In Re Barlow

631 A.2d 853, 160 Vt. 513, 1993 Vt. LEXIS 74
CourtSupreme Court of Vermont
DecidedAugust 13, 1993
Docket91-491
StatusPublished
Cited by25 cases

This text of 631 A.2d 853 (In Re Barlow) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Barlow, 631 A.2d 853, 160 Vt. 513, 1993 Vt. LEXIS 74 (Vt. 1993).

Opinions

Dooley, J.

Petitioners Robert and Barbara Barlow appeal a

ruling by the Vermont Environmental Board requiring them to [516]*516obtain an Act 250 permit to continue operating their gravel pit. They argue that their operation is exempted from review by 10 V.S.A. § 6081(b) because it preexisted the enactment of Act 250. The State has moved to dismiss this appeal, contending that the action is moot because petitioners have now received a permit. We deny the State’s motion to dismiss and affirm the Board’s decision that petitioners’ gravel operation is not exempt from the Act 250 permit requirements.

The land now known as the Barlow gravel pit was purchased in 1959 by Joseph and Martha Sarkis. At that time, the lot consisted of a 122-acre parcel on Dean Road in the Town of Pownal. Some years later, portions of the lot were sold, including a four-acre lot now owned by Harriet Burdick.

Gravel extraction on the parcel occurred as early as 1940. Prior to 1970, gravel extraction occurred only on the eastern portion of the lot, while sand and dirt, but no gravel, were extracted from the western portion. The owners did not operate the gravel pit; independent contractors such as John W. Patterson, Sr. and the Town of Pownal worked the pit and paid the owners for the gravel they removed. Exact records were not maintained, and the most reliable source regarding the extraction of gravel from the pit is Patterson, who took gravel from the property from 1966 through 1978. The Board accepted Patterson’s testimony that the annual extraction rate from 1966 through 1970 ranged between 5,800 and 11,200 cubic meters of gravel, sand, and sand and dirt fill, and that the pit was not used on a daily basis. The extraction rate remained approximately the same for the years 1970 through 1977.

In 1978, Harwood and Lauretta Moore purchased the property. In May 1978, the district coordinator for the District 8 Commission issued to the Moores a project review sheet that stated: [517]*517From 1978 to 1982, the Moores increased the extraction rate to approximately 26,000 cubic yards per year. In addition, the gravel extraction operation was extended to the western portion of the property because the eastern portion was nearly exhausted.

[516]*516(Tentative as of 5-18-78) Purchase of existing continuously used gravel pit from Joseph Sarkis for identical use by Harwood D. Moore. Currently 2+ acres are opened and possibly up to 15-20 acres of the 100 contain saleable earth resource. New owner would probably be removing 100-200 [cubic yards] per day for sale in Massachusetts. No [Act 250] permit required unless operation substantially changes.

[517]*517In 1983, petitioners purchased the western portion of the parcel, as gravel extraction had ceased on the eastern portion of the land the previous year. They continued gravel extraction on the western portion and extracted from 14,727 to 55,562 cubic yards per year between 1983 and 1990, averaging approximately 26,000 cubic yards per year. Petitioners have operated the pit on a daily basis.

The gravel pit on the western portion has expanded over the years to comprise an approximately nine-acre area, and now has approached to within 150 feet of the Burdick land. As a result, pit operations have become more audible to the residents of that property. Petitioners plan to continue gravel extraction at the same average rate of 26,000 cubic yards per year that they maintained during the 1980s.

While applying for a waste disposal permit, petitioners were advised to discover whether they were required to obtain an Act 250 permit. They did so and initially were told they did not need a permit. On June 14,1989, the district coordinator reconsidered and determined that a permit was required. The Board’s executive officer affirmed this determination.

Petitioners appealed, and the Environmental Board affirmed. It found that there had been three changes in the gravel pit operation: (1) petitioners used a portable stone crusher where none had been used before; (2) the annual extraction rate had greatly increased since 1970; and (3) the frequency of gravel extraction had increased, from a sporadic undertaking to a daily occurrence. It found that the latter two changes were “substantial” and triggered the need for a permit. See 10 V.S.A. § 6081(b) (“any substantial change” to preexisting development triggers Act 250 jurisdiction). It explained its rationale as follows:

In making this determination, the Board is examining not whether the impacts actually exist, but whether they potentially exist. The Board is only evaluating whether a permit is required because of the potential for significant [518]*518impacts, and it is for the District #8 Commission, following submission of a permit application, to review the projects impacts in deciding whether to issue a permit.

(Emphasis in original.) The Board also rejected petitioners’ argument that it was estopped from finding Act 250 jurisdiction because petitioners reasonably relied on the 1978 project review sheet.

After commencing of this appeal, petitioners applied for and were granted an Act 250 permit for their gravel operation, subject to specified conditions. The State has moved to dismiss this appeal, claiming that the permit renders it moot.

Before addressing the merits, we must determine whether this appeal is moot.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Geromy Wells
2025 VT 5 (Supreme Court of Vermont, 2025)
NE Materials Group, LLC Act 250
Vermont Superior Court, 2015
In re North East Materials Group LLC Act 250 JO 5-21
199 Vt. 577 (Supreme Court of Vermont, 2015)
Dorr Earth Extraction
Vermont Superior Court, 2015
N.E. Materials Group LLC
Vermont Superior Court, 2014
In re Hale Mountain Fish & Game Club, Inc.
2007 VT 102 (Supreme Court of Vermont, 2007)
In re Vermont RSA Ltd. Partnership
2007 VT 23 (Supreme Court of Vermont, 2007)
In Re Vermont Rsa Limited Partnership
2007 VT 23 (Supreme Court of Vermont, 2007)
In Re Appeal of S-S Corp./Rooney Housing Developments
2006 VT 8 (Supreme Court of Vermont, 2006)
In Re Lyon
2005 VT 63 (Supreme Court of Vermont, 2005)
Appeal of County of Windsor (Fence)
Vermont Superior Court, 2003
In Re White
779 A.2d 1264 (Supreme Court of Vermont, 2001)
Sisters & Bros. Investment Group v. Vermont National Bank
773 A.2d 264 (Supreme Court of Vermont, 2001)
In Re Appeals of Letourneau
726 A.2d 31 (Supreme Court of Vermont, 1998)
LaFrance v. Environmental Board
706 A.2d 957 (Supreme Court of Vermont, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
631 A.2d 853, 160 Vt. 513, 1993 Vt. LEXIS 74, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-barlow-vt-1993.