Brooklyn Waterfront Terminal Corp. v. International Terminal Operating Co.

211 F. Supp. 702, 1962 U.S. Dist. LEXIS 3382
CourtDistrict Court, S.D. New York
DecidedMarch 20, 1962
StatusPublished
Cited by16 cases

This text of 211 F. Supp. 702 (Brooklyn Waterfront Terminal Corp. v. International Terminal Operating Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brooklyn Waterfront Terminal Corp. v. International Terminal Operating Co., 211 F. Supp. 702, 1962 U.S. Dist. LEXIS 3382 (S.D.N.Y. 1962).

Opinion

WEINFELD, District Judge.

Plaintiff, Brooklyn Waterfront Terminal Corp., hereafter called Brooklyn, seeks to recover damages to a pier allegedly caused by dredging operations conducted by or on behalf of the defendant, International Terminal Operating Co., Inc., hereafter called International. Defendant denies liability, asserting in general that the damage to the pier was due to defective conditions existing prior to the dredging.

[703]*703Brooklyn, the owner of Pier 3, located at the foot of East 19th Street, Gowanus Canal, Brooklyn, New York, leased it to International in April 1956 for a fifteen-year term. In order to accommodate ships of deep draft, International, in November 1956 and January 1957, pursuant to permission granted it by plaintiff, dredged the slip of the pier to a depth of twenty-eight feet below mean low water at a distance of twenty-five feet off the face of the pier. This dredging, however, failed of its intended purpose; vessels went aground in the slip and could not be berthed close to the pier. Thereupon International requested Brooklyn’s consent to another dredging —this time to a depth of thirty feet below mean low water and at a distance of ten feet off the face of the pier.

Brooklyn questioned whether a dredging to a greater depth and closer to the fender piles could be effected without damage to the pier. However, consent thereto was granted, conditioned upon International’s agreement to make good any damage that might result to the pier and bulkhead and also upon the issuance of an appropriate policy of insurance in plaintiff’s favor, which in due course was issued by the co-defendant, Fireman’s Fund Insurance Company. Thereafter, the second dredging was performed in April 1957 to a depth of thirty feet plus two feet1 below mean low water and ten feet off the fender piles.

The pier is a pile platform thirty feet wide and about 620 feet long. It consists of a concrete deck about ten inches thick supported on timber piles placed in lines called bents running the width of the pier. These bents are spaced at intervals of ten feet for the whole length of the pier.2 The piles in each bent are spaced approximately four feet six inches on centers and are braced horizontally and diagonally. In general, each bent consists of seven bearing piles, one batter pile, one fender pile, a cross cap of twelve-by-twelve timber beams carrying the deck and a lateral bracing system. There are also some intermediate batter' piles between bents.

The water slip where ships berth abuts-the northerly side of the pier. Along the rear of the pier, distant thirty feet southerly from the face thereof, is a bulkhead running the entire length of the pier’s underside. Beyond the bulkhead is miscellaneous fill consisting of sand, gravel, cinders, silt and other substances. The surface of the fill material is paved to a width of about twenty feet beyond the bulkhead, making a street adjacent to the pier deck.

The function of the bulkhead is to retain the fill. It consists of timber sheathing driven into the soil below the water and held in place by two timber wales— one just below the cap beam and the other at or below the low water line. The batter piles are secured to the top wale generally at five-foot intervals; in the instances where they are located at the-bents they are also connected to the cap> beams. The pressure or force actuated by the fill material, trucks using its surface and cargo stored thereon, if not resisted by an adequate counterforce on the water side of the bulkhead, would tend to move the pier structure out toward the slip rendering it unstable and unfit for use. The pier did become unstable and the conflict here centers about the cause. The plaintiff contends that the second dredging set in motion forces which resulted in the instability. The defendant,, on the other hand, contends that deficiencies in the pier, antedating the dredging, were the cause.

About three weeks after the completion of the April 1957 dredging, there was subsidence of the fill area alongside of and for a distance of twenty feet beyond the bulkhead. The subsidence, or depression, adjacent to the bulkhead extended from the inshore bents to bent-45, and ranged originally from two inch[704]*704es to a foot and progressively deepened as time went on. In addition, there was a lateral movement of the pier toward the water or slip side; the platform listed toward the water from three to four inches at one end to one and one half feet at the other. Eventually, the platform and various parts of the understructure were affected. Piles were dislodged and shifted from their usual positions of support for the pier structure. The bearing piles moved or tilted toward the slip; the batter piles, originally driven into the ground at an angle, straightened out, moved up and pushed against and into the asphalt and concrete decking of the pier and the deck platform was raised above the bulkhead sheathing. In end result the pier was rendered unstable and, to make it useable and workable, it had to be completely rehabilitated.3

Plaintiff, to prove its claim, relied upon the testimony of a soil engineer and other expert witnesses. The soil engineer made test borings in front of and under the pier and in the fill area. Among the matters which he determined were the nature of the various soil materials at different strata underneath the mud line, 4 the in-place shear strength value of the soil — i. e., its cohesive resistance, and the content of the fill material back of the bulkhead.

Based principally upon the soil engineer’s testimony, the plaintiff’s claim is that the dredging caused a massive rotational failure or slide of soil from south to north commencing at a point approximately twenty feet behind the bulkhead moving counterclockwise and passing through the average bottom elevation of the sheet pile bulkhead, through the area of the piles supporting the pier and out toward the slip. In the opinion of the plaintiff’s expert the earth removed by the 1957 dredging had, prior to its removal, served, together with other elements, as a sort of brake against a mass movement of soil. It was his view that before the dredging, the soil and other forces on the water side of the bulkhead were sufficient to resist the downward and outward pressure created by the fill material and various surcharges thereon5 — that the factor of safety, as the experts term' it, was then at least or greater than one — in substance, that the resistant forces counterbalanced the actuating forces exerting pressure, thereby preventing sliding or mass movement of soil.

The expert believed that the soil removed by the dredging off the face of the pier caused a sloughing off of the earth beyond it which could not sustain itself in a vertical slope, altered the soil contour and reduced the resistant forces below the actuating forces. He concluded that because of this imbalance, which resulted in reducing the factor of safety below one, a massive rotational slide or movement occurred which involved the entire soil area, including the bulkhead, the soil on the land side of the bulkhead and the soil on the water side. It was his judgment that this slide accounted for the subsidence behind the bulkhead, the lateral offshore movement of the pier structure and the dislocation of the batter and bearing piles. In sum, that the instability of the pier was a direct result of, and attributable to, the April 1957 dredging.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andrew McMichael v. Commonwealth of Kentucky
Court of Appeals of Kentucky, 2021
Crowley v. Costa
924 F. Supp. 2d 402 (D. Connecticut, 2013)
In Re Stone & Webster, Inc.
279 B.R. 748 (D. Delaware, 2002)
State v. Sossei
144 A.D.2d 888 (Appellate Division of the Supreme Court of New York, 1988)
Freeport Sulphur Company v. S/S Hermosa
368 F. Supp. 952 (E.D. Louisiana, 1973)
American Oil Company v. M/T LACON
398 F. Supp. 1181 (S.D. Georgia, 1973)
Elaine Jones v. Griffith
480 F.2d 11 (Fifth Circuit, 1973)
Canal Barge Co. v. Griffith
480 F.2d 11 (Fifth Circuit, 1973)
Hinfin Realty Corporation v. M/V POLING BROS. 7
348 F. Supp. 1391 (E.D. New York, 1972)
State Of Oregon v. Tug Go-Getter
468 F.2d 1270 (Ninth Circuit, 1972)
Oregon v. Tug Go-Getter
468 F.2d 1270 (Ninth Circuit, 1972)
Pennsylvania Power & Light Co. v. Decker
1 Pa. D. & C.3d 303 (Lehigh County Court of Common Pleas, 1966)
Seaboard Air Line Railroad v. Marine Industries, Inc.
237 F. Supp. 10 (E.D. South Carolina, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
211 F. Supp. 702, 1962 U.S. Dist. LEXIS 3382, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brooklyn-waterfront-terminal-corp-v-international-terminal-operating-co-nysd-1962.