In re Authorization for Freshwater Wetlands Statewide General Permit 6

80 A.3d 1132, 433 N.J. Super. 385
CourtNew Jersey Superior Court Appellate Division
DecidedSeptember 9, 2013
StatusPublished
Cited by14 cases

This text of 80 A.3d 1132 (In re Authorization for Freshwater Wetlands Statewide General Permit 6) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Authorization for Freshwater Wetlands Statewide General Permit 6, 80 A.3d 1132, 433 N.J. Super. 385 (N.J. Ct. App. 2013).

Opinion

The opinion of the court was delivered by

WAUGH, J.A.D.

In these consolidated actions, appellants Residents for Enforcement of Existing Land Use Code, Susan Tierney, and the Pond Run Watershed Association appeal several administrative decisions by respondent New Jersey Department of Environmental Protection (Department) in connection with its grant of a general [389]*389freshwater wetlands permit and transition area waivers to respondent Care One, Inc. (CareOne), which seeks to expand its assisted living facility in Hamilton Township. We dismiss the appeal in Docket No. A-3400-10 as interlocutory. We affirm the administrative agency action in Docket No. A-3837-09, and reverse the administrative agency actions in Docket No. A-2231-08. Finally, we remand for further proceedings consistent with this opinion.

I.

We discern the following facts and procedural history from the record on appeal.

In 1999, the Department granted CareOne a freshwater wetlands permit to fill 0.97 acres of isolated wetlands and to create a stormwater management basin, also known as a detention basin,1 for construction of an assisted living facility on approximately seven acres in Hamilton Township, Mercer County. The facility, known as CareOne at Hamilton, is located on the northern corner of the intersection of Cypress Lane and Whitehorse-Hamilton Square Road. A 0.47 acre portion of the permitted area was left undisturbed.

In 2007, CareOne wanted to construct a two-story, 62,259 square foot addition, as well as a paved parking lot. The proposed construction would require the filling of the existing detention basin and other wetlands on the site, and the construction of a new, L-shaped detention basin along Cypress Lane.

In April, CareOne submitted a combined application for a “Letter of Interpretation” (LOI) to delineate the site’s freshwater wetlands and a “Freshwater Wetlands Statewide General Permit No. 6” (GP6), see N.J.A.C. 7:7A-5.6, to fill the undisturbed segment of the land covered by the 1999 permit, or 21,800 square feet (0.5 of an acre) of freshwater wetlands, and to disturb an addition[390]*390al 35,906 square feet (0.82 of an acre) of the adjoining transition area.2

According to CareOne, the nearest waterway to the site is Pond Run. The affected onsite wetlands were isolated and of intermediate resource value, requiring an adjacent transition area of fifty feet. No bog turtle populations would be impacted and “no flood hazard permit was required,” because no activities were proposed within the flood hazard area or riparian zones.

CareOne’s application package contained, among other documents: (1) a March 2007 “Statement of Compliance” by its licensed professional engineers, Taylor Wiseman & Taylor (TWT), which included a “Freshwater Wetlands Delineation Report”; (2) grading and groundwater recharge plans, maps, soil boring logs, vegetative and hydrological analyses, photographs, and a description of the onsite vegetative species; (3) two stormwater management reports by TWT dated March 2007, “Drainage and Detention Calculations,” and “Detention Facilities Operation and Maintenance Manual”; and (4) a March 2007 preliminary and final site plan. CareOne also provided the required notice of its project to Hamilton Township and landowners within 200 feet of the site. The Department published notice of the applications in the DEP Bulletin on May 2, 2007.

In March 2008, CareOne responded to the Department’s request for additional information by submitting (1) hydrographs, including inflow and outflow hydrographs of the existing and proposed basins for the two-, ten-, twenty-five-, and hundred-year storms; (2) calculations and diagrams for two recharge areas, one each in the front and rear of the building, showing that they both would drain within the Department’s required seventy-two-hour limit; (3) existing and proposed flow charts, and drainage area and grading maps; (4) a February 2008 revision of TWT’s “Drainage [391]*391and Detention Calculations”; and (5) a February 2008 revision of TWT’s “Detention Facilities Operation and Maintenance Manual.”

CareOne’s proposed stormwater management plan included (1) the new detention basin designed to meet the two-year, ten-year, and hundred-year storm flow estimates and to “dry out” within the seventy-two-hour time limit required by the Department; (2) two recharge areas with VortSentry® treatment devices to manage stormwater quality by removing the total suspended solids (TSS) in any runoff within 17.3 hours; (3) two “StormChambers” to meet infiltration or groundwater recharge estimates; and (4) an “Emergency Spillway” that would convey any flows from a hundred-year storm.

While the Department’s staff was reviewing CareOne’s application and submissions, CareOne applied to the Hamilton Township Zoning Board of Adjustment (Zoning Board) for use and site plan approvals and bulk variances for its project. On June 9, 2009, the Zoning Board voted to deny CareOne’s request for site plan approval with bulk variances. The decision is not in the record. CareOne did not appeal the Zoning Board’s denial.

In a May 8, 2008 internal “Engineer’s Report for SWM [storm-water management] review,” the Department’s staff recommended “approval,” concluding that “[t]his project is in conformance with all of the engineering aspects of the Stormwater rules.” The staff also (1) determined that the “[ojverall proposed land disturbance is more than 1 acre and new impervious area is more than 1/4 acre, therefore review of stormwater management was required for this project”; (2) found that CareOne’s submitted Nonstructural Strategies Points System (NSPS) spreadsheet had been “completed correctly”; (3) “accepted” CareOne’s calculations that its proposed TSS removal plans of an extended detention basin and two water quality treatment devices to treat any runoff from the new parking lot and sidewalks, and from the pre-existing impervious area, would remove approximately seventy-four percent of TSS; (4) noted that CareOne had proposed two recharge chambers, or bio-retention swales, to provide the required recharge [392]*392volume within seventy-two hours; and (5) found that stormwater flows would be “further reduced due to Bio[s]wales.”3 Finally, the staff approved the drawings that CareOne had submitted, including CareOne’s overall site plan, grading plan, utility plan, and construction details.

On June 19, CareOne submitted a separate application to the Department for a “Special Activity Transition Area for Stormwater Management.” The application, which included a June 2008 version of TWT’s “Statement of Compliance,” concerned proposed construction on a section of CareOne’s property that was part of the transition area associated with freshwater wetlands on the other side of Whitehorse-Hamilton Square Road. Because the offsite wetlands were of exceptional resource value, they required a 150-foot transition area, which extended across the road onto CareOne’s property.4 CareOne provided the required notice to Hamilton Township and adjacent landowners.

Objectors, including appellants and other property owners living in the adjacent Society Hill community, opposed CareOne’s proposal. Their major concerns centered on stormwater management and local flooding risks. The Department assured them that their concerns would be considered before any approvals were given.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In the Matter of Flood Hazard Area Verification, Etc.
New Jersey Superior Court App Division, 2024
In the Matter of Permit
New Jersey Superior Court App Division, 2023
Twp. of Bordentown v. Fed. Energy Regulatory Comm'n
903 F.3d 234 (Third Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
80 A.3d 1132, 433 N.J. Super. 385, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-authorization-for-freshwater-wetlands-statewide-general-permit-6-njsuperctappdiv-2013.