In Re Operation of the Missouri River System Litigation

305 F. Supp. 2d 1096, 2004 U.S. Dist. LEXIS 2832, 2004 WL 350914
CourtDistrict Court, D. Minnesota
DecidedFebruary 26, 2004
Docket03-MD-1555 (PAM)
StatusPublished
Cited by4 cases

This text of 305 F. Supp. 2d 1096 (In Re Operation of the Missouri River System Litigation) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Operation of the Missouri River System Litigation, 305 F. Supp. 2d 1096, 2004 U.S. Dist. LEXIS 2832, 2004 WL 350914 (mnd 2004).

Opinion

MEMORANDUM AND ORDER

MAGNUSON, District Judge.

This matter is before the Court on a Motion for Amendment of the October 1, 2003, Scheduling Order filed by Defendants U.S. Army Corps of Engineers (“Corps”) and the Fish and Wildlife Service (“FWS”).

In 1944, Congress enacted the Flood Control Act (“FCA”), which provided for the management of the Missouri River and its reservoirs. Pub.L. No. 78-534, 58 Stat. 887 (1944). The Act delegated the responsibility of managing the river basin to the Corps. The core function of the FCA was to control flooding and maintain downstream navigation. ETSI Pipeline Project v. Missouri, 484 U.S. 495, 512, 108 S.Ct. 805, 98 L.Ed.2d 898 (1988); see also H.R. Doc. No. 475, 78th Cong., 2d Sess. 28-29 (1944); S. Doc. No. 247, 78th Cong.2d Sess. 3 (1944). Because the FCA only identified the broad goals for the river’s operation, a more detailed plan was promulgated to aid the Corps in river management. The Missouri River Main Stem Reservoir System Reservoir Regulation Manual (“Master Manual”) specifically explains how the Corps must conduct its operation of the Missouri River. The first Master Manual was developed more than 40 years ago and it has been revised three times, in 1973, 1975, and 1979. The Corps, on its own initiative, began revising the 1979 Manual in the late 1980s. For fifteen years, the various interests in the Missouri River basin have eagerly awaited the Corps’ completion of its revisions to the Master Manual. Despite repeated promises that a new Master Manual is forthcoming, the Corps has continually failed to complete it.

Revising and issuing a new Master Manual is a lengthy process that requires the Corps to comply with significant regulations and procedures. In particular, the Corps must work closely with various agencies so that all river interests are adequately considered. Prior to the revision of a new Master Manual, the Corps must issue a Final Environmental Impact Statement (“EIS”). The Corps claims that it has been unable to issue a new Master Manual because it has been unable to issue a Final EIS and conduct a review period. Now, in its Motion to the Court, the Corps insists that a Final EIS is completed, but because it is so “voluminous,” it is impossible to publish it before February 27, 2004. As a result, the 30-day review period will begin on March 5, 2004 and end on April 5, 2004. Within 10 days of the completion of this review period, the Corps contends that it will be able to issue a new Master Manual. However, in a footnote, the Corps claims to “reserve the right” to extend time again. (Defs.’ Mem. in Supp. of Mot. to Amend at 3.)

Plaintiffs North Dakota and American Rivers and Environmental Defense, et al. (“American Rivers”) outline, with reference to the administrative record, many of the Corps’ illusory assurances to revise the Master Manual over the last fifteen years. (See North Dakota Mem. in Supp. of Partial Summ. J. at 4-6; American Rivers Opp’n. Mem. to Federal Defs.’ Summ. J. at 3 — 4.) Because the Corps fails to address any of the substantive arguments set forth in any of the Motions, the Court is inclined to accept these factual assertions.

In November 1989, Assistant Secretary of the Army Robert W. Page “directed the Corps of Engineers to undertake a thorough review of the Missouri River main stem Reservoir Operating Plan” and to update the plan to “reflect current condi *1098 tions in the basin.” (U.S. Army Corps of Engineers, N.W. Division, Missouri River Master Manual Review and Update Administrative Record (“USACE Admin. R.”) Ex. 11.) Phase One of this review process was to be finished by May 1, 1990, and Phase II, which included the completion of a Final EIS new Master Manual, was to be finished by October 31, 1991. {Id. Ex. 15.) In September 1990, the anticipated completion of Phase II was pushed back to October 1, 1992. {Id. Ex. 106.) In February 1991, the completion date was modified to “the end of 1992 rather than mid-1992.” {Id. Ex. 156.) From November 1992 until April 1993, the completion date was delayed at least three different times. {Id. Exs. 423, 472, and 475.) In mid-April 1993, the Corps projected Master Manual completion to late 1995. {Id. Ex. 475 at 8939.) In February 1996, the Corps delayed the new Master Manual to 1998. {Id. Ex. 884.) In July 1996, the Corps projected completion for 2000. {Id. Ex. 894.) In March 1998, this deadline was extended to 2002. {Id. Ex. 908.) In October 1999, the new Master Manual was delayed to March 2003. {Id. Ex. 1032.) In July 2003, the Corps again delayed completion to spring 2004. {Id. Ex. 1785.) Presently, the Corps represents to the Court that is unable to meet its previously anticipated March 2004 deadline.

These continuous delays in the administrative record are not an exclusive listing of the Corps’ false assurances to revise the Master Manual. In addition, the Corps has assured numerous courts of its continued intention to issue a new Master Manual. For example, the Eighth Circuit Court of Appeals determined that because a new Master Manual was forthcoming, the legal issues before it were moot: “[w]e thus do not believe that the possibility that the Upper Basin states will be challenging future Corps actions taken pursuant to the 1979 Manual — especially in view of the fact that the Manual is being revised — rises to the level of a concrete possibility [to be capable of repetition but evading review].” South Dakota v. Hazen, 914 F.2d 147, 151(8th Cir.1990). In 1993, the Corps represented to the Montana District Court its intention to issue a new Master Manual, and as a result, that court dismissed the action as moot: “there is a reasonable expectation that the Corps’ revised plan will reflect contemporary uses and needs of the Missouri River Basin.” South Dakota v. Bomhoft, File No. 91-26, slip op. at 3 (D.Mont. Feb. 3, 1993). With respect to the cases involved in this litigation, the Corps has consistently maintained that a revised Master Manual is forthcoming. See South Dakota v. Ubbelohde, 330 F.3d 1014, 1020 (8th Cir.2003) (“the Corps assures this Court that the revisions should be completed quite soon”); American Rivers v. U.S. Army Corps of Eng’rs, 271 F.Supp.2d 230, 239 (D.D.C.2003) (“after more than ten years of work and multiple assurances to various courts that the latest revision would be soon completed, the Corps has not yet completed its revision” (internal citations omitted)). At the status conference in September 2003, the Corps represented to this Court its intentions to issue a new Master Manual by the end of 2003. Even now, the Corps’ consolidated Motion for Summary Judgment on all of the parties’ claims asserts that all of the pending claims on the existing factual circumstances are moot because a revised Master Manual is forthcoming. However, the Corps now presents to this Court its inability to comply with the October 1, 2003, Scheduling Order, and further submits that it “reserves the right” to request an additional extension of time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NOLAN v. United States
Federal Claims, 2024
Ideker Farms, Inc. v. United States
71 F.4th 964 (Federal Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
305 F. Supp. 2d 1096, 2004 U.S. Dist. LEXIS 2832, 2004 WL 350914, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-operation-of-the-missouri-river-system-litigation-mnd-2004.