In re Public Service Electric

748 A.2d 1161, 330 N.J. Super. 65, 2000 N.J. Super. LEXIS 150
CourtNew Jersey Superior Court Appellate Division
DecidedApril 13, 2000
StatusPublished
Cited by2 cases

This text of 748 A.2d 1161 (In re Public Service Electric) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Public Service Electric, 748 A.2d 1161, 330 N.J. Super. 65, 2000 N.J. Super. LEXIS 150 (N.J. Ct. App. 2000).

Opinion

The opinion of the court was delivered by

KING, P.J.A.D.

TABLE OF CONTENTS

I INTRODUCTION...................................82

II THE HISTORY.....................................83

III CO-STEEL’S CONTRACT IMPAIRMENT AND RELATED CLAIMS...............................92

IV PROCEDURAL DUE PROCESS CONCERNS........104

TV A THE BPU DID NOT ERR IN REFUSING TO REOPEN THE RECORD AFTER PASSAGE OF THE ACT...................107

IV B THE BPU DID NOT ERR IN REFUSING TO REOPEN THE RECORD AFTER NEW ISSUES ALLEGEDLY WERE RAISED IN STIPULATION I...............Ill

[81]*81IV B1 THE IMMEDIATE TRANSFER OF GENERATING FACILITIES TO AN UNREGULATED AFFILIATE, GENCO..............112

IV B 2 A FOUR-YEAR TRANSITION AND RATE REDUCTION PERIOD ............................113

IV B 3 THE USE OF DEFERRED ACCOUNTING TO ACHIEVE STATUTORY RATE REDUCTIONS ...........................113

IV C THE BPU DID NOT INAPPROPRIATELY RELY ON A DOCUMENT OUTSIDE THE RECORD............................114

IV D THE BPU NEED NOT HAVE CONDUCTED HEARINGS ON SECURITIZATION. ....................................117

IV E THE BPU PROPERLY DENIED NJBUS INTERVENTION IN THE SECURITI-ZATION PROCEEDINGS. .................121

IV F CONCLUSION OF TV........................122
V FACT-FINDING DISPUTES........................122

VA THE VALUATION OF GENERATION-RELATED ASSETS FOR THE GENCO TRANSFER REFLECTS FULL MARKET VALUE OF THE ASSETS. ............123

VB THE SHOPPING CREDITS..................133

V C PSE & G’s USE OF EXCESS DEPRECIATION RESERVE FUNDS.................136

VD PSE & G’s USE OF DEFERRED ACCOUNTING ...............................138

VE THE BPU DID NOT ALLOW PSE & G TO SECURITIZE MORE THAN THE 75% OF STRANDED COSTS ALLOWED UNDER THE ACT.........................140

VF PSE & G HAS PASSED THROUGH TO CUSTOMERS ALL SAVINGS FROM ECURITIZATION.........................143

TABLE OF ACRONYMS

BGS Basic Generation Service

BSCRO Bondable Stranded Cost Rate Order

[82]*82EHEP Experimental Hourly Energy Pricing tariff

HTS High Tension Service

LEAC Levelized Energy Adjustment Clause

MTC Market Transition Charge

NTC Nonutility Generator Transition Charge

NUG Nonutility generator

PJM Pennsylvania-New Jersey-Maryland power pool

SBC Societal Benefits Charge

TBC Transition Bond Charge

I

INTRODUCTION

This is a consolidated appeal from two decisions of respondent the Board of Public Utilities (BPU): (1) its Final Decision and Order on the rate unbundling, stranded costs, and restructuring filings of respondent Public Service Electric and Gas Company (PSE & G), and (2) its bondable stranded cost rate order (BSCRO) on PSE & G’s petition to finance, or securitize, its recovery-eligible stranded costs.

Co-Steel Raritan (Co-Steel), one of PSE & G’s largest commercial customers, appeals from that portion of the Final Decision which ordered payment of stranded cost charges mandated by the Electric Discount and Energy Competition Act of 1999, N.J.S.A. 48:3-49 to -98, L. 1999, c. 23, effective February 9, 1999 (the Act), despite Co-Steel’s special contract with PSE & G. The Division of the Ratepayer Advocate (RA) and New Jersey Business Users (NJBUS), a group of large industrial and commercial customers, appeal from specific findings in the Final Decision and on procedural due process grounds, contending that they were denied due process when the BPU refused to reopen the record after passage of the Act and BPU decided the securitization issue without holding hearings, among other procedural irregularities. The RA is also a respondent on the issues raised by Co-Steel. Briefs have been filed on behalf of six intervenors in the proceedings before the agency: Jersey Central Power & Light Company (GPU), [83]*83Rockland Electric Company (RECO), New Jersey Commercial Users (NJCU), Enron Energy Services (Enron), Independent Energy Producers of New Jersey (IEPNJ), and Tosco Refinery Company (Tosco).

The administrative proceedings leading up to these decisions were unusual in many ways: hearings on the unbundling, stranded costs, and restructuring issues were held before an administrative law judge before the Act was passed; the securitization issue invited comments from interested parties but no hearings. Quasi-legislative public hearings were held on deregulation three years before the Act actually was introduced in the Legislature. The BPU’s Final Decision relied heavily on a negotiated agreement between PSE & G and seven intervenors which had an opportunity to comment on the agreement. Despite the unusual procedure, however, we conclude that all parties had ample opportunity to be heard on all aspects of both decisions. We find no denial of due process and no fundamental unfairness. We affirm.

To assist the reader in understanding the terms and acronyms we use we provide a Table of Acronyms.

II

THE HISTORY

From the early 1900s until the Act was passed in 1999, the electric power industry had been composed of vertically-integrated public utility companies. Each company owned power generation plants, plus transmission, distribution, and customer service facilities. The companies had virtual monopolies over their geographically-defined service territories. The charges for all services power supply, electric transmission and distribution, and such customer services as connects and disconnects, metering, billing, and account administration were “bundled” and billed at a single price.

[84]*84In the late 1970s, electricity rates increased dramatically; by 1985 New Jersey consumers were paying about 50% above the national average for electricity. This situation persisted into the late 1990s. Although such factors as a higher cost of living, higher energy taxes, tighter environmental standards, and a lack of indigenous energy supplies played a part in this rise in rates, a major factor was the high average power production costs in New Jersey. Power production costs were high due to expensive utility-owned nuclear power plants and expensive power purchase agreements with nonutility generators (NUGs).

Competition began in the production aspect of the electric power industry after Congress enacted the Public Utility Regulatory Policies Act of 1978, 16 U.S.C.A. §§ 2601-2645 (PURPA), which provided incentives to develop nonutility electricity generation. Because of various federal initiatives, by 1997 there were a growing number of power producers and suppliers offering power for sale regionally at competitive prices.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NEW JERSEY EDUC. ASS'N v. State
989 A.2d 282 (New Jersey Superior Court App Division, 2010)
In Re Pse&g Co.'s Rate Unbundling
748 A.2d 1161 (New Jersey Superior Court App Division, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
748 A.2d 1161, 330 N.J. Super. 65, 2000 N.J. Super. LEXIS 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-public-service-electric-njsuperctappdiv-2000.