In re: Cube Yadkin Generation

CourtCourt of Appeals of North Carolina
DecidedDecember 17, 2019
Docket18-1203
StatusPublished

This text of In re: Cube Yadkin Generation (In re: Cube Yadkin Generation) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re: Cube Yadkin Generation, (N.C. Ct. App. 2019).

Opinion

IN THE COURT OF APPEALS OF NORTH CAROLINA

No. COA18-1203

Filed: 17 December 2019

North Carolina Utilities Commission, Nos. E-2, Sub 1177; E-7, Sub 1172

IN THE MATTER OF CUBE YADKIN GENERATION, LLC, Complainant

v.

DUKE ENERGY PROGRESS, LLC, Respondent

Appeal by Complainant from Order entered 16 July 2018 by the North

Carolina Utilities Commission. Heard in the Court of Appeals 8 August 2019.

Kilpatrick Townsend & Stockton LLP, by Joseph S. Dowdy, Benjamin L. Snowden, and Phillip A. Harris, Jr., for complainant-appellant.

The Allen Law Offices, by Dwight W. Allen, Britton H. Allen, and Brady W. Allen, and Kendrick Fentress, Associate General Counsel of Duke Energy Corporation, for respondent-appellee.

HAMPSON, Judge.

Factual and Procedural Background

Cube Yadkin Generation, LLC (Cube) is a limited liability company that

acquires, develops, and modernizes hydroelectric facilities. The present dispute

arises out of Cube’s purchase of hydroelectric facilities (the Yadkin Project)1 from

Alcoa Power Generating, Inc. (Alcoa) on 1 February 2017 and Cube’s efforts to sell

1 The Yadkin Project consists of four hydroelectric facilities; however, the parties agree only three of these facilities are in dispute. Therefore, for ease of reading, the Yadkin Project, as used in this opinion, refers only to the three disputed facilities. CUBE YADKIN GENERATION, LLC V. DUKE ENERGY PROGRESS, LLC

Opinion of the Court

electrical power generated by these facilities to Duke Energy Progress, LLC (Duke).

In this appeal, Cube appeals from the Order Granting Motion to Dismiss (Order)

entered on 16 July 2018 by the North Carolina Utilities Commission (Commission),

dismissing Cube’s Verified Complaint, Request for Declaratory Ruling, and Request

for Arbitration (Complaint) against Duke. The Record tends to show the following:

In 1978, Congress enacted the Public Utility Regulatory Policies Act of 1978

(PURPA), which sought, inter alia, to encourage a national policy of energy

conservation. See FERC v. Mississippi, 456 U.S. 742, 745, 72 L. Ed. 2d 532, 537-38

(1982). “Pursuant to section 210 of [PURPA], regulations of the Federal Energy

Regulatory Commission (FERC) promulgated thereunder, and implementation

mechanisms of the states, electric utilities are required to purchase power produced

by qualifying cogeneration and small power production facilities [(collectively,

Qualifying Facilities)] and are required to pay their ‘avoided costs’ for the power

unless the rate is negotiated.” State ex rel. Utilities Comm. v. N.C. Power, 338 N.C.

412, 416, 450 S.E.2d 896, 898 (1994); see also 16 U.S.C.A. § 824a-3(d) (West 2010)

(defining avoided cost as “the cost to the electric utility of the electric energy which,

but for the purchase from such [Qualifying Facilities], such utility would generate or

purchase from another source”). Under FERC regulations, a Qualifying Facility can

sell its power pursuant to a Legally Enforceable Obligation and can choose to fix the

-2- CUBE YADKIN GENERATION, LLC V. DUKE ENERGY PROGRESS, LLC

price “at the time the [Legally Enforceable Obligation] is incurred” or at the moment

of delivery. 18 C.F.R. § 292.304(d)(2)(i)-(ii) (2019).

Prior to 2016, the Commission applied a two-part test for determining the

establishment of a Legally Enforceable Obligation. See N.C. Utils. Comm’n, Order

Establishing Standard Rates and Contract Terms for Qualifying Facilities, Docket

No. E-100, Sub 140, at *52 (Dec. 17, 2015) [hereinafter Sub 140 Order]. The

Commission required a Qualifying Facility to (1) obtain a Certificate of Public

Convenience and Necessity (CPCN)2 and (2) indicate to the utility that it was “seeking

to commit itself to sell its output[.]” N.C. Utils. Comm’n, Order Establishing

Standard Rates and Contract Terms for Qualifying Facilities, Docket No. E-100, Sub

136, at *37 (Feb. 21, 2014) [hereinafter Sub 136 Order]; see also N.C. Gen. Stat. § 62-

110.1(a) (2017) (requiring a CPCN from the Commission before “construction of any

. . . facility for the generation of electricity”). However, because this second prong was

vague and difficult to establish, the Commission later created the Notice of

Commitment (NOC) Form, demonstrating a Qualifying Facility’s commitment to sell

its output. Sub 140 Order, at *51-52. Effective 26 January 2016, the Commission

thus revised its Legally-Enforceable-Obligation test, ordering that for a Qualifying

Facility to establish a Legally Enforceable Obligation, the developer of the Qualifying

2 If the Qualifying Facility was under 2 megawatts, the Qualifying Facility filed a Report of Proposed Construction instead of a CPCN; however, none of Cube’s Qualifying Facilities were under 2 megawatts.

-3- CUBE YADKIN GENERATION, LLC V. DUKE ENERGY PROGRESS, LLC

Facility was required to: “(1) have self-certified with the FERC as a [Qualifying

Facility]; (2) have made a commitment to sell the facility’s output to a utility pursuant

to PURPA via the use of [the NOC Form;] and (3) have received a CPCN for the

construction of the facility.” Sub 140 Order, at *52. Indeed, relevant to this appeal,

Section Three of the NOC Form specifically requires a Qualifying Facility to indicate

whether it has applied for or received a CPCN from the Commission.

According to Cube’s Complaint, the Yadkin Project facilities have been in

operation since at least 1958. In 2000, Alcoa acquired the Yadkin Project, and on 22

September 2016, FERC issued a new long-term license to Alcoa for the Yadkin

Project, allowing for the operation and maintenance of the Yadkin Project until 31

March 2055. On 30 June 2016, Cube signed a contract with Alcoa to acquire the

Yadkin Project, and approximately a month later, Cube submitted an application to

FERC seeking approval of the transfer of Alcoa’s Yadkin Project license. FERC

approved the transfer on 13 December 2016. Cube “formally consummated its

agreement to purchase the Yadkin Project” on 1 February 2017. Prior to this transfer,

Alcoa self-certified the Yadkin Project as Qualifying Facilities by filing Form 566s

with FERC on 28 September 2016, and on 16 March 2017, Cube filed Form 566s with

FERC, self-recertifying the Yadkin Project as Qualifying Facilities.

In March 2016, Cube, as part of its due diligence process, contacted Duke to

introduce itself and begin inquiries about entering into a Power Purchase Agreement

-4- CUBE YADKIN GENERATION, LLC V. DUKE ENERGY PROGRESS, LLC

(PPA) with Duke. The parties subsequently held an in-person meeting to discuss

entering into “a potential long-term PPA for the [Yadkin Project Qualifying

Facilities].” Cube and Duke continued discussions, and by letter dated 21 September

2016, Duke stated:

You [(a representative for Cube)] informed me that [Cube] does not currently own or operate the Yadkin [Project] system, but anticipates that it will close on the transaction to own and operate the facilities around November 1, 2016. As I communicated to you previously, Duke does not have any current needs for energy or capacity . . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Energy Regulatory Commission v. Mississippi
456 U.S. 742 (Supreme Court, 1982)
State Ex Rel. Utilities Commission v. Carolina Utility Customers Ass'n Inc.
500 S.E.2d 693 (Supreme Court of North Carolina, 1998)
White v. White
252 S.E.2d 698 (Supreme Court of North Carolina, 1979)
Sutton v. Duke
176 S.E.2d 161 (Supreme Court of North Carolina, 1970)
Bledsole v. Johnson
579 S.E.2d 379 (Supreme Court of North Carolina, 2003)
Stanback v. Stanback
254 S.E.2d 611 (Supreme Court of North Carolina, 1979)
Duncan v. Duncan
754 S.E.2d 451 (Court of Appeals of North Carolina, 2014)
Jackson/Hill Aviation, Inc. v. Town of Ocean Isle Beach
796 S.E.2d 120 (Court of Appeals of North Carolina, 2017)
State ex rel. Utilities Commission v. Village of Pinehurst
415 S.E.2d 199 (Supreme Court of North Carolina, 1992)
State ex rel. Utilities Commission v. North Carolina Power
450 S.E.2d 896 (Supreme Court of North Carolina, 1994)
State ex rel. Utilities Commission v. Village of Pinehurst
393 S.E.2d 111 (Court of Appeals of North Carolina, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
In re: Cube Yadkin Generation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-cube-yadkin-generation-ncctapp-2019.