In Re Stone & Webster, Inc.

279 B.R. 748, 2002 Bankr. LEXIS 606, 2002 WL 1286138
CourtUnited States Bankruptcy Court, D. Delaware
DecidedMay 30, 2002
Docket17-12759
StatusPublished
Cited by5 cases

This text of 279 B.R. 748 (In Re Stone & Webster, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Stone & Webster, Inc., 279 B.R. 748, 2002 Bankr. LEXIS 606, 2002 WL 1286138 (Del. 2002).

Opinion

MEMORANDUM OPINION

MCKELVIE, District Judge.

This is a commercial dispute that arises in the context of a bankruptcy action.

Stone & Webster Engineering Corporation (“SWEC”) is a Massachusetts corporation with its principal place of business in Boston, Massachusetts. Stone & Webster Incorporated (“SWINC”) is a Delaware corporation with its principal place of business in Boston, Massachusetts. Stone & Webster Engineers and Constructors, Inc. (“SWE&C”) is a Maryland Corporation with its principal place of business in Boston, Massachusetts. The Stone & Webster companies are affiliated in the following manner. SWINC owns one hundred percent of the shares of SWE & C which, in turn, owns one hundred percent of the shares of SWEC. The court will refer to these three companies collectively as either “the Debtors” or “the Stone & Webster companies.”

Claimant Maine Yankee Atomic Power Company is a Maine corporation with its principal place of business in Wiscasset, Maine. Maine Yankee owns a nuclear power generating facility in Wiscasset, Maine.

This dispute arises from a contract, effective August 31, 1998, that was entered between Maine Yankee and SWEC, whereby Maine Yankee hired SWEC to decommission Maine Yankee’s Wiscasset nuclear power generating facility (the “Decommissioning Agreement”). Pursuant to the Decommissioning Agreement, SWE&C and SWINC executed written guaranties of SWEC’s performance under the Agreement. SWE&C executed its written guarantee of SWEC’s performance at the time that Maine Yankee and SWEC entered into the Agreement, while SWINC executed its written guaranty in December of 2000, in the wake of concerns voiced by Maine Yankee regarding SWEC’s solvency-

On May 4, 2000, Maine Yankee issued a notice to SWEC stating that it was terminating the Decommissioning Agreement based upon SWEC’s insolvency and because SWEC had not adequately performed under the contract. Both purported grounds for termination are provided for under the contract as allowable reasons to terminate the Agreement for cause. Soon thereafter, on June 2, 2000, SWINC, and certain of its affiliates, including SWE&C and SWEC, filed voluntary petitions for bankruptcy relief under Chapter 11 of the United States Bankruptcy Code, 11 U.S.C. §§ 101-1330. Maine Yankee has assumed the role of the contractor on its project, and is currently proceeding with the decommissioning of the power plant.

On August 23, 2000, Maine Yankee filed proofs of claim in the bankruptcy cases against SWEC and against SWINC and *755 SWE & C, as guarantors of SWEC’s performance. Maine Yankee’s proofs of claim seek damages from the debtors for SWEC’s breach of the Decommissioning Agreement. On November 16, 2000, the Debtors objected to Maine ' Yankee’s claims, arguing that the court should disallow the claims because Maine Yankee did not properly terminate the Decommissioning Agreement for either insolvency or failure to perform and, in any event, did not have a right to damages for terminating the agreement on account of SWEC’s insolvency.

On February 13, 2001, the court held a one-day non-jury trial to consider Maine Yankee’s claims and certain of the Debtors’ threshold defenses. In an opinion dated July 26, 2001, the court refused to disallow Maine Yankee’s claims. 1 However, it did permit SWEC to assert its own claims against Maine Yankee for work performed by SWEC that was uncompensated by Maine Yankee. Any damages proven by SWEC could then be set-off against Maine Yankee’s claims.

In a subsequent memorandum opinion, dated November 21, 2001, the court considered several motions for partial summary judgment that had been filed by the Debtors. The court granted the Debtors’ motion limiting Maine Yankee’s damages claim to the $65 million damages cap set forth in Article 30.2 of the Decommissioning Agreement. The court denied the remainder of Debtors’ motions, which sought summary judgment based on the following affirmative defenses: (i) that Maine Yankee’s damages claim is unripe due to Maine Yankee’s failure to fulfill certain conditions precedent under the Decommissioning Agreement; and (ii) that Maine Yankee’s claim should be barred because it failed to mitigate damages by refusing to accept the tender of performance offered by SWINC and SWE&C.

In order to resolve Maine Yankee’s August 23, 2000 Proofs of Claim, the court held a seven day bench trial between November 26 and December 3, 2001. The principal issues presented to the court included: (i) whether Debtors are liable to Maine Yankee for breach of the Decommissioning Agreement; (ii) what amount of damages, if any, is Maine Yankee entitled to from SWEC for SWEC’s alleged breach of the Decommissioning Agreement; and (iii) what amount of damages, if any, is Maine Yankee entitled to from SWINC and SWE&C pursuant to their guarantees of SWEC’s performance under the Decommissioning Agreement. If it finds that Maine Yankee is entitled to damages, the court must also resolve whether its findings based on the trial are to be used for purposes of allowing Maine Yankee’s claim or for purposes of estimating the dollar amount of Maine Yankee’s future allowable claim.

Closing arguments in the trial were made on April 3, 2002, and the post-trial briefing is now complete. Having reviewed the trial transcript, exhibits, and briefing, this is the court’s decision on Maine Yankee’s Proofs of Claim.

I. FACTUAL BACKGROUND

The court draws the following facts from the stipulated facts set forth in the pretrial order and from the testimony and exhibits presented during the trial in this case.

*756 In its case in chief, Maine Yankee called eleven witnesses, including Wayne Norton, Maine Yankee’s current President and its former contract manager and Vice President of Decommissioning; Edward Doubleday, Maine Yankee’s damages expert; Raymond Burke, Maine Yankee’s current Vice President of Decommissioning and the former contracts manager for SWEC on the Maine Yankee decommissioning project; Michael Evringham, Maine Yankee’s current contracts and procurement manager; Todd Smith, Maine Yankee’s project controls manager; David Holbert, Maine Yankee’s logistics project manager for the waste management group; Michael Meisner, Maine Yankee’s former President and current Chief Nuclear Officer; Paul Plante, Maine Yankee’s project manager for cask loading and fuel transfer; James Garvey, Maine Yankee’s director of business integration; Michael Thomas, Maine Yankee’s Vice President and Chief Financial Officer; and Robert Gerber, an environmental consultant who assisted Maine Yankee and SWEC on the decommissioning project.

Maine Yankee also designated portions of deposition testimony from James Bern-hard, the Chief Executive Officer of the Shaw Group, a company that bid on the Maine Yankee project and ultimately acquired the assets of Stone & Webster at a bankruptcy auction, and Jerome Kane, the replacement project manager that SWEC deployed to manage the decommissioning project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Rappaport
517 B.R. 518 (D. New Jersey, 2014)
In re Mud King Products, Inc.
514 B.R. 496 (S.D. Texas, 2014)
Yankee Atomic Electric Company v. United States
113 Fed. Cl. 323 (Federal Claims, 2013)
American Property Construction Co. v. Sprenger Lang Foundation
768 F. Supp. 2d 198 (District of Columbia, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
279 B.R. 748, 2002 Bankr. LEXIS 606, 2002 WL 1286138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-stone-webster-inc-deb-2002.