In re Complaint of Allied Erecting & Dismantling Co., Inc. v. Ohio Edison Co. (Slip Opinion)

2021 Ohio 2300, 180 N.E.3d 1063, 165 Ohio St. 3d 510
CourtOhio Supreme Court
DecidedJuly 8, 2021
Docket2014-0008
StatusPublished

This text of 2021 Ohio 2300 (In re Complaint of Allied Erecting & Dismantling Co., Inc. v. Ohio Edison Co. (Slip Opinion)) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Complaint of Allied Erecting & Dismantling Co., Inc. v. Ohio Edison Co. (Slip Opinion), 2021 Ohio 2300, 180 N.E.3d 1063, 165 Ohio St. 3d 510 (Ohio 2021).

Opinion

[Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In re Complaint of Allied Erecting & Dismantling Co., Inc. v. Ohio Edison Co., Slip Opinion No. 2021-Ohio-2300.]

NOTICE This slip opinion is subject to formal revision before it is published in an advance sheet of the Ohio Official Reports. Readers are requested to promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65 South Front Street, Columbus, Ohio 43215, of any typographical or other formal errors in the opinion, in order that corrections may be made before the opinion is published.

SLIP OPINION NO. 2021-OHIO-2300 IN RE COMPLAINT OF ALLIED ERECTING & DISMANTLING COMPANY, INC., APPELLANT, v. OHIO EDISON COMPANY, INTERVENING APPELLEE; PUBLIC UTILITIES COMMISSION, APPELLEE. [Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In re Complaint of Allied Erecting & Dismantling Co., Inc. v. Ohio Edison Co., Slip Opinion No. 2021-Ohio-2300.] Public Utilities—An appellant bears the burden of demonstrating that the Public Utilities Commission’s decision is against the manifest weight of the evidence or is clearly unsupported by the record—Orders affirmed. (No. 2014-0008—Submitted May 11, 2021—Decided July 8, 2021.) APPEAL from the Public Utilities Commission of Ohio, No. 07-905-EL-CSS. __________________ FISCHER, J. {¶ 1} Appellant, Allied Erecting & Dismantling Co., Inc. (“Allied”), appeals from orders of appellee, Public Utilities Commission, requiring Allied to pay for electricity consumed during an almost three-year period in which SUPREME COURT OF OHIO

intervening appellee, the Ohio Edison Company, failed to bill Allied for one of its electric meters. Ohio Edison estimated the amount owed based on Allied’s historical electricity usage, and the commission found that Ohio Edison had provided sufficient evidence to support the accuracy of its estimates. On appeal, Allied primarily argues that the commission failed to enforce a provision in Ohio Edison’s tariff regarding estimated billing. For the reasons explained below, we hold that Allied has failed to demonstrate reversible error. We therefore affirm the commission’s orders. I. FACTUAL AND PROCEDURAL BACKGROUND A. Allied’s complaint against Ohio Edison {¶ 2} Allied is an industrial contractor with a 250-acre facility in Youngstown, Ohio. In December 2003, a motor-vehicle accident destroyed one of Allied’s six electric meters at its Youngstown facility. When Ohio Edison replaced the damaged meter, it mistakenly deleted one of Allied’s other, undamaged meters from Ohio Edison’s internal billing system. Although the deleted meter was functional and remained physically accessible at Allied’s facility, Ohio Edison did not read the meter or bill Allied for the electric usage recorded by that meter. In June 2006, Ohio Edison discovered its error, and after an internal investigation, it calculated Allied’s back bill for the unbilled period—from February 2004 to January 2007—to be $94,676.58. {¶ 3} In January 2007, Ohio Edison sent Allied the back bill. Allied was surprised by the amount due and later filed a complaint with the commission pursuant R.C. 4905.26. Allied requested (1) an explanation of the error, (2) an explanation of the back-bill calculation considering Ohio Edison’s failure to read the meter for a 2.5-year period, (3) protection against an unwarranted assessment of interest and late fees, and to the extent that any amount is due, (4) an appropriate payment plan. B. The conflicting evidence adduced at the hearing

2 January Term, 2021

{¶ 4} The commission held a two-day hearing on Allied’s complaint. Ohio Edison presented Lisa Nentwick, a senior account manager, to testify about how she had calculated Allied’s back bill. Nentwick explained that when Ohio Edison cannot obtain an actual reading of a meter, it will estimate a customer’s bill based on at least two years of the customer’s historical electric usage. According to Nentwick, there are two ways to estimate usage based on historical data: (1) taking the lowest usage for each corresponding month from the previous two years or (2) calculating an average usage from the corresponding months from the two previous years. {¶ 5} Regarding Allied’s bill, Nentwick testified that actual readings were unavailable from February 2004 to June 2006 because the meter was not in Ohio Edison’s billing system. Therefore, she had had to estimate usage for each of those months. To calculate the estimated usage, Nentwick used a combination of the two methods described above. For the first 12 months of the unbilled period, she used the lowest usage amount for the corresponding month from the two previously available years. For example, to calculate Allied’s bill for June 2004, she examined Allied’s usage in June 2002 and June 2003 and took the lower of those two numbers. For the other months, Nentwick used the average of the usage for that month from the two previously available years. After the discovery of Ohio Edison’s error in June 2006, Nentwick took actual readings from the meter for June, July, and August 2006, but estimated usage for the four remaining months in 2006. Ohio Edison entered Nentwick’s estimated readings and the three actual readings into its billing system, which generated Allied’s back bill of $94,676.58. {¶ 6} Allied presented Douglas Hull, who testified that Ohio Edison’s estimates and calculations were unreliable and flawed. Hull, a retired Ohio Edison employee, explained that the type of meter at issue here gets reset only when actual readings are taken. Hull claimed that because Ohio Edison had not read the meter in question from February 2004 to June 2006, the meter had not been reset for 28

3 SUPREME COURT OF OHIO

months. And because the meter had not been reset, Hull testified, the first reading in June 2006—which was 38 kW—must have been the single high for the previous 28 months. Therefore, according to Hull, the demand for each of the previous 28 months should have been equal to or less than 38 kW a month. Hull concluded that because Nentwick’s estimates ranged from 77 kW to 100 kW a month, she had disregarded the actual reading of the meter and overstated the amount of Allied’s back bill. {¶ 7} Nentwick acknowledged that Ohio Edison’s first reading after discovering its error was 38 kW and that it used that actual reading to calculate Allied’s monthly charge for June 2006. But she further testified that the 38 kW reading was not a reliable number to use for any other month. According to Nentwick, the 38 kW reading was less than half of any other reading ever recorded by that meter and was likely a result of transcription error by the meter reader or the meter “turn[ing] over” or resetting during the unbilled period. C. The commission’s order {¶ 8} In its September 2013 opinion and order, the commission first found that Ohio Edison had violated Ohio Adm.Code 4901:1-10-05(I) by failing to obtain actual readings of all its meters at least once each calendar year. Because Ohio Edison violated this regulation, the commission ordered it to conduct an internal review of its metering operations and policies and file a report of its findings within 90 days of the commission’s order. {¶ 9} Notwithstanding Ohio Edison’s violation of the administrative rule, the commission also found that (1) Ohio Edison had provided sufficient evidence supporting the accuracy of the estimates in the back bill and (2) Allied had not sustained its burden in proving that Ohio Edison’s estimates were unreasonable. Accordingly, the commission ordered that Ohio Edison establish a 36-month payment plan for Allied to pay the back bill, with no interest or late fees. After the

4 January Term, 2021

commission denied Allied’s application for rehearing, Allied appealed to this court. Ohio Edison intervened as an appellee. D.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monongahela Power Co. v. Public Utilities Commission
2004 Ohio 6896 (Ohio Supreme Court, 2004)
Grossman v. Public Utilities Commission
214 N.E.2d 666 (Ohio Supreme Court, 1966)
Norman v. Public Utilities Commission
406 N.E.2d 492 (Ohio Supreme Court, 1980)
Constellation NewEnergy, Inc. v. Public Utilities Commission
104 Ohio St. 3d 530 (Ohio Supreme Court, 2004)
Ohio Consumers' Counsel v. Public Utilities Commission
114 Ohio St. 3d 340 (Ohio Supreme Court, 2007)
Ohio Partners for Affordable Energy v. Public Utilities Commission
115 Ohio St. 3d 208 (Ohio Supreme Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2021 Ohio 2300, 180 N.E.3d 1063, 165 Ohio St. 3d 510, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-complaint-of-allied-erecting-dismantling-co-inc-v-ohio-edison-ohio-2021.