine which, if
any, of Tyco’s claims are arbitrable because the Retention
Agreement reserves such questions for the arbitrator. Because
Kozlowski’s argument runs counter to the presumption that the
court should resolve arbitrability issues, I will accept his
argument only if the Retention Agreement “clearly and
unmistakably” provides that arbitrability issues should be
resolved by an arbitrator rather than the court. Howsam v . Dean
Witter Reynolds, Inc., 537 U.S. 7 9 , 83 (2002)(quoting AT & T
Techs., Inc. v . Communications Workers, 475 U.S. 643, 649 (1986).
Kozlowski bases his argument on the Retention Agreement’s
arbitration clause, which states that “[a]ny dispute or
controversy under this Agreement shall be settled exclusively by
2 arbitration in accordance with the rules of the American
Arbitration Association then in effect.” (Mot. of Def. to
Dismiss or Stay & Compel Arb. Ex. A ¶ 18.) He then cites Rule 8
of the applicable American Arbitration Association (“AAA”) rules,
which provides that “the arbitrator shall conduct an Arbitration
Management Conference with the parties . . . to explore and
resolve matters that will expedite the arbitration proceedings.
The specific matters to be addressed include: (i) the issues to
be arbitrated . . . .” (Mot. of Def. to Dismiss or Stay & Compel
Arb. Ex. B ¶ 8.) Because the Retention Agreement incorporates an
AAA rule that requires the arbitrator to discuss the “issues to
be arbitrated” at an Arbitration Management Conference, Kozlowski
claims that the Retention Agreement clearly and unmistakably
requires arbitrability questions to be resolved by the
arbitrator. I disagree.
Rule 8 requires the arbitrator to convene an Arbitration
Management Conference “[a]s soon as possible” after the
arbitrator is appointed. The stated purpose of the conference is
“to explore and resolve matters that will expedite the
3 arbitration proceedings.” The rule then lists 12 specific
matters to be discussed at the conference, including “the issues
to be arbitrated.”1 Kozlowski views Rule 8 as a grant of
authority to the arbitrator to resolve all arbitrability
questions as well as to control the other matters identified in
the rule. A review of the rule in context, however, reveals that
it merely identifies issues that must be discussed at the
conference without granting the arbitrator any additional power
that she does not otherwise have under the Retention Agreement
itself or other AAA rules.
Although Rule 8 lists items to be discussed at the
Arbitration Management Conference, the arbitrator’s authority
over each of the identified items is established by a counterpart
elsewhere in the rules. Two examples illustrate the point. Rule
1 The 12 matters to be discussed include (i) the issues to be arbitrated; (ii) the date, time, place, and duration of the hearings; (iii) the resolution of outstanding discovery issues; (iv) the applicable rules of evidence and burdens of proof; (v)the exchange of stipulations; (vi) witness names and scope of their testimony; (vii) bifurcation of the proceedings into liability and damages phases; (viii) the need for a stenographic record; (ix) the need for oral argument; (x) the form of the award; (xi) any other issues relating to the subject or conduct of the arbitration; and (xii) the allocation of attorney’s fees.
4 8 requires the arbitrator to discuss outstanding discovery issues
at the conference but the arbitrator’s power to control discovery
is found in Rule 7 , which provides in pertinent part that
“[t]he arbitrator shall have the authority to order such
discovery . . . as the arbitrator considers necessary . . . .”
Similarly, Rule 8 requires the arbitrator to discuss “the date,
time, place and estimated duration of the hearing” but the
arbitrator’s power to determine disputes concerning these matters
is found in Rule 10 which provides that “[t]he arbitrator shall
have the authority to set the date and time of the hearing in
consultation with the parties.” Each of the other items listed
in Rule 8 has a similar counterpart elsewhere in the rules that
explicitly defines the arbitrator’s authority with respect to that item.2
2 The authority to allow a new or different claim or counterclaim after the appointment of the arbitrator is set out in Rule 5 ; to determine the date, time, and place of the hearing is in Rule 9 and 1 0 ; to resolve discovery issues is in Rule 7 ; to determine the standards of proof, applicable law, witness names and scope of their testimony, and to exercise authority over the presentation of evidence is in Rule 2 2 ; to determine to bifurcate the proceedings is in Rule 2 4 ; to set oral argument is in rule 3 0 ; to determine the form of the award is in Rule 34(d); to set the rules of conduct for the proceedings is in Rule 2 2 ; and to award attorney’s fees is in Rule 34(e).
5 Rule 5 is the counterpart to Rule 8’s listing of “the issues
to be arbitrated” as an issue to be discussed at the Arbitration
Management Conference. It describes the procedures that the
parties must follow when amending arbitration claims and gives
the arbitrator the power to reject new or different claims that
are filed after the arbitrator is appointed. Nowhere do the
rules grant the arbitrator the exclusive power to resolve other
arbitrability disputes. Thus, while Rule 8 requires the
arbitrator to discuss the issues to be arbitrated at the
conference, the power to resolve arbitrability questions, apart
from the power to reject claims that are filed after the
arbitrator is appointed, must be found in the parties’ agreement
to arbitrate. Because the Retention Agreement does not clearly
and unmistakably give such power to the arbitrator, I reject
Kozlowski’s claim that the arbitrator must resolve the
arbitrability issues that his motion to compel presents.
II.
Kozlowski alternatively argues that I should determine that
all of Tyco’s claims are subject to arbitration. I have
6 previously considered identical arguments supporting Mark
Belnick’s request for arbitration under an identical arbitration
clause. See In re Tyco Int’l Inc. Multidistrict Litig., Opinion
N o . 2003 DNH 228. Rather than repeat my analysis, I find that
Tyco’s fraudulent inducement claim is arbitrable but that its
remaining claims are not for the reasons I articulated in that
Order. I also reject Kozlowski’s request to stay the litigation
of the nonarbitrable claims.3
3 Tyco makes a waiver argument that is slightly more developed here than in the prior Belnick proceeding and so I address it briefly. The crux of Tyco’s argument is that Kozlowski’s delay in seeking arbitration for sixteen months from the time of his employment termination, and a delay of over a year since Tyco first filed this suit against him, waives his rights under the arbitration agreement. I disagree. In determining whether a party has waived its arbitration rights I must be mindful that any doubts as to arbitrability “should be resolved in favor of arbitration, whether the problem at hand is . . . an allegation of waiver, delay, or a like defense to arbitrability.” Moses H . Cone Mem’l Hosp. v . Mercury Constr. Corp., 460 U.S. 1 , 25 (1983)(“‘[W]aiver is not to be lightly inferred, and mere delay in seeking [arbitration], without some resultant prejudice to a party cannot carry the day’” (citing Rush v . Oppenheimer & Co., 779 F.2d 885 (2d Cir. 1985)); Page v . Moseley, Hallgarten, Estabrook & Weeden, Inc., 806 F.2d 2 9 1 , 293 (1st Cir. 1986); see also Creative Solutions Group, Inc. v . Pentzer Corp., 252 F.3d 28 (1st Cir. 2001). Tyco fails to assert any prejudice caused by Kozlowski’s delay in seeking arbitration and therefore fails to establish that Kozlowski waived his arbitration rights. Given the slow progress of litigation in the civil proceedings to date, Tyco would be
7 III.
Kozlowski’s next argument challenges the sufficiency of
Tyco’s breach of contract claim under Fed. R. Civ. P. 12(b)(6).
Kozlowski contends that the complaint merely asserts that he
breached the Company’s Key Employee Loan (“KEL”) Program, and
does not allege that he breached a valid contract. Again, I
disagree.
In considering a Rule 12(b)(6) motion, I “must accept as
true the well-pleaded factual allegations of the complaint, draw
all reasonable inferences therefrom in the plaintiff’s favor, and
determine whether the complaint, so read, limns facts sufficient
to justify recovery on any cognizable theory.” LaChapelle v .
Berkshire Life Ins. Co., 142 F.3d 5 0 7 , 508 (1st Cir. 1998). The
pleadings must give the defendant fair notice of what the claims
are and the grounds on which they rest. E.g., Persson v . Scotia
hard pressed to establish that a delay of only sixteen months has produced sufficient prejudice to warrant a waiver of Kozlowski’s arbitration rights. See Restoration Pres. Masonry, Inc. v . Grove Eur. Ltd., 325 F.3d 5 4 , 61 (1st Cir. 2003) (“The length of delay must be evaluated in the context of litigation activities engaged in during that time.”). For these reasons, I reject Kozlowski’s waiver argument.
8 Prince Cruises, Ltd., 330 F.3d 2 8 , 34 (1st Cir. 2003). With this
in mind, I evaluate Tyco’s breach of contract claim.
In order to establish a breach of contract, the complaint
“must allege (1) the existence of a valid and binding contract;
(2) that plaintiff has complied with the contract and performed
his own obligations under i t ; and (3) breach of the contract
causing damages.” Id. The complaint alleges these exact
requirements. Tyco alleges that Kozlowski bound himself to the
terms of a loan program by accepting the loans and breached those
terms by not repaying the loans upon the termination of his
employment. In other words, the complaint argues that a valid
and binding contract existed whereby Kozlowski agreed to repay
any outstanding loans made by Tyco under the program upon the end
of his employment. Tyco gave Kozlowski the loans, thereby
fulfilling its obligation under the contract, and Kozlowski
breached the contract by not repaying the loans, resulting in
damages to Tyco in the amount of the unpaid loans. The complaint
directs Kozlowski to the appropriate loan agreement, the KEL
Program, and the amount of unpaid loans ($43,840,461). The
complaint asserts enough to easily satisfy Rule 12(b)(6) by
9 alleging a breach of contract, even if Tyco does not call the
breached agreement a contract per s e . See, e.g., Carroll v .
Kahn, N o . 03-CV-0656, 2003 WL 22327299, at *4 (N.D.N.Y. Oct. 9,
2003) (complaint found sufficient that asserted an agreement had
been made and then breached without referring to it as a contract
per s e ) . I therefore deny Kozlowski’s motion to dismiss the
breach of contract claim under Rule 12(b)(6).
IV.
Kozlowski also argues that Tyco’s contract claim is unripe
because it is contingent upon the outcome of the ERISA,
Securities, and Derivative Actions pending against i t . I
A federal court may entertain only claims that involve
actual justiciable controversies. See Ala. Fed’n of Labor v .
McAdory, 325 U.S. 4 5 0 , 461 (1945). These controversies must be
“definite and concrete, touching the legal relations of parties
having adverse legal interests. [They must be controversies]
admitting of specific relief through a decree of a conclusive
character, as distinguished from an opinion advising what the law
10 would be upon a hypothetical state of facts.” Aetna Life Ins.
C o . v . Haworth, 300 U.S. 2 2 7 , 240-41 (1937). Therefore, the
“disagreement [between the litigants] must not be nebulous or
contingent but must have taken on fixed and final shape so that a
court can see what legal issues it is deciding, what effect its
decision will have on the adversaries, and some useful purpose to
be achieved in deciding them.” Pub. Serv. Comm’n v . Wycoff Co.,
344 U.S. 2 3 7 , 244 (1952).
The Court has gone even further by declaring that the issue
of ripeness turns on “the fitness of the issues for judicial
decision and the hardship to the parties of withholding court
consideration.” Pac. Gas & Elec. C o . v . State Energy Res.
Conservation & Dev. Comm’n, 461 U.S. 1 9 0 , 201 (1983) (internal
quotations omitted). The ripeness inquiry, however, is case
specific, “and the various integers that enter into the ripeness
equation play out quite differently from case to case.” Ernst &
Young v . Depositors Econ. Prot. Corp., 45 F.3d 5 3 0 , 535 (1st Cir.
1995) (“The ripeness inquiry is often sui generis.”).
This circuit has held in a similar circumstance that a
contribution claim is ripe, even if it is contingent on a
11 separate finding of liability, as it is here. D’Onofrio Constr.
C o . v . Recon Co., 255 F.2d 904 (1st Cir. 1958). In D’Onofrio,
the court stated:
But if the event has already occurred out of which a common liability may be asserted to have arisen, and if the injured party has already commenced an action against one of the possible joint tortfeasors, one cannot deny that a case or controversy in a constitutional sense has already come into existence as between the defendant sued and the other possible joint tortfeasor who is under a contingent obligation to make contribution.
Id. at 909. While D’Onofrio dealt with joint tortfeasors and a
contingent contribution claim, its principle applies equally to
Tyco’s contingent contribution claim against Kozlowski.
Likewise, in Lehman v . Revolution Portfolio LLC, the First
Circuit held that impleading a third-party defendant on theories
of indemnification and contribution presented justiciable claims
even though the claims were contingent upon the defendant being
found liable to the plaintiff in the underlying suit. 166 F.3d
389 (1st Cir. 1999). In so far as a claim for contribution
against an impleaded third-party defendant is ripe, that same
claim is also ripe outside the impleader context.
12 I agree with Tyco that its claim for contribution is a
“real, immediate and concrete controversy among true adversaries
which is ripe for resolution.” Avemco Ins. C o . v . Pond, N o . 94-
CV-073-B, 1994 WL 516449, at *2 (D.N.H. Sept. 2 0 , 1994). Tyco
currently faces multiple lawsuits for extraordinary damages
stemming, arguably, from Kozlowski’s alleged breach of fiduciary
duties. The facts underlying Kozlowski’s alleged liability for
contribution will be developed in the present litigation and Tyco
and Kozlowski are clearly adverse parties. With this in mind,
Tyco’s contribution claim against Kozlowski is fit for judicial
review.4
CONCLUSION
For the reasons set forth in this Memorandum and Order, I
grant Kozlowski’s request to compel arbitration of Tyco’s
fraudulent inducement claim and otherwise deny its request to
either compel arbitration of Tyco’s remaining claims or to stay
the litigation of those claims until the fraudulent inducement
4 damage award on the contribution claim can always be A until Tyco’s liability in the underlying suits is deferred finally established, if in fact it ever i s . See Oxford Shipping C o . v . N.H. Trading Corp., 697 F.2d 1 , 8 (1st Cir. 1982).
13 claim is resolved (doc. n o . 6 ) . I also deny Kozlowski’s motion
to dismiss the breach of contract and contribution claims.
SO ORDERED.
Paul Barbadoro Chief Judge March 1 6 , 2004
cc: Counsel of Record