In Re Northern States Power Co.

775 N.W.2d 652, 2009 Minn. App. LEXIS 208, 2009 WL 4251125
CourtCourt of Appeals of Minnesota
DecidedDecember 1, 2009
DocketA09-364
StatusPublished
Cited by2 cases

This text of 775 N.W.2d 652 (In Re Northern States Power Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Northern States Power Co., 775 N.W.2d 652, 2009 Minn. App. LEXIS 208, 2009 WL 4251125 (Mich. Ct. App. 2009).

Opinion

OPINION

HALBROOKS, Judge.

Relator Southern Minnesota Municipal Power Agency (SMMPA), a municipal utility, challenges respondent Minnesota Public Utilities Commission’s (MPUC) approval of a mercury-emissions-reduction plan for Sherburne County Generating Facility Unit 3 (Sherco 3) as exceeding MPUC’s jurisdiction. Alternatively, SMMPA challenges MPUC’s approval of the plan as arbitrary or capricious. Because we conclude that MPUC acted within its legislatively granted authority and did not act arbitrarily or capriciously, we affirm.

FACTS

The Minnesota Mercury Emissions Reduction Act states:

[A] public utility that owns a dry scrubbed unit at a qualifying facility shall develop and submit to the agency and the commission a plan for mercury emissions reduction at each such unit. At each dry scrubbed unit owned and operated by the utility, the plan must propose to employ the available technology for mercury removal that is most likely to result in the removal of at least 90 percent of the mercury emitted from the unit.

Minn.Stat. § 216B.682, subd. 1(a). The “agency” refers to the Minnesota Pollution Control Agency (MPCA), and the “commission” refers to MPUC. Minn.Stat. §§ 216B.02, subd. la, .68, subd. 2 (2008). After a plan is submitted, MPCA “shall evaluate a utility’s mercury emissions-reduction plan[ ] ... and submit its evaluation to [MPUC] within 180 days.” Minn. Stat. § 216B.684.

Following the MPCA evaluation, MPUC “shall review and evaluate a utility’s mercury emissions-reduction plant ]” considering “the environmental and public health benefits, the agency’s assessment of technical feasibility, competitiveness of customer rates, and cost-effectiveness of the utility’s proposed mercury-control initiatives in *655 light of the [MPCA’s] report under section 216B.684.” Minn.Stat. § 216B.685, subd. 1. Then, “[wjithin 180 days of receiving the agency’s report on a utility’s plan ..., the commission shall order the implementation of [the plan], unless the commission determines that the plan as proposed fails to provide for increased environmental and health benefits or would impose excessive costs on the utility’s customers.” Id., subd. 2(a).

Respondent Northern States Power Company d/b/a Xcel Energy (Xcel) submitted its “Mercury Control Plan for Sherco Unit 3” to MPCA and MPUC in accordance with the act. Sherco 3 is an electric power plant co-owned by SMMPA (41% ownership interest) and Xcel (59% ownership interest). Xcel is the sole operator of Sherco 3, and the parties’ co-ownership is governed by agreement. Xcel stated in its plan that it was “filing this Plan on its own behalf’ and that “[w]e are currently discussing cost sharing options for the project with SMMPA.” In the plan, Xcel estimated the cost of implementation at $87 million by 2020, which corresponds to a rate increase in 2010 of $.10 per month per residential customer, assuming no cost sharing with SMMPA. MPCA recommended approval of Xcel’s plan to MPUC. During MPUC’s subsequent review and evaluation of the plan, SMMPA filed comments, requesting “that the Commission delay taking action in this docket until after SMMPA and Xcel resolve the issues associated with Xcel’s Plan. In the alternative, if the Commission approves the Plan, the Commission should require that Xcel alone bear the costs and risks of the Plan.” SMMPA argued to MPUC that the act did not apply to it, as a municipal utility, and “therefore SMMPA’s property interests cannot be impacted by [the act] without SMMPA’s consent.” SMMPA also argued that Xcel’s plan failed to address indirect costs. Finally, SMMPA stated that “[a]d-ministrative efficiency compels the Commission to wait until it has all pertinent information, including Xcel’s emissions reduction rider, before it makes any decisions regarding the Plan.”

MPUC held a hearing to address Xcel’s plan on October 23, 2008. At the hearing, SMMPA raised the arguments that were contained in its comments. In its order, MPUC found that SMMPA is not subject to the act, but that Sherco 3 is subject to the act. MPUC determined that “[t]he obligations arising from [Xcel’s] ownership and operation are not eliminated by the partial ownership interest of a [municipal utility].” MPUC further stated “that the proposed plan filed by Xcel meets the requirements of the statute, promises significant environmental and health benefits, is technically feasible, is cost-effective, and will not impose excessive costs on Xcel’s customers.” MPUC clarified that its “decision neither includes nor implies any determination on cost recovery methods or allocations, which need not be decided today.”

SMMPA requested reconsideration by MPUC, which was denied. SMMPA brought this certiorari appeal, arguing that MPUC exceeded its statutory authority by exercising jurisdiction over SMMPA through the approval of Xcel’s plan for Sherco 3 and that MPUC acted arbitrarily or capriciously in its approval of Xcel’s plan by failing to consider rate impact as required by the act.

ISSUES

I. Did MPUC exceed its jurisdiction by approving Xcel’s mercury-reduction plan?

II. Was MPUC’s approval and order for implementation of Xcel’s mercury-reduction plan arbitrary or capricious?

ANALYSIS

MPUC decisions are subject to appeal under the Administrative Procedure Act. *656 Minn.Stat. § 216B.52, subd. 1 (2008). The Administrative Procedure Act states that a reviewing court may reverse an agency’s decision if it concludes that the agency’s actions were:

(a) in violation of constitutional provisions; or
(b) in excess of the statutory authority or jurisdiction of the agency; or
(c) made upon unlawful procedure; or
(d) affected by other error of law; or
(e) unsupported by substantial evidence in view of the entire record as submitted; or
(f) arbitrary or capricious.

Minn.Stat. § 14.69 (2008). Under this standard, SMMPA appeals MPUC’s decision on the grounds that it exceeds MPUC’s jurisdiction and is arbitrary or capricious.

I. Did MPUC exceed its jurisdiction by approving Xcel’s mercury-reduction plan?

SMMPA asserts that MPUC exceeded its jurisdiction by approving Xcel’s “overly broad” plan, thereby regulating SMMPA. SMMPA argues that “[ajbsent SMMPA’s consent, Xcel’s plan should have been limited to Xcel’s 59% ownership interest.”

Whether an agency has jurisdiction over a matter is a legal question, and thus a reviewing court need not defer to “agency expertise.” Frost-Benco Elec. Ass’n v. Minn. Pub. Utils. Comm’n, 358 N.W.2d 639, 642 (Minn.1984). But

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
775 N.W.2d 652, 2009 Minn. App. LEXIS 208, 2009 WL 4251125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-northern-states-power-co-minnctapp-2009.