In Re an Investigation Into the Commission's Jurisdiction Over the Hutchinson's Intrastate Natural Gas Pipeline

707 N.W.2d 223, 2005 Minn. App. LEXIS 791, 2005 WL 3527134
CourtCourt of Appeals of Minnesota
DecidedDecember 27, 2005
DocketA04-2342, A04-2414
StatusPublished
Cited by2 cases

This text of 707 N.W.2d 223 (In Re an Investigation Into the Commission's Jurisdiction Over the Hutchinson's Intrastate Natural Gas Pipeline) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re an Investigation Into the Commission's Jurisdiction Over the Hutchinson's Intrastate Natural Gas Pipeline, 707 N.W.2d 223, 2005 Minn. App. LEXIS 791, 2005 WL 3527134 (Mich. Ct. App. 2005).

Opinion

OPINION

HALBROOKS, Judge.

Relators Hutchinson Utilities Commission (HUC), a municipal utility, and Minnesota Municipal Utilities Association (MMUA), a nonprofit corporation that provides services and assistance to Minnesota cities engaged in utility enterprises, challenge the exercise of jurisdiction by respondent Minnesota Public Utilities Commission (MPUC) over a pipeline owned by the City of Hutchinson on the ground that it exceeds the statutory mandate of the MPUC. Alternatively, relators challenge the MPUC’s exercise of jurisdiction as arbitrary and capricious. Because we find that the MPUC exceeded its statutory mandate, we reverse without reaching re-lators’ alternative argument.

FACTS

This case concerns the regulation of an 89-mile underground natural-gas pipeline that runs from Trimont to Hutchinson and transports natural gas to the City of New Ulm, New Ulm’s electric-generating facilities, the City of Hutchinson, and HUC’s electric-generating facilities. Beginning in 1960, HUC contracted with Northern Natural Gas Company (Northern) for its natural-gas supply. But in 2001, Northern offered HUC insufficient natural-gas capacity. Because of the energy shortfall, HUC decided to build its own pipeline. Construction of a natural-gas pipeline involves oversight by the MPUC. See Minn. Stat. § 216B.243, subd. 2 (2004) (requiring that a certificate of need be filed with the MPUC before siting or construction of any “large energy facility”).

HUC applied for and was granted a Certificate of Need from the MPUC on December 13, 2002. 1 At that time, the *225 MPUC concluded that it need not decide whether the pipeline would be subject to regulation under Minn.Stat. § 216B.045 (2004).

On January 28, 2004, Northern, now a competitor of HUC, submitted a letter to the MPUC requesting that the commission address the jurisdictional issues deferred in the certificate-of-need decision and investigate to determine whether HUC’s pipeline services complied with Minn.Stat. § 216B.045. 2 On March 23, 2004, the MPUC held an initial hearing but ultimately deferred the matter and ordered additional briefing.

The next hearing occurred on August 19, 2004. At that time, the MPUC considered whether it had jurisdiction and, if so, whether it should regulate HUC’s pipeline under section 216B.045. In an order issued September 15, 2004, the MPUC determined that the HUC’s pipeline meets the statutory definition of an intrastate natural-gas pipeline under Minn.Stat. § 216B.045, subd. 1, and that MPUC had jurisdiction over HUC’s pipeline.

HUC, MMUA, and the City of New Ulm petitioned the MPUC for reconsideration, but the MPUC denied reconsideration. HUC and MMUA thereafter filed petitions for writ of certiorari with this court, seeking review of the MPUC’s decision.

ISSUE

Did the MPUC exceed its statutory mandate by exercising jurisdiction over HUC’s pipeline?

ANALYSIS

Whether an agency has jurisdiction over a matter is a legal question, and thus a reviewing court need not defer to agency expertise on the issue. Frost-Benco Elec. Ass’n v. Minn. Pub. Utils. Comm’n, 358 N.W.2d 639, 642 (Minn.1984). Statutory construction is a question of law, which we review de novo. Brookfield Trade Ctr., Inc. v. County of Ramsey, 584 N.W.2d 390, 393 (Minn.1998).

Minn.Stat. § 14.69 (2004) outlines the scope of judicial review of an agency decision:

In a judicial review under sections 14.63 to 14.68, the court may affirm the decision of the agency or remand the case for further proceedings; or it may reverse or modify the decision if the substantial rights of the petitioners may have been prejudiced because the administrative finding, inferences, conclusion, or decisions are:
(a) in violation of constitutional provisions; or
(b) in excess of the statutory authority or jurisdiction of the agency; or
(c) made upon unlawful procedure; or
(d) affected by other error of law; or
(e) unsupported by substantial evidence in view of the entire record as submitted; or
(f) arbitrary and capricious.

On appeal from an agency decision, the party seeking review bears the burden of proving that the agency’s conclusions violate one or more provisions of Minn.Stat. § 14.69. Markwardt v. State, Water Resources Bd., 254 N.W.2d 371, 374 (Minn. *226 1977). Minn.Stat. § 216B.52, snbd. 1 (2004), provides that an appeal from a decision and order of the MPUC may be commenced according to the Administrative Procedure Act.

As a creature of statute, the MPUC enjoys only the authority granted to it by the legislature. Minnegasco v. Minn. Pub. Utils. Comm’n, 549 N.W.2d 904, 907 (Minn.1996); Frost-Benco Elec. Ass'n 358 N.W.2d at 642; see also Great N. Ry. v. Pub. Serv. Comm’n, 284 Minn. 217, 220-21, 169 N.W.2d 732, 735 (1969) (applying same principle in case involving the interstate commerce commission). That authority may be either express or implied. “While express statutory authority need not be given a cramped redding, any enlargement of express powers by implication must be fairly drawn and fairly evident from the agency objectives and powers expressly given by the legislature.” Peoples Natural Gas Co. v. Pub. Utils. Comm’n, 369 N.W.2d 530, 534 (Minn.1985) (holding that the commission lacked express or implied authority to enforce its own orders by ordering a customer refund; noting that other enforcement tools were available in the statutes).

Here, HUC and MMUA argue that the MPUC exceeded its statutory authority when it asserted jurisdiction over HUC’s pipeline. MPUC asserted jurisdiction pursuant to MinmStat. § 216B.045, subd. 3 (2004), which provides: “Every owner or operator of an intrastate pipeline shall offer intrastate pipeline transportation services by contract on an open access, nondiscriminatory basis.”

MPUC noted in its order that jurisdiction was proper because (1) the pipeline meets the definition of an “intrastate pipeline” under the statute; (2) the statute gives jurisdiction over “every owner or operator” and HUC is an “owner or operator” of a pipeline; (3) the only owners excluded from regulation under Minn.Stat.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Baxter v. City of Brainerd
932 N.W.2d 477 (Court of Appeals of Minnesota, 2019)
In Re Northern States Power Co.
775 N.W.2d 652 (Court of Appeals of Minnesota, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
707 N.W.2d 223, 2005 Minn. App. LEXIS 791, 2005 WL 3527134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-an-investigation-into-the-commissions-jurisdiction-over-the-minnctapp-2005.